RAJIV LIFT IRRIGATION SCHEME (BHIMA) - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

RAJIV LIFT IRRIGATION SCHEME (BHIMA)

Description:

Investigation, design, estimation and execution for convesting the existing ... Under Sangambanda BR, RAJIV LIFT IRRIGATION ... Only) against Rs. 70.80 Crs. ... – PowerPoint PPT presentation

Number of Views:2358
Avg rating:3.0/5.0
Slides: 19
Provided by: rgo57
Category:

less

Transcript and Presenter's Notes

Title: RAJIV LIFT IRRIGATION SCHEME (BHIMA)


1
RAJIV LIFT IRRIGATION SCHEME (BHIMA)
1 Project Profile Project Profile Lifting of 20 tmc of water from foreshore of PJP and Ookachettivagu Project Pondage
2 Administrative Sanction Administrative Sanction G. O. Ms. No. 166, I CAD, Dt 30-10-2003 for Rs. 1426.30 Crores
3 No. of EPC Packages 13 Nos. No. of EPC Packages 13 Nos. No. of EPC Packages 13 Nos. No. of EPC Packages 13 Nos.
4 Agt. Value of 13 Pkgs Agt. Value of 13 Pkgs Rs. 1417.92Crs.
5 Budget Provision for 2006-07 Rs. 193.20 Crs.
6 Expenditure
2004-05 2004-05 Rs. 108.68 Crs. (Incl. Sangambanda BR)
2005-06 2005-06 Rs. 238.50 Crs.
TOTAL Rs. 347.18 Crs.
7 Utilisation 20 TMC
8 Ayacut New Ayacut 2,03,000 Acres
Stabilization 4,000 Acres
2
RAJIV LIFT IRRIGATION SCHEME (BHIMA)
9 Lift-I
Lift Height 67 M
No. of Pumps 6 Nos.
Total pumps capacity 48 MW
10 Lift-II
Lift Height 61 M
No. of Pumps 6 Nos.
Total pumps capacity 48 MW
11 Total Power required Total Power required 96 MW
3
RAJIV LIFT IRRIGATION SCHEME (BHIMA)
12 Land Acquisition
Required 21,641 acres
Acquired 8,278 acres
Requisitioned 13,000 acres
13 Est. Cost for LA Rs. 120 Crs.
14 Est. Cost for R R Rs. 40 Crores
15 Mobilisation Advance Paid Recovered
2004-05 62.57 Crs -
2005-06 22.10 Crs. 14.99 Crs.
Total Rs. 84.78 Crs. Rs.14.99 Crs.
16 Target date for completion 9/2007
4
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
PKG No. Description Awarded Bid Amount Rs. in Crs.
13 Excavation of High level right main canal, distributary system including construction of CM CD works from Sangambanda BR to feed ayacut of 18400 Acres. M/s. R.M.M. BRC (JV) 57.97
14 Excavation of High level left main canal, distributary system including construction of CM CD works etc. to feed an ayacut of 35,800 Ac. Under Sangambanda BR M/s. VPR-Cromandal (JV) 68.94
15 Investigation, design, estimation and excavation of canal distributary system including construction of CM CD works from Yenukunta BR, Waddewata (V), Kottakota (M), Mahabubnagar (D) to feed about 14,000 Acres upto Rangasamudram BR. M/s. Prathibha-Ch MR (JV) 51.270
16 Excavation of canal distributary system including constrction of CM CD works from Ranga Samudram to feed an ayacut of 21,000 Acres M/s. RNS-GSR CO (JV) 70.800
17 Investigation, design, estimation and execution for converting the existing Rangasamudram tank, near Sri Rangapuram (V) Pebbair (M), Mahabubnagar district as balancing reservoir under Bhima Lift Irrigation Project (Lift-II) M/s. ALS-KVR (JV) 41.540
