The different phases of the MOX fuel manufacturing MELOX plant start up - PowerPoint PPT Presentation

About This Presentation
Title:

The different phases of the MOX fuel manufacturing MELOX plant start up

Description:

The links between the authorisation process and the safety assessment. By Jean-Pierre Carreton (IRSN) and Jean Jaraudias (DGSNR) OCDE/NEA FUEL CYCLE WORKSHOP ... – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 18
Provided by: CARR99
Category:

less

Transcript and Presenter's Notes

Title: The different phases of the MOX fuel manufacturing MELOX plant start up


1
OCDE/NEA FUEL CYCLE WORKSHOP TOKYO 2002
  • The different phases of the MOX fuel
    manufacturing MELOX plant start up
  •  
  • The links between the authorisation process and
    the safety assessment
  •  
  •  
  • By Jean-Pierre Carreton (IRSN) and Jean Jaraudias
    (DGSNR)

2
MELOX plant start up
  • Summary
  • Introduction
  • MELOX plant technical information
  • MELOX history
  • Creation
  • Operation
  • Modification
  • Conclusion

3
MELOX plant start up
  • On the 17th of April 2000, the French
    Environment and Industry Ministers approved the
    industrial commissioning of the MOX fuel
    manufacturing MELOX plant. It followed an
    assessment of the final safety documents
    transmitted by the operator (safety report,
    general operating rules and emergency plan)
    carried out by the French nuclear safety and
    radioprotection authority (DGSNR) and its
    technical supports.

4
MELOX plant start up
  • The objective of this talk is to describe
    the plants commissioning authorisation process,
    carried out after the plant's design basis was
    transmitted by COGEMA in 1985.
  • The different actors
  • the operator COGEMA,
  • the French nuclear safety authority the DGSNR,
  • the technical supports which advise this
    authority the Radiation Protection and Nuclear
    Safety Institute (IRSN) and the Advisory
    Committee for the nuclear laboratories and
    industrial plants (GPU).

5
MELOX plant start up
  • MELOX plant some technical information
  • The COGEMA-operated plant is located on the
    nuclear site of Marcoule in the south-east of
    France.
  • It manufactures LWR MOX fuel assemblies using the
    MIMAS process (micronization of a master blend).
  • First limited to the French market, it was
    extended in 1999 to the needs of foreign
    electricity companies by the start up of a new
    line for the manufacturing of different design
    fuel assemblies.

6
MELOX plant start up
7
MELOX plant start up
B500 manufacturing B501 waste treatment
Nuclear buildings
Non nuclear buildings
8
MELOX plant start up
  • The MELOX history could be divided in two phases
  • a definition and design phase, characterised by
    the presentation and the analysis of
  • the safety options,
  • the preliminary safety report,
  • thus leading to the plant creation authorization
    decree (DAC)
  • the probatory operating phase, which started with
    a heavy test period, followed by the progressive
    increase of the production level, and recently
    ended with the industrial commissioning of the
    plant.

9
MELOX plant start up
Creation
Operation
Releases
June 85 Safety options
1987 Preliminary studies
March 93 IRSNs assessment
May 90 Creation decree
June 93 Provisional safety report
June-July 93 Public inquiry
July 94 Release orders
August 94 operating authorisation
September 99 Final safety report
May 2000 Industrial commissioning
10
MELOX plant start up
June 85 Safety options
November 87 Creation authorisation request
October 85 IRSNs assessment Advisory Committee
March 88 Preliminary safety report
March 88 Public inquiry
June 88 IRSNs assessment Advisory Committee
March 89 CIINB
May 90 Creation decree
11
MELOX plant start up
  • The MELOX plant authorisation decree limits
  • the annual production of LWR fuel rods and
    assemblies to 115 tons of mixed oxide,
  • the mass of plutonium oxide in the plant to 14
    tons,
  • the 240 isotope and 241Am content of the
    plutonium used,
  • - mentiones the main workshops
  • the manufacturing building (n 500), including
    all the manufacturing equipment from the
    reception of the powder to the control and the
    shipping out of the final products,
  • the waste management building (n 501),

12
MELOX plant start up
  • - requires various measures related to internal
    and external hazard control,
  • - defines a set of rules for the administrative
    monitoring of the plant throughout its life in
    particular the transmission of
  • a provisional safety report, general operating
    rules and an on-site emergency plan six months
    before radioactive materials are first delivered
    to the plant,
  • a final safety report including the operational
    feed back and a time limit for the industrial
    commissioning of the facility (10 years).

13
MELOX plant start up
May 91 New Preliminary safety report Waste
building
June 93 Provisional safety report
June 92 IRSNs assessment Advisory
Committee Waste Building
Mach 94 IRSNs assessment Advisory
Committee Manufacturing Building
June 95 IRSNs assessment Advisory
Committee Waste Building
August 94 Manufacturing building operating
authorisation
July 95 Waste building operating authorisation
14
MELOX plant start up
September 99 Final safety report
April 2000 IRSNs assessment Advisory Committee
May 2000 Industrial commissioning
15
MELOX plant start up
  • Two main modifications have been implemented
  • an extension of the manufacturing building to
    produce foreign customers fuels (PWR and BWR),
  • the adaptation of the shipping workshop to the
    reception of new transportation casks (MX8).

16
MELOX plant start up
  • Conclusions
  • This creation authorisation process needed 15
    years and
  • the transmission of several safety files by the
    licensee,
  • the IRSNs assessment of this files and six
    meetings of the Advisory Committee,
  • two proceedings, each including a public inquiry,
  • numerous inspections carried out by the Safety
    Authority during the successive building, tests,
    starting up and operational phases,
  • .

17
MELOX plant start up
The five operating years feedback studied
emphasised that a satisfying control of the
hazards presented by the MELOX plant was
achieved. Nevertheless, the French Safety
Authority, according to its missions, keeps up a
sustained follow up of the plant, in particular
by mean of a specific inspection program. The
Authority also requests IRSNs assessments about
the different plant modifications, and a periodic
plant safety reassessment carried out usually
with a ten-year periodicity.
Write a Comment
User Comments (0)
About PowerShow.com