Title: PSR Section 3
1Section 3 Verification Process
. . . Mark Perry Swales Aerospace
2Verification Process Agenda
- Environmental Test Approach
- Verification Matrix
- Satellite Environmental Test Flow
- Satellite Environmental Test Documentation
- Summary of Satellite and Component Test Time
- Functional and Performance Testing
- Environmental Testing Overview
- LV Separation Shock / Vibration
- Acoustics
- EMI/EMC
- Magnetic Survey
- RF Compatability
- Thermal Balance/Thermal Vacuum
- Alignment
- Mass Properties
- X-Band Near Field Assessment
- End to End Instrument Optical Testing
3Environmental Test Approach
- EO-1 Verification Process is described in the
EO-1 Verification Plan and Environmental
Specification (SAI-SPEC-158) - Verification Matrix identifies the box and system
level testing - Some flight box level testing was deferred to
observatory level testing based on qualification
by similarity or a second in a series of like
hardware - System level environmental testing was with all
flight hardware with exception of the flight
battery or where configuration did not allow
example the solar array was not included with the
Observatory during Thermal Vacuum - Satellite Environmental Flow comprised the
following - Shock (2) Firings
- Vibration - 3 axis sine sweep at protoflight
levels (1.25 x flight limits) - Acoustic at protoflight levels
- EMI/EMC
- Thermal Balance
- Thermal Vacuum
4Final System Level Spacecraft Verification
5Spacecraft Verification Flow
5/3
5/11
7/14
7/15
7/24
7/26
7/26
7/30
7/31
8/5
8/5
8/6
7/16
7/23
1773 Sensitivity Test
1st CPT (PreShip to GSFC) SA Deployment on S/C
OTDR F/O measurements, S/W Tests
Partial 2nd CPT MOC Tests
Acoustic Test
Weigh Satellite 3 Axes Vibration 2 Shock Tests -
Modal Tap Test AST/IRU Alignment
CPTMOC
Acoustic
CPT
F/O
Modal/Align
Vib/Shock
F/O S/W
8/7
8/8
8/29
9/4
9/5
9/16
9/17
10/1
10/1
10/20
10/30
10/21
8/17
8/19
EMI/ EMC Radiation Emissions Test
M5, RSN, PSE S/W Test Regression Test
TB/TV 4 Cycles - CPT HOT - CPT Cold - MOC
Simulation - Safe Hold 24 Hrs - 1773
Sensitivity - Functional Test
Alignment Measurement
RF Compatibility CPT0-CPT11
S/C Timing Test 1773 Margin Test Functional
Test ACE/XPA/PSE S/W
ACE/XB S/W Load Test
Alignment
RF Compatibility and CPT
EMC
F/O, Timing
S/W
S/W Test
TB TV
11/1
Pre-Ship
11/9
11/17
11/8
11/18
11/30
12/11
11/29
Verification Flow -CPT -F/O Sensitivity -Modal
Survey -Alignment Measurements -Weigh
S/C -Vibration -Shock -Acoustic -RF
Compatibility -EMC/RE -Thermal Balance -Thermal
Vac -Instr End to End - Magnetic Survey
(Static) -EMC/CE -Pre-Ship CPT -Mass Properties
ALI Hyperion ETE Test Hyperion VNIR
Characterization XB NF Test
1773 Bus Buster MOC SIMS
Magnetic Survey RCS Press/Leak EMI/EMC CE Test
Self Compatibility
Pre-Ship CPT
Mass Properties
Ship to WTR
Instrument ETE X-Band Characterize
S/W, MOC Test
EMC
Mass PROPS
CPT
6Verification Documentation
- EO-1 Verification Plan Environmental
Specification SAI-SPEC-158 - CPT SAI-PROC-679A
- F/O Sensitivity TD WOA-462
- 1773 Sensitivity TD WOA-496
- Alignment SAI-PLAN-206
- Modal Test SAI-PLAN-341
- Shock Test SAI-PLAN-341 SAI-PROC-739
- Vibration Test SAI-PLAN-307 SAI-PROC-739
- Acoustic Test SAI-PLAN-320
- RF Compatibility SAI-PLAN-XXX, WOA-410/590 (STDN
- 408.1) - Mass Properties SAI-PLAN-319 (Test Postponed)
- TB/TV SAI-PLAN-273 SAI-PROC-619
- Instrument End-to-End SAI-PLAN-358
- Magnetic Test SAI-PROC-768
- EMI/EMC Test SAI-PROC-752
- X-Band Near Field Test SAI-PLAN-368
7Additional S/C Testing
- Testing not included in original Verification
Plan - ALI Hyperion End to End Testing (Optical
Testing) - Hyperion VNIR Characterization
- 1773 Bus Buster Test
- MV Stress Testing
- S/C Timing Test
- X-Band Near-Field Test
- Post-Environmental Flash Test of Solar Arrays
8Projected Power On Time
9EO-1 Functional and Performance Testing
10CPT Design and Description
- Goal is to test every function and to measure
performance for each subsystem and for the
complete EO-1 system - With the exception of some RF and RCS testing,
all tests are conducted from ASIST STOL
procedures to facilitate repeatability and reduce
errors - The CPT contains about 100 individual tests.
