Available Transfer Capability Determination - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

Available Transfer Capability Determination

Description:

System Conditions. Critical Contingencies. Parallel Path Flows ... Second-Kick based Energy Margin Computation. Time Domain Simulation (ETMSP) System trajectory ... – PowerPoint PPT presentation

Number of Views:572
Avg rating:3.0/5.0
Slides: 32
Provided by: ECSE
Category:

less

Transcript and Presenter's Notes

Title: Available Transfer Capability Determination


1
Available Transfer Capability Determination
Third NSF Workshop on US-Africa Research and
Education Collaboration Abuja, Nigeria, December
13-15, 2004
  • Chen-Ching Liu and Guang Li
  • University of Washington

2
Overview
  • Background of Available Transfer Capability (ATC)
  • Definitions of ATC
  • Determination of ATC
  • Examples of ATC in Nigerian NEPA 330kV Grid
  • Optimization Technique to Calculate ATC
  • Stability-Constrained ATC Calculation Method
  • Conclusions

3
Background
  • ATC is the transmission limit for reserving and
    scheduling energy transactions in competitive
    electricity markets.
  • Accurate evaluation of ATC is essential to
    maximize utilization of existing transmission
    grids while maintaining system security.

4
Transmission Service Types
  • Recallable transmission service Transmission
    service that a transmission provider can
    interrupt in whole or in part.  
  • Non-recallable transmission service Transmission
    service that cannot be interrupted by a provider
    for economic reasons, but that can be curtailed
    for reliability.

5
ATC Under Operating Constraints
  • Transfer capability must be evaluated based on
    the most limiting factor.

6
Available Transfer Capability (ATC) (North
American Electric Reliability Council)
7
Definition of ATC
  • ATC TTC TRM Existing Transmission
    Commitments (including CBM)
  • Transmission Transfer Capability Margins
  • Transmission Reliability Margin (TRM)
  • Capacity Benefit Margin (CBM)

8
Transmission Reliability Margin (TRM)
  • Uncertainty exists in future system topology,
    load demand and power transactions
  • TRM is kind of a safety margin to ensure reliable
    system operation as system conditions change.
  • TRM could be 8 or 10 of the TTC

9
Capacity Benefit Margin (CBM)
  • CBM is reserved by load serving entities to
    ensure access to generation from interconnected
    systems to meet generation reliability
    requirements.
  • Intended only for the time of emergency
    generation deficiencies

10
State of the Art ATC Methods
11
First Contingency Incremental Transfer Capability
(FCITC) First Contingency Total Transfer
Capability (FCTTC)
FCITC
FCTTC
BASE POWER TRANSFERS
12
Total Transfer Capability (TTC)
  • System Conditions
  • Critical Contingencies
  • Parallel Path Flows
  • Non-Simultaneous and Simultaneous Transfers
  • System Limits

13
Procedure to Calculate TTC
  • Start with a base case power flow
  • Increase generation in area A and increase demand
    in area B by the same amount
  • Check the thermal, stability and voltage
    constraints.
  • Evaluate the first contingency event and ensure
    that the emergency operating limits are met.
  • When the emergency limit is reached for a first
    contingency, the corresponding (pre-contingency)
    transfer amount from area A to area B is the TTC.

14
Example 1 2-Area NEPA 330kV Grid
15
2-Area Base-Case Tie Flow
Single transmission line contingency
Notation
No thermal limit (assumed 120 base case flow)
reached
First thermal limit reached
4.64 MW
Tie Line Flow
21
23
Area 1
Area 2
16
Area 1 to Area 2 ATC Calculation
gt 4.64 MW
Increasing Generation DP MW
Increasing Demand DP MW
21
23
Area 1
Area 2
Increased Demand 0.32 MW
Increased Generation 0.32 MW
4.96 MW
7-25
21
23
2-8
FCTTC
Area 1
Area 2
FCITC
17
Area 2 to Area 1 ATC Calculation
lt 4.64 MW
Increasing Demand DP MW
Increasing Generation DP MW
21
23
Area 1
Area 2
Increased Generation 0.1 MW
Increased Demand 0.1 MW
4.54 MW
21
23
5-24
7-25
FCTTC
Area 1
Area 2
FCITC
18
2-Area ATC Calculation
Direction Area 1 to Area 2 Area 2 to Area 1
Critical Contingency Line 7-25 (Delta-Aladja) Line 7-25 (Delta-Aladja)
Thermal Limit Reached Line 2-8 (Jebba G.S.-Jebba T.S.) Line 5-24 (Alam-Aba)
FCTTC 4.96 MW ?4.54MW
FCITC 0.32 MW 0.1 MW
19
Example 2 4-Area NEPA 300kV Grid
AREA 1
AREA 3
AREA 2
AREA 4
20
4-Area Base-Case Tie Flows
Area 1
8.24 MW
8.5 MW
16.6 MW
4.64 MW
Area 4
Area 2
Area 3
21
Area 3 to Area 1 ATC calculation (Example of
Parallel Path Flows)
Area 1
FCTTC 9.1 8.65 17.75 MW FCITC 17.75 ? (8.5
8.24) 1.01 MW
Increased Demand 1.01 MW
8.65 MW
9.1 MW
17.2 MW
4.64 MW
1-7
7-25
Increased Generation 1.01 MW
Area 4
Area 2
Area 3
22
Area 4 to Area 2 Simultaneous ATC with a
Pre-existing Area 3 to Area 1 17.75 MW Transfer
Area 1
FCTTC ?16.99 ? (?17.2) 0.21 MW FCITC 4.85 ?
4.64 0.21 MW
8.65 MW
9.1 MW
Increased Generation 0.21 MW
16.99 MW
4.85 MW
4-10
Increased Demand 0.21 MW
7-25
Area 4
Area 2
Area 3
23
Optimization Technique to Calculate ATC
sum of generation in sending area A
Objective
- system dynamic behavior - power flow equations
Subject to
- active power output - thermal limit - voltage
profile - energy margin
24
Stability-Constrained ATC
25
Second-kick-based energy margin computation
Perform time-domain simulation
- Simulation
Obtain system trajectory following a
pre-specified disturbance sequence
- Trajectory
Compute potential energy of first- and
second-kick trajectories
- Potential energy
Potential energy difference at the respective
peaks of the first- and second-kick disturbances
- Energy margin
26
Energy margin sensitivity computation
  • Determine the search direction with the
    Broyden-Fletcher-Goldfarb-Shanno (BFGS) method

D is an approximation to the inverse of Hessian
matrix
27
Generation adjustment
- Adjustment
- Update
28
2-Area Test System
29
Stability-Constrained ATC Results
30
Conclusions
  • ATC provides a reasonable and dependable
    indication of available transfer capabilities in
    electric power markets.
  • ATC considers reasonable uncertainties in system
    conditions and provides operating flexibility for
    the secure operation of the interconnected
    network.
  • The effects of simultaneous transfers and
    parallel path flows are studied.
  • Need for ATC calculation method to incorporate
    voltage, angle stability limits as well as
    thermal limits.

31
References
  • 1 North American Electric Reliability Council,
    Available Transfer Capability Definitions and
    Determination, June 1996.
  • 2 North American Electric Reliability
    Council,Transmission Transfer Capability, May
    1995.
  • 3 S. K. Joo, C. C. Liu, Y. Shen, Z. Zabinsky
    and J. Lawarree, Optimization Techniques for
    Available Transfer Capability (ATC) and Market
    Calculations, IMA Journal of Management
    Mathematics (2004) 15, 321-337.
Write a Comment
User Comments (0)
About PowerShow.com