18 Investigation, design, estimation and execution for convesting the existing Shankarasamudram tank, near Knaipally (V) Kothakota (M), Mahabubnagar district as balancing reservoir under Bhima Lift Irrigation Project (Lift-II) M/s. Sri Avanthi Saivenkata (JV) 42.100
CATEGORY-II
5
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Pkg No. Description Awarded Bid Amount Rs. in Crs.
19 Shankara Samudram Balancing Reservoir Right Main canal. M/s. G.H. Reddy Associate K.K.R Co (JV) 36.90
20 (i) Formation of Earth Dam with FRL 352m (ii) Construction of spillway, (iii) Construction of Head Regulator to let out into left and right main canals. Budpur Balancing Reservoir M/s. KNR-SLEC (JV) 36.98
21 Investigation, Designs and excavation of left main canal, distributary system including construction of CM CD works from budpur Balancing reservoir, Budpur (V), Atmakur (M), Mahabubnagar (D) to feed about 32,000 Acres M/s. S.V.E.C. Co., 60.39
22 Investigation, Designs and excavation of right main canal, distributary system including construction of CM CD works from budpur Balancing reservoir, Budpur (V), Atmakur (M), Mahabubnagar (D) to feed about 32,000 Acres M/s. S.V.E.C. Co., 26.73
27 Investigation, Design, excavation of left main canal, distributary system including construction of CM CD works from Sankarsamudam Balancing Reservoir . M/s. KNR Const. Ltd. BPL (JV) 149.40
OC LIFT-I Design, manufacture, supplying erection of pumps, motors, electro mechanical works, including tunnel, cistern and pump house etc. M/s. Patel Engg. Ltd. 383.349
OC Design and execution of Stage-I and stage-II pumping stations of LIFT-II at Thirumalayapalli Kothakota (M), Mahabubnagar (D) on EPC basis. M/s. NEC-NCC-MAYTAS (JV) 391.55
TOTAL 1417.919
CATEGORY-II
6
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor M/s R.M.M BRC (JV)
Agreement Amount Rs. 57.97Crs. Agreement
Date 03-03-2005 Period of Completion 24
Months (8 milestones) Date of completion
03-03-2007
Package No. 13/Cat-II Excavation of High level
right main canal, distributary system including
construction of CM CD works from Sangambanda BR
to feed ayacut of 18400 Acres.
  • Investigation completed Completed
  • Designs 9.2 KM approved against 24 KM
  • Execution (Main canal) 15 KM length in progress
    against total length of 24.00KM
  • Qty. of earth work done 6.00Lakh Cum against
    37.32 Lakh Cum.
  • Qty. of concrete work done 500 cum against 3500
    cum
  • No. of Machinery Deployed 15Nos (Excavators
    2 Nos.,Tipper-8Nos., T Roller- 2Nos., Dozers
    1 Nos., Water tank -1No.Crushing plant-1No.)
  • Land Acquisition Required 1000 Acres,
    Requisition 260 acres, Acquired 81 acres
  • Expenditure Rs. 14.90 Crs. against Rs. 57.97
    Crs.,
  • Mob. Adv. Paid Rs. 2.90 Crs.
  • Mob. Adv. Recovered Rs. 2.90 Crs.
  • Bottlenecks Land Acquisition

