ATC Order 890 Stakeholder Update Preliminary Results - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

ATC Order 890 Stakeholder Update Preliminary Results

Description:

1. ATC Order 890 Stakeholder Update Preliminary Results. ATC Economic ... Lore Spring Green - Cardinal 345 kV Line. Preliminary 2018 Non-Project Results ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 16
Provided by: Rebecca320
Category:

less

Transcript and Presenter's Notes

Title: ATC Order 890 Stakeholder Update Preliminary Results


1
ATC Order 890 Stakeholder Update Preliminary
Results
  • ATC Economic Planning
  • 12-18-08

2
2008 Analysis Preliminary Results
  • Projects to Analyze
  • Bain Zion 345 kV Line
  • North La Crosse Hilltop Spring Green
    Cardinal 345 kV Line
  • Lore Spring Green - Cardinal 345 kV Line
  • Preliminary 2018 Non-Project Results
  • Preliminary 2024 Non-Project Results
  • Preliminary 2024 Project Results

3
Projects to AnalyzeBain Zion 345 kV
These drawings are intended for informational
purposes only and do not depict actual
transmission line additions or potential routes
and siting
4
Projects to AnalyzeNorth La Crosse Hilltop
Spring Green Cardinal 345 kV
These drawings are intended for informational
purposes only and do not depict actual
transmission line additions or potential routes
and siting
5
Projects to AnalyzeLore Spring Green
Cardinal 345 kV
These drawings are intended for informational
purposes only and do not depict actual
transmission line additions or potential routes
and siting
6
Preliminary 2018Non-Project Results
Utilizes the MISO Wind Transmission Overlay
7
Preliminary 2024Non-Project Results
Utilizes the MISO Wind Transmission
Overlay Utilizes the MISO Reference
Transmission Overlay
8
Preliminary 2024Reference FutureProject Results
Utilizes the MISO Reference Transmission Overlay
9
Preliminary 2024Robust Economy FutureProject
Results
Utilizes the MISO Reference Transmission Overlay
10
Preliminary 2024High Retirements FutureProject
Results
Utilizes the MISO Reference Transmission Overlay
11
Preliminary 2024High Environmental
FutureProject Results
Utilizes the MISO Reference Transmission Overlay
12
Preliminary 2024Slow Growth FutureProject
Results
Utilizes the MISO Reference Transmission Overlay
13
Preliminary 202420 Wind FutureProject Results
Utilizes the MISO Wind Transmission Overlay
14
Preliminary 2024Fuel Investment Limitation
FutureProject Results
Utilizes the MISO Reference Transmission Overlay
15
Questions?
  • ATC Economic Planning
  • Dale Burmester
  • dburmester_at_atcllc.com
  • Tom Dagenais
  • tdagenais_at_atcllc.com
  • Arash Ghodsian
  • aghodsian_at_atcllc.com
  • Chris Hagman
  • chagman_at_atcllc.com
  • Todd Tadych
  • ttadych_at_atcllc.com