Mature process in place used to manage project risks ... Centrally managed between LCLS Project Director and Federal Project Director ... – PowerPoint PPT presentation

Number of Views:12
Avg rating:3.0/5.0
Slides: 11
Provided by: wwwssrlSl3
Category:
Tags: department | energy | ray

less

Transcript and Presenter's Notes

Title: U.S. Department of Energy


1
U.S. Department of EnergysOffice of Science
OECM Limited-External Independent Review of
the Linac Coherent Light Source
Hanley Lee Federal Project Director DOE Stanford
Site Office October 9, 2007
2
Outline
  • Purpose of the review
  • Project Overview
  • Impacts of FY2007 continuing resolution and
    funding shortfall
  • Revised cost and schedule baseline
  • Risk and Contingency management
  • Conclusion

3
Purpose of Review
  • EIR based on the limited lines of inquiry
  • Evaluate and validate the projects revised cost
    and schedule baseline
  • There is no change in the mission and technical
    performance
  • Recommend to OECM the reasonableness of the
    revised cost and schedule baseline

4
Project Organization
5
Project Overview
1.1 Management, Global Controls
1.1 Management, Global Controls
1.2 Injector
1.3 Linac
1.2 Injector
1.3 Linac
CLO Building
Far Experiment Hall
1.4 Undulator
Far Experiment Hall
Near Experiment Hall
Near Experiment Hall
1.5 X-Ray Transport/Optics/Diagnostics
1.6 X-Ray Endstation Systems
1.9 Conventional Facilities
6
Project Overview - continued
  • LCLS Mission
  • Research and development center for x-ray free
    electron laser (XFEL) physics in the hard x-ray
    regime and
  • Provide a facility for the application of XFEL
    radiation to experimental science
  • To achieve the mission, LCLS scope was defined to
    build a free electron laser. The scope remains
    unchanged in the revised cost and schedule
    baseline.
  • Project is 54 complete as of July 2007
  • Civil construction contract is 37 complete
  • Overall TEC is 58 complete
  • Project performance prior to FY07 was good (PARS
    criteria)

7
FY2007 Continuing Resolution Impacts
  • Project performance degraded rapidly due to the
    CR and funding shortfall
  • Re-directed resources to evaluate impacts,
    re-plan activities, and prepare revised baseline
    the costs for these efforts are
    non-recoverable.
  • Delayed undulator and controls activities and
    procurements until March 2007.
  • FY2007 funding shortfall cannot be restored until
    FY2009 re-plan Photon system activities which
    delays project completion to July 2010.
  • Reporting against the current baseline causes
    sharp decline in performance.

8
Revised Cost and Schedule Baseline
9
Risk and Contingency Management
  • Risk Management Process
  • Mature process in place used to manage project
    risks
  • Project mitigates risks (through various measures
    including VE) without compromising the LCLS
    mission and technical performance
  • Updated monthly
  • Provides the basis for cost contingency
  • Contingency Management
  • Bottoms up development by project staff based on
    risks
  • Centrally managed between LCLS Project Director
    and Federal Project Director
  • Thresholds are defined in the Project Execution
    Plan

10
Conclusion
  • Revised cost and schedule baseline completed with
    adequate cost contingency and schedule float
  • Project mission remains unchanged
  • LCLS mission will be achieved with the revised
    baseline
  • Project management systems and processes exists
    and working well
  • Revised baseline is ready for validation