Title: Beam Delivery Systems
1Beam Delivery Systems
- Are we headed in the right direction to produce a
CDR by the Spring of 2001 - Are we configured correctly and focused on the
right things
2Cost
- In 1996 ZDR Cost estimate BDS was 5 of total
project cost - CollimationBig Bends 72 M
- Final Focus, IR, Dumps 135 M
- Total Beam Delivery IR 207 M
- Total Project 4338 M
- We will not pay much attention to cost or
construction schedules in this review
3To have a credible CDR we must be able to
convince ourselves and the physics community that
- we can take a design emittance beam from the
linac and de-magnify it to 3 nm - we can get two independent beams to collide and
that we can maintain those collisions - that there is sufficient understanding ,
protection, controls, and diagnostics so that the
high power beams do not destroy the beam line nor
cause unacceptable backgrounds - that there is sufficient understanding of the
luminosity dependent backgrounds generated at the
IP and an adequate masking design
4Why might it be difficult to convince a skeptic?
- It has taken the SLC 10 years to (almost) reach
design luminosity - While much has been learned, NLC breaks new
ground in many areas
5What did we have in the ZDR?
- Collimation System
- very long to provide passive protection for
spoilers collimators - severe optics
- chromatic problems
- tight tolerances
- octupoles
- wakefield problems
- very difficult to calculate for flat collimators
- rectangular apertures
6What did we have in the ZDR? (continued)
- IP Switch, Big Bend, and the Final Focus
- 10 mrad bend
- Two IPs
- 40 m transverse separation
- symmetrically located in z
- 2 m L design
- Well studied optics
- Jitter drift tolerances on individual elements
- 0.5 lt Ecm lt 1.5 TeV, but magnets need transverse
displacement - Extraction and Diagnostic Line
- impossible REC quads 2m from IP
- common e and g dump
- chicane to separate e and g lines for diagnostics
7What did we have in the ZDR? (continued)
- IR design
- Achieve 1nm stability via
- Optical anchor concept
- Compact detector
- Simple 100-150 mrad dead cone masking scheme
- based on 2 Tesla field and the ee- pair pt
distribution - Good muon background calculations
- Four 9 m long tunnel filling spoiler magnets
- lt Entire beam (1012 e-) could strike collimator
make lt 1 m _at_ detector - Good ee- and SR background calculations and
detector simulations - lt 10 hits/mm2/train _at_ r 1 cm in 4 Tesla
8Where are we today?
- Collimation System
- Collimation group formed and considered novel
schemes - lasers
- octupoles
- post-bunch compressor / pre-linac
- intra-linac
- post-linac
- Reduce requirement of collimator survival and
redesign a conventional scraper system - Tors talk
- Wakefield tests planned for near future
9Where are we today? (continued)
- IP Switch, Big Bend, and the Final Focus
- First real design of IP switch
- pay attention to spatial conflicts between the
two IP beamlines - 300 m IP separation in z
- Magnets redesigned to
- reduce number of magnet classes
- increase vacuum bore and minimize changes in bore
- Final quads redesigned to reduce pole tip fields
and increase beam stay clears - change Q1 A B for 350 lt Ecm lt 750 GeV and 750 lt
Ecm lt 1000 GeV - Well studied optics
- No longer need transverse displacement to upgrade
beam energy to 1 TeV - Feedback, stability, and tolerance studies just
begun
10Where are we today? (continued)
- Extraction and Diagnostic Line
- ZDR optics analyzed and found to produce
unacceptable beam loss - Redesign begun
- move first quads further away from the IP
- improve beam loss
11IR status today?
- Small spots Many belts suspenders
- Optical anchor RD well developed (Mike Woods)
- 1 m interferometer
- piezo-mover vs. interferometer calibrations
- 10 m interferometer
- 100 kg quad simulator
- Goal IR mock-up
- Re-open question of non-optical stabilization
devices (Joe Frisch) - geophones
- accelerometers
- Very fast IP feedback (John Fox)
- Bunch spacing 1.4 ns -gt 2.8 ns
- Use head of bunch to correct tail
- Goal 50 ns to correct following bunches of 244
ns long train - RD planned developed
- looking for student(s)
- FFTB Run 1 70 nm spots, 40 nm jitter
12IR status today? (continued)
- Engineering
- Nothing new since Snowmass 96
- Basic IR parameters
- Ideally, study the engineering, optics, and
backgrounds for - L 1, 2, 3 m
- Large and Small detectors (B_solenoid)
- Crossing angle ?c
- Q1 technology choice REC, SC, Hybrid, Normal
- Currently L 2m, B_s 4 Tesla, ?c 20 mrad,
REC Q1 - Crossing Angle requires RF Crab cavity
- stability requirements analyzed and thought not
to be a show stopper - RD program to verify this developed
13IR status today? (continued)
- Basic IR parameters (continued)
- Vertical deflection of beams due to ?c and Bs
- steering 45 mm deflection
- dispersion 135 nm added to vertical spot size
- Need one of
- Flux exclusion solenoid around Q1, or
- 800 G-m steering corrector after Q1, or
- Tuning with upstream skew-quad system
- Relative merits of each choice need study
- B_s apparently not constrained to within x2
- Desirable to coalesce JLC/NLC choices
- L 2 m
- ?c 8 mrad
- Iron Q1 system with a flux exclusion solenoid
- B_solenoid 2 T
14IR status today? (continued)
- Backgrounds
- Source Calculations
- Beam - Beam incoherent pairs
- CAIN - Guinea-Pig code comparison
- Agree within x2
- Differences due to internal technical cuts
- SR, Muons
- Not yet redone for the newest lattice
- In principle, no problem
- Detector Simulations
- EGS -gt GEANT3 -gt GEANT4
- GEANT3
- Beam-Beam pairs e, g, n backgrounds as function
of radius - SR e, g, n backgrounds as function of radius
- calculation of n from 500 GeV e- hitting main
dump just begun - MUCARLO
- Opportunities for improvement, cost savings,
agreement with JLC
15IR status today? (continued)
- Extraction Line Diagnostics
- No one working in this area
- Tools to unfold beamstrahlung spectra
- Luminosity monitors
- Instrumented masks
- Energy spectrometers
- Polarimeters
- Radiative Bhabha monitors
- Beamstrahlung monitors
16General Comments
- Unless there is a change of direction we will
continue to act on a best efforts basis each
individual working in their area of expertise
until a given deadline. Then there will be a
brain-dump and the machine status will be written
up with a positive spin, just like for the ZDR. - Why?