7
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor M/s VPR Coromandal
(JV) Agreement Amount Rs. 68.94Crs. Agreement
Date 05-03-2005 Period of Completion 24
Months (8 milestones) Date of completion 24-02-20
07
Package No. 14/Cat-II Excavation of High level
left main canal, distributary system including
construction of CM CD works etc. to feed an
ayacut of 35,800 Ac. Under Sangambanda BR,
  • Investigation Completed (40.645 KM)
  • Designs Main canal completed (40.465 KM)
  • Execution (main canal) 28.75KM length in
    progress against total length of 40.645 KM
  • Qty. of earth work done 18 Lakh Cum against
    26.20 Lakh Cum.
  • Qty. of concrete work done 1500 cum
  • No. of Machinery Deployed 29Nos

    (Excavators 6 Nos.,
    Dozers 2 Nos, Tippers 21Nos. etc)
  • Expenditure Rs. 29.88 Crs. against Rs. 68.94
    Crs.,
  • Mob. Adv. Paid Rs. 6.88 Crs.
  • Mob. Adv. Recovered Rs. 1.68 Crs.
  • Land Acquisition Required 1867 Acs, Requisition
    651 Acquired 205.54 Acres

8
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. 15/Cat-II Investigation, design,
estimation and excavation of canal distributary
system including construction of CM CD works
from Yenukunta BR, Waddewata (V), Kottakota (M),
Mahabubnagar (D) to feed about 14,000 Acres upto
Rangasamudram BR.
Name of the Contractor M/s Prathibha Ch MR-
(JV) Agreement Amount Rs. 51.27 Crs.
Agreement Date 05-03-2005 Period of
Completion 24 Months (8 milestones) Date of
completion 05-03-2007
  • Investigation Completed (30.25 KM)
  • Design 26.75 KM approved against 30.25 KM
  • Execution (main canal) 13 KM length in progress
    against total length of 30.25 KM
  • Qty. of earth work done 5,70,000 Cum against
    20,00,000 Cum
  • No. of Machinery Deployed 28Ns (Excavators
    6 Nos., Tippers20Nos, Leveller 2No.)
  • Land Acquisition Required 943 Acres,
    Requisition 407Acs. Acquired 218.71Acs.
  • Expenditure Rs. 8.12 Crs. (Inc. Mob. Adv. Rs.
    5.12 Crs.) against Rs. 51.27 Crs.

9
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor M/s RNS-GSR Co.
(JV) Agreement Amount Rs. 70.80Crs Agreement
Date 02-03-2005 Period of Completion 24
Months (8 milestones) Date of completion
02-03-2007
Package No. 16/Cat-II Excavation of canal
distributary system including construction of
CM CD works from Ranga Samudram to feed an
ayacut of 21,000 Acres.
  • Investigation (HPs) Length 58Kms finalised
    against 81Kms
  • Execution Excavation in 1.5 KM length in
    progress against total length of 81.00 KM
  • Qty. of earth work done 10,000 Cum against
    16,00,000 Cum
  • No. of Machinery Deployed 15 Nos
    (JCB-1No.Excavators 4 Nos, Tippers-2Nos,
    S.Crushers- 2Nos, Hard top jeep-4Nos)
  • Expenditure Rs. 3.54Crs. (Mob. Adv. Only)
    against Rs. 70.80 Crs.
  • Land Acquisition Required 1415 Acres,
    Requisition 162.34Acres Acquired Nil
  • Bottle Necks Land Acquisition

10
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. 17/Cat-II Investigation, design,
estimation and execution for converting the
existing Rangasamudram tank, near Sri Rangapuram
(V) Pebbair (M), Mahabubnagar district as
balancing reservoir under Bhima Lift Irrigation
Project (Lift-II)
Name of the Contractor M/s A L S-KVR(JV)
Agreement Amount Rs. 41.50 Crores Agreement
Date 07-03-2005 Period of Completion 24
Months (8 milestones) Date of completion
07-03-2007
  • Investigation Completed
  • Designs (Earth Bund Weir) 80 approved
  • Execution Started
  • Qty. of earth work done Cut off trench
    excavated for a length of 1.50 KM
  • Expenditure Rs. 2.08 Crs. (Mob. Adv. Only)
    against Rs. 41.50 Crs.
  • Land Acquisition Required 2452.30Acres, Requi.
    2526.11Acrs Acquired Nil
  • Bottle Necks Land Acquisition

11
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. 18/Cat- Investigation, design,
estimation and execution for convesting the
existing Shankarasamudram tank, near Knaipally
(V) Kothakota (M), Mahabubnagar district as
balancing reservoir under Bhima Lift Irrigation
Project (Lift-II)
Name of the Contractor M/s Sri Avanthika
Saivenkata (JV) Agreement Amount Rs. 42.10
Crores Agreement Date 14-03-2005 Period of
Completion 24 Months(8 Mile Stones) Date of
completion 14-03-2007
  • Investigation Completed (3.69 KM)
  • Designs (Earth bund Weir) 80 of designs
    approved.
  • Execution Yet to start (Water in the Tank
    objections of Kanepally (V) for want of
    inclusion of village in R R Package.
  • Expenditure Rs. 2.11 Crs. (Mob. Adv. only)
    against Rs. 42.10 Crs.
  • Land Acquisition Required 2220 Acres,
    Requisitioned 1491Ac. Acquired 1436 acres

