Production Readiness Review of - PowerPoint PPT Presentation

About This Presentation
Title:

Production Readiness Review of

Description:

... tension should be measured, for those panels carrying wires only on one side. ... New moulds (M2-3, M4-5) under construction (one ready by Christmas) ... – PowerPoint PPT presentation

Number of Views:55
Avg rating:3.0/5.0
Slides: 11
Provided by: pcam4
Category:

less

Transcript and Presenter's Notes

Title: Production Readiness Review of


1
Production Readiness Review of Frascati MWPC
Production Site
December 4th, 2003 P. Campana
2
  • Scope and Goals of the PRR
  • Verify / assess
  • Readiness of the chamber design and of the
    construction procedures
  • Readiness of the tooling and of the production
    site
  • Quality controls and assurance tests
  • Material procurement and its flow
  • Interface and integration issues
  • Chamber logistics
  • Manpower availability
  • Production and installation schedule

3
  • Status of LNF production site
  • In August, the set up of the clean room (transfer
    and set up of tooling)
  • In September-November startup of M3R3
    (pre)production 4 final chambers done (two more
    under construction)
  • 2 chambers tested under beam
  • choice between double and single cathode readout
  • test ASDQ vs Carioca
  • Several upgrades of the tooling done and to be
    done (automatic gluing, more HV bar gluing
    tables, etc...)
  • A lot of effort in finalizing QA/QC tests and in
    optimizing the work flow (this has still to
    improve)
  • The production speed was limited by material
    availability and to several operations we plan to
    do in outside company (e.g. components on HV bars)

4
  • EDR recommendations
  • A small pre-production series should be
    constructed and tested for each chamber type
  • The goal was to build and test 4 final chambers
    we succeeded in building them, but due to time
    shortage, and many other commitments (and a
    small accident), only 2 were (nearly) fully
    tested
  • 2. At least one of these pre-production chambers
    of each type should have undergone a successful
    ageing test
  • This has been done with LNF prototypes in
    Casaccia. This item has been discussed at length
    in CERN PRR and will be not treated here
  • 3. The opening of the chambers should be
    exercised. In fact, the reviewers are mostly
    worried about the proposal to close two of the
    three chamber types by gluing
  • This will be discussed later

5
  • A wire replacement procedure should be defined
    and tested for each chamber type.
  • This happened several times and will be
    explained in the afternoon
  • 5. At nominal gas flow rate, the eventual
    formation of pockets should be checked by
    efficiency mapping, especially in the case of the
    longest chamber type.
  • We did uniformity checks and no particular
    problems appeared
  • 6. As the gap size is probably the most critical
    parameter for pulse height uniformity, an effort
    should be made to produce panels of best possible
    flatness.
  • This will be reported later
  • 7. The sagitta of the panels due to wire tension
    should be measured, for those panels carrying
    wires only on one side.
  • Calculations and direct measurements show no
    sizeable effect

6
  • The precision of the wiring should be checked on
    all pre-production chambers.
  • This has been done for the pre-production
  • 9. Gluing should be handled with the utmost
    attention, with well tested, constant procedures,
    in particular under lt50 humidity
  • Does not represent a problem and its
    automatisation is under way
  • 10. Chamber materials and components (panels,
    bars, wires, glue, resistors and capacities)
    should be identical as much as possible for all
    chamber types.
  • Largely achieved (already discussed at CERN PRR)
  • 11. A well-defined testing procedure during
    production should be established with the
    pre-series, including some final two weeks of
    operation at nominal voltage with final gas
    mixture and flow.
  • Fully done for 2 chambers, under way for the
    remaining 2
  • 12. On the basis of the experience gained with
    the pre-production series, the production
    schedule should be re-evaluated
  • This item will be discussed later

7
Chamber gluing and its reliability In the period
2001-2003, 11 MWPC chambers were built in
Frascati of various dimensions (1.5/2.0 mm pitch,
6 of final size) and all the chambers have been
glued and built with similar techniques None of
the 960 wire pads of 9 chambers (some 15,000
wires), tested under HV showed problems so
important to need a reopening of the chamber In
these chambers we observed that after few weeks
of constant gas flowing also the wire pads that
initially were more sensitive to HV, recovered
and could be operated at the same HV as the
others In the overall design we considered of
utmost importance the availability of the access
to single pads we believe this is mandatory for
a detailed tracking of problems (especially
before chamber closing) and even afterwards, in
case a single pad shows some HV-weakness, it can
be re-routed on a lower-HV line (the so called
hospital channel, which we foresee in our
layout), without spoiling the overall chamber
efficiency and without the need of reopening (or
worst) throwing away a full chamber
8
A stressing HV test should not be performed in
the presence of humid gas, such as open air
during their construction in the clean room We
experienced that only after a very long (several
weeks) training with increasing steps in HV and
maintaining always a low current limit (in the
range of 300-400 nA for a gap of a big chamber),
the chamber can reach operating voltage well
beyond its working point The first two final
M3R3 chambers (C001-C002) were kept for 3 weeks
at 2.75 kV (200 V inside efficiency plateau) with
currents of few nA/gap We observed that a
resonably fast and simple HV test (few hours,
current limited to 200 nA per wire layer) during
the production in the clean room is able to spot
problems (see Carlos talk) On the experience
gained in two years of MWPC construction, we
believe that, once reasonable HV QC tests have
been performed, the chambers can be safely closed
with a definitive gluing
9
Status of panel production It is going on (300
for PNPI 100 for INFN) at a rate of 25-30/week
for a single mould (yesterday, 130 done, 6
discarded) See Carlos talk for details on
planarity measurements Rome 2 is setting up the
automatic measuring device at the company New
moulds (M2-3, M4-5) under construction (one
ready by Christmas) The final set up (with 3
moulds) foresees 20 panels/day (total no. of
panels 5360 gtgt 270 working days spare) A
detailed production plan for panels has to be
setup to ensure continuity for various production
centers We are planning also a clever scheme
for expedition of panels to CERN/PNPI to minimize
the number of transports and the number of boxes
10
  • Program outline
  • Carlo Construction procedures, travellers and
    QC/QA
  • Davide Source and cosmic ray test stands
  • Gaia Test beam on M3R3 chambers
  • gtgtgt break
  • Alessio Access to chamber construction
    information
  • Adalberto - Interface and integration issues
  • Pierluigi Material procurement, logistics,
    manpower, production schedule
  • gtgtgt lunch
  • Visit to production site
Write a Comment
User Comments (0)
About PowerShow.com