- Too few physicists engineers devoted to this
part of the project - Effort diluted in an attempt to broadly cover
machine, ignoring the fact that our main effort
is to investigate the design parameter space
sufficiently to believe that we have produced the
best design possible. - Inability to articulate what is critical and to
bring what resources we have to bear on the
problem.
17People(red full time beam delivery)
- Engineering
- Leif Eriksson
- Andy Ringwall
- Dieter Walz
- Other Accelerator Design Issues
- Yuri Nosochkov
- Peter Tenenbaum
- Kathy Thompson
- Tor Raubenheimer
- Collimation
- Joe Frisch
- Rainer Pitthan
- Frank Zimmermann
- IR Design
- Tom Markiewicz
- Takashi Maruyama
- Mike Woods
- Tracy Usher
- In the bullpen /or consultants
- Gordon Bowden
- John Fox
- Dick Helm
- Stan Hertzbach
- Nan Phinney
- Sayed Rokni
- Marc Ross
- Tim Slaton
18(No Transcript)
19What do we really need in the CDR?
- Evidence that we have sufficiently analyzed the
parameter space that defines the overall
footprint of the beam delivery system - Explain the parameter space or design options
- L, ?c, NLC vs. JLC style final focus, NLC vs.
JLC collimation, sacrificial or indestructible
collimators, active or passive protection, etc. - Justify choice of design MPS, Collimation,
IP/BB/FF, Dump - describe design and its tolerances and
performance _at_ 500 GeV and 1 TeV - Specify tuning, feedback, and diagnostic systems
- De-magnification assured (FFTB) but can we get
and maintain collisions given tolerances - Monte Carlo - like simulation results which
incorporate feedback, tolerances, drifts and
jitter and which indicate the performance specs
or aberration limits for each part of the system - compare to alternate schemes
- Explain what changes to design might be possible
with more work but within the footprint - e.g. more collimation _at_ 1.5 TeV
- e.g. range of allowable L
20What do we really need in the CDR?
- Engineering
- Identification and prototype results of items
with high technical risk - Identification of problem areas arising because
of the scale of project - Reliability
- Schedule
- Fabrication
- QC
- Installation
- Cost estimate
- Large contingency allowable
- Boilerplate
- Parts counts
- Engineering specs
21What do we really need in the CDR?
- Description of IR parameter space
- L, ?c, Q1 technology choice, Flux excluder or
not, tune-ability, vibrations, mass, stiffness,
Solenoid field strength - Justify choices and describe performance
- Put to bed the IR stability question
- Build an adequately engineered full scale
prototype of IR - Present experimental evidence on
- the amplification (or lack) of ground motion and
culturally induced jitter - the achievable jitter reduction as a function of
frequency - relative to local bedrock
- absolute
- Hardware simulation of a low latency pickup and
correction scheme - FFTB2 measurement of 40 nm spots desirable but
expensive in terms of effort
22What do we really need in the CDR?
- Description of detector backgrounds from all
sources and optimization of shielding - Easier to calculate sources
- Beam-beam pairs
- SR photons
- Muons
- Harder to calculate sources
- Jets from gg
- Lost particles, energy tails, .
- Design and simulate a minimal set of dump line
instruments - required to tune luminosity
- required to extract physics
23What post-CDR study can go on?
- Design can be tweaked until the engineering
contracts are bid, but changes that do lengthen
the tunnel footprint will probably be strongly
discouraged
24Conclusions
- Main concern is that important parts the BD
design remain while ULM has taken an engineering
mind-set. Will BD work or not? Would like to
see lots of convincing calculations and
experimental results. - that not enough options have been investigated
- current lattice needs lots more attention
- requisite RD may be happening at too slow a rate
to allow for its results to be included in the
final design - e.g. current tunnel depth is 30 stability may
require gt300 - large implication to project design
- Please advice ULM to find resources to address
these problems quickly if Spring 2001 CDR
deadline is to be met - people
- money (to buy/rent people)
- beam time (Coll. Tests, FFTB?, )