These tests were planned to perform as much
parallel testing as possible without sacrificing
the integrity of the individual tests. - All nominal and critical commands (about 500)
tested during the CPT - The rest of the on-orbit commands are tested
outside the CPT, such as during
software-acceptance tests - Additional commands, which were used for
integration, development, test and diagnosis,
will be deleted from the database. - The CPT is comprised of 12 sections, as defined
in SAI-PLAN-659A
11CPT Sections
- Sections 0 and 1 Power-on defaults, launch,
ascent, deployment, and sun acquisition - Sections 2, 5, and 6 Exhaustive s/c tests ACS,
Power, CDH, RF, S/A drive, deployment
redundancy - Section 3 Non-imaging instrument and WARP
- Section 4 EFF
- Sections 7 and 8 Exhaustive imaging
- Sections 9 and 10 Restart, safemode, and
load- shedding - Section 11 Orbit-timeline
12Non-CPT System Performance Tests
- These are special tests that are incompatible
with the CPT - Require special satellite configuration which
would inhibit other tests - Require special GSE
- Limitations such as maximum pressure cycling
- Specific Non-CPT Tests
- End-to-end optical tests verify instrument
alignment and optics (require EO-1 in a
horizontal attitude) - 1773 tests bus buster/SEU and optical
performance (special GSE) - X-band ACS-to-X-band pointing tests and
near-field test (special GSE) - GPS constellation tests requires special GSE and
is incompatible with other systems tests using
ephemeris and time. - ACS virtual satellite (simulates ACS components)
software testing - FDC testing TSMs, RTSs, WARP, PSE, and ACS
- Solar-array mechanical deployment (to exercise
the s/a array drive and associated software, the
s/a is not mounted during CPT) - RCS pressure testing propulsion tank is limited
to a few cycles - Heater tests requires cold-soak
- MOC simulation tests system tests in additional
operational scenarios - LFSA and PPT (category III payloads) tested
separately - Flash test of solar arrays (requires special
equipment and location)
13Baseline CPT
- Conducted August 31st to September 4th
- Generated 160 problem reports, dominated by
procedure errors - 120 PRs defined as procedural errors
- 20 software errors
- 3 GSE problems
- 14 incorrect limits and data-base errors
- 8 open PRs, 5 are pending verification as of 8
December 1999 - Main deficiency of baseline CPT was that final
flight s/w was not ready - PSE (FDCmisc.), HK RSN (GPSmisc.), and TSM/RTSs
are biggest changes - Mitigated by two later CPTs (12/6/99 and 2/00),
which use final flight software - Subsystem reports and analysis
- Initial problems, mostly software, already
identified, corrected, and verified - Reports and analysis nearly complete all known
results are nominal no problems discovered that
require hardware modification
14Functional Test
- Used between moves and after environmental tests
to verify all EO-1 functions - Performed after transportation to GSFC and
planned for after transport to launch site
(omitted if CPT performed). - Performed between vibration and TV tests and
after TV test. - Performed (with some modification) at the launch
pad - Objective is to test every wire and connection on
EO-1 - Much of the software is tested as a by-product
- The functional test is a subset of the CPT tests
- Maximum use of well-developed tests
- The functional does not include tests that are
exclusively performance tests
15System Testing During Thermal/Vacuum Test
- Each CPT section conducted at both hot and cold
plateaus - Since hot/cold plateaus are only 24 hours long,