12
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Name of the Contractor M/s G. H. Reddy
Associates K.K.R Co. (JV), Agreement
Amount Rs. 36.90 Crores Agreement Date
19-02-2005 Period of Completion 24 Months
(Milestones 8)
Package No. 19/Cat-II Shankara Samudram
Balancing Reservoir Right Main canal.
  • Investigation Completed (39 KM)
  • Designs (HPs Structures) approved
  • Execution 34 KM length in progress against
    total length of 39 KM
  • Qty. of earth work done 5.5 Lakh Cum against 6
    Lakh Cum.
  • Qty. of concrete work done 2500 cum against
    30,000 cum
  • Structure 25 Nos. executed against 110 Nos.
  • Expenditure Rs. 16.68 Crs. against
    36.79Crores
  • Mob. Adv. Paid Rs. 3.68 Crs.
  • Mob. Adv. Recovered Rs. 0.70 Crs.
  • Land Acquisition Required 800 Acres,
    Requisitioned 459 Acs Acquired 236 acres

13
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. 20/Cat- (i) Formation of Earth Dam
of Budpur with FRL 352m (ii) Construction of
spillway, (iii) Construction of Head Regulator to
let out into left and right main canals.
Name of the Contractor M/s KNR-SLEC (JV),
Hyd. Agreement Amount Rs. 36.98Crs Agreement
Date 07-03-2005 Period of Completion 24
Months (8 milestones)
  • Investigation Completed (6.10 KM)
  • Designs Approved
  • Execution Qty. of earth work 5.64 Lakh cum
    completed.
  • Expenditure Rs. 15.43 Crs. (Inc. Mob. Adv.
    Rs. 3.43 Crs.) against Rs. 36.98Crs.
  • Mob. Adv. Recovered Rs. 1.37 Crs.
  • Machinery deployed Excavator-1No.,
    Tippers-5No., Dozer-1No., Other M/C-7Nos.
  • Land Acquisition Required 2073.11 Acres,
    Requisitioned- 2073.11 Acs Acquired 358Acs.

14
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. 21/Cat-II Investigation, Designs
and excavation of left main canal, distributary
system including construction of CM CD works
from budpur Balancing reservoir, Budpur (V),
Atmakur (M), Mahabubnagar (D) to feed about
32,000 Acres
Name of the Contractor M/s S.V.E.C Co.,
Hyd. Agreement Amount Rs. 60.39
Crores Agreement Date 25-02-2005 Period of
Completion 24 Months (milestones)
  • Investigation completed (32 KM)
  • Designs (HPs Structures) Length 28.65 Km
    approved against 37.825Kms.
  • Execution (Canal) 28.10 KM length in progress
    against total length of 37.825KM
  • Structures 13 Nos. executed against 79 Nos.
  • Machinery deployed 10Nos. (Tippers-4Nos,
    Poclains-4Nos, DRR-1No,Dozer-1No.)
  • Land Acquisition Required 1386 Acres,
    Requisitioned 316Acs Acquired 98 Acs.
  • Expenditure Rs. 18.04 Crs. (inc. mob. Adv. Rs.
    6.04 Crs.) against Rs. 60.39 Crs.
  • Bottle necks Land acquisition not handed over
    by Revenue authorities

