SCoAG Update -Auditor General Consideration of alternate Funding Options - PowerPoint PPT Presentation

About This Presentation
Title:

SCoAG Update -Auditor General Consideration of alternate Funding Options

Description:

Option retains auditee billing and collection mechanism whilst addressing ... Additional scrutiny and possible impingement on independence. ... – PowerPoint PPT presentation

Number of Views:11
Avg rating:3.0/5.0
Slides: 8
Provided by: cori92
Category:

less

Transcript and Presenter's Notes

Title: SCoAG Update -Auditor General Consideration of alternate Funding Options


1
SCoAG Update -Auditor GeneralConsideration of
alternate Funding Options
  • April 2008

2
Content
  • Primary Funding Options under consideration
  • Retain and Improve existing model
  • Chapter 9 allocation
  • Way Forward

3
Primary option 1 Retain and improve existing
model
  • Option retains auditee billing and collection
    mechanism whilst addressing constraints which
    have been introduced to the tariff model over
    time. The following changes are required
  • Remove all tariff caps currently restricting
    recoverability.
  • Introduce additional tariff intervals for high
    cost staff.
  • Reduce recoverable hours to realistic historic
    levels.
  • Re-introduce tariff model symmetry.
  • Revise allowable surplus margin from 3 to
    between 4 and 5.
  • Determine tariffs based on the new relationship
    between direct audit staff costs and overheads
    .including a revised surplus margin.
  • Recognise realistic vacancy estimates in the
    tariff determination process.
  • Above would require an estimated 14.9 once-off
    adjustment to tariffs in financial year 2009/10.
  • Revise billing and collection processes including
    a more active Treasury role.

4
Primary option 1 Retain and improve existing
model cont/.
  • Advantages
  • Interaction between auditee and AG maintained in
    fee negotiation process.
  • Linkage between service receipt and payment is
    maintained.
  • Enables flexibility in application of external
    contract work.
  • Recognises changed AG cost structure.
  • Aligns AG tariffs with audit industry, approach
    albeit at lower rates.
  • Disadvantages
  • Effective cross subsidisation of poor paying
    auditees by paying entities.
  • Rates will increase by an additional 14.9 as a
    once-off adjustment. Thereafter normal cost
    increases will apply.
  • Significant management effort and focus on fee
    collections is retained.
  • Increased bad debts from local authorities
    resulting from higher audit charges.

5
Primary option 2 Chapter 9 allocation
  • Option is aligned to the recommendations
    contained in the Report of the ad hoc Committee
    on the Review of Chapter 9 and Associated
    Institutions dated 31 July 2007. The commission
    was chaired by Hon. Prof. AK Asmal.
  • The reports recommendations include
  • The budgets of all Chapter 9 institutions should
    be part of Parliaments Budget Vote.
  • The above process should be negotiated with
    National Treasury and should afford the
    institutions adequate opportunity to motivate
    their budget submissions directly to National
    Treasury before decisions on the budget
    allocations are taken.
  • the programme within Parliaments Budget Vote
    for these institutions would still fall under the
    Public Finance Management Act and would be
    subject to accountability and audit arrangements
    common to other organs of state.

6
Primary option 2 Chapter 9 allocation cont/.
  • Advantages
  • The effort associated with debt collection is
    avoided enabling audit staff focus on primary
    area of responsibility.
  • Process aligned to global best practice.
    Universal international practice allows for
    centralised responsibility of AG funding.
  • Disadvantages
  • Dependency of approval of the budget by National
    Treasury.
  • Additional scrutiny and possible impingement on
    independence.
  • The additional monitoring and reporting
    requirements of the PFMA need to be complied
    with.
  • Possible loss of focus on cost controls and the
    achievement of efficiencies.
  • Potential additional funding requirements
    (brought about by say additional vacancies /
    contract work) will need to be separately
    requested and motivated.
  • Removes the linkage between the entity for whom
    the work is undertaken and the entity responsible
    for payment. This may have a negative impact on
    the auditees approach towards the cost effective
    completion of the audit.

7
2. Way forward
  • The preferred funding option will be recommended
    after completing the following
  • Interact with National Treasury at DG level
  • Engage with SCoAG
  • Receive input from the SAI Global Working Group
  • Engage with IRBA
  • Discuss and evaluate all options at AG EXCO
  • The final recommendation will be made to SCoAG at
    the June 2008 meeting
Write a Comment
User Comments (0)
About PowerShow.com