15
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. 22/Cat- Investigation, Designs and
excavation of right main canal, distributary
system including construction of CM CD works
from budpur Balancing reservoir, Budpur (V),
Atmakur (M), Mahabubnagar (D) to feed about
32,000 Acres
Name of the Contractor M/s S.V.E.C Co.,
Hyd. Agreement Amount Rs. 26.73
Crores Agreement Date 25-02-2005 Period of
Completion 24 Months (8 milestones)
  • Investigation Completed (15.025 KM)
  • Design (HPs) Approved
  • Execution (Canal) 14.50 KM length in progress
    against total length of 15.025KM
  • Qty. of earth work done 2.86 Lakh cum against
    2.95 Lakh cum
  • Qty. of concrete work done 5200 cum
  • Structures 23 Nos. executed against 54 Nos.
  • Expenditure Rs. 14.68 Crs. (Inc. Mob. Adv.
    Rs. 2.68 Crs.) against Rs. 26.73 Crs.
  • Mod. Adv. Recovered Rs. 0.73 Crs.
  • Machinery deployed 13Nos. (Tippers-4Nos,
    Poclains-7Nos, DRR-1No,Dozer-1No.)
  • Land Acquisition Required 354 Acres,
    Requisitioned 212Acres Acquired 128 Acs.
  • Bottlenecks Land acquisition

16
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. OC (Pkg. 27) Investigation, Design,
excavation of left main canal, distributary
system including construction of CM CD works
from Sankarsamudam Balancing Reservoir .
Name of the Contractor M/s KNR Const. Ltd.
BPL (JV) Agreement Amount Rs.
149.40Crs. Agreement Date 9/2005
AGREEMENT DATE 9/2005
INVESTIGATION and DESIGNS are in PROGRESS
Financial Rs. 7.47 Crores (Mob. Adv. Only)
against Rs. 149.40 Crores
  • Land Acquisition
  • Required 3,000 Acs.
  • Requisitioned 169.95 Acs.
  • Acquired Nil

17
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. EPC / OC- LIFT-I Design,
manufacture, supplying erection of pumps,
motors, electro mechanical works, including
tunnel, cistern and pump house etc.
Name of the Contractor M/s Patel Engineering
Ltd. Agreement Amount Rs. 383.349Crores Agreeme
nt Date 07-03-2005 Period of Completion 30
Months (10 milestones)
  • Investigation Completed (3.0725 KM)
  • Designs (Tunnel, Pump House, Surge pool,
    Cistern) 2.70 KM approved against 3.0705
  • Execution Excavation in progress (approach
    channel, tunnel, surge pool Pump house)
  • Qty. of earth work done 5.50 Lakh Cum against
    7.82 Lakh Cum.
  • No. of Machinery Deployed 8 Nos (Excavators
    6 Nos., Dozers 2 Nos. etc)
  • Land Acquisition Required 250 Acres,
    Requisitioned 218Acs Acquired 111 Acs.
  • Expenditure Rs. 52.16 Crs. against Rs. 383.34
    Crs. (Mob. Adv paid Rs. 19.58 Crs.)
  • Mob Adv. Recovered Rs. 1.61 Crs.
  • Bottlenecks Land Acquisition

18
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT)
Package No. EPC / OC- Design and execution of
Stage-I and stage-II pumping stations of lift-II
at Thirumalayapalli Kothakota (M), Mahabubnagar
(D) on EPC basis.
Name of the Contractor M/s NEC NCC MAYTAS
(JV) Agreement Amount Rs. 391.55
Crores Agreement Date 14-03-2005 Period of
Completion 30 Months
  • Investigation Completed (3.132 Kms)
  • Designs (Tunnel, Pump House, Surge pool,
    Cistern) Approved
  • Execution Excavation 0.383Km in progress
    (approach channel, tunnel,
    surge pool Pump
    house)
  • Qty. of earth work done 1,70,000 Cum against 5
    Lakh Cum.
  • No. of Machinery Deployed 18 Nos (Excavators
    4 Nos., Dumpers 12 Nos., Dozers 2
    Nos. etc)
  • Land Acquisition Required 135 Acres,
    Requisitioned 67 Acs. Acquired Nil
  • Expenditure Rs. 71.58 Crs. against Rs. 391.55
    Crs.
  • Mob. Adv. Paid Rs. 19.58 Crores.
  • Mob. Adv. Recovered Rs. 6.00 Crores.
Write a Comment
User Comments (0)
About PowerShow.com