CPT was not continuous at each plateau - Functional conducted during pumpdown and at the
end, just before chamber break - 150 PRs, 80 are closed and verified as of 8
December 1999 - All critical PRs closed
- Nadir-deck heater short was only hardware anomaly
- Several new software errors discovered
- Some procedure errors discovered
16Post-Environmental CPT Preliminary Results
- Conducted December 6-9, 1999
- All flight hardware and software configuration
except - LFSA not mounted
- Will probably modify HK RSN software
- Will fuse LVPC non-critical power services
- Several table parameters to be modified for
flight (telemetry filter, TSM, RTS) - Except as noted in PRs, all results reviewed to
date are nominal - 20 PRs initial assessment (through CPT5)
- 6 were procedure or operator errors (already
corrected) - 4 were nominal conditions initially perceived as
problems - 4 GSE problems (3 FEDS and 1 GPS simulator)
- No hardware problems
- 5 PRs were software problems
- Unexpected safehold entry due to M5 warmstarts (2
PRs) - Deployment may re-start if HK RSN has a warm
start (statistics are 1-in-50 known cause not
necessary to fix) - Unexpected WARP error (status?)
- 1 RTS-table error
- 1 not investigated
17Environmental Testing Overview
18LV Separation Shock
- Test Configuration (Building 7 Test Cell 040 )
- Flight-Type Payload Attach Fitting Clamp Band
System (Boeing) - Spacecraft supported from crane and PAF dropped
on to foam pad - Spacecraft fully configured and powered in
launch mode - Hyperion and LFSA not electrically integrated
(not powered during launch) - Thirty one tri-axial accelerometers used to
monitor shock levels - Time History plots
- Shock response Spectra Plots, Q10, 100-2000Hz
- Two Firings performed
- Results
- All responses, with exception of two on Nadir
deck, well within specified environments - Conclusions
- Environment benign
- Aliveness test indicated no anomalies
19Vibration Test
- Test Configuration (Building 7 Test Cell 040 )
- Flight-Type Payload Attach Fitting Clamp Band
System (Boeing) - MAP Spacecraft vibration test fixture (force ring
transducers) - Spacecraft fully configured and powered in
launch mode - Thirty three tri-axial accelerometers used to
monitor shock levels - Three axis sine sweep vibration to protoflight
levels (1.25 x Flight Limit Loads) - Results
- No physical damage to structure No shift in
Frequency pre- versus post-vib - Conclusions
- Spacecraft Structure qualified for flight
- Coupled Loads Analysis model updated and
submitted to Boeing for VLC base banding
(fundamental freq. increased over predicts) - Verification Coupled Loads results confirm all
margins positive - Aliveness test indicated no anomalies
20Acoustic Test
- Configuration (Building 7 Acoustic Chamber)
- Spacecraft lifted off dolly and suspended by
chamber crane - Thirty three tri-axial accelerometers used to
monitor shock levels - Spacecraft fully configured and powered in
launch mode - Boeing Delta 7320-10 Levels (Overall 141.1 dB)
- Protoflight levels (one minute duration)
- Results
- No physical damage to structure
- Protoflight level achieved (within tolerance)
- Responses well within specified component test
levels - Conclusions
- Spacecraft Structure qualified for flight
- Aliveness test indicated no anomalies
21EMI/EMC Test
- Configuration
- Spacecraft fully configured with exception of
solar array removed - Radiated Emissions Testing Radiated
Susceptibility (GEVS Range/ELV) Testing
performed in GSFC EMI facility (performed pre TV) - Power Profile Testing Conductive Emissions
Testing performed in EO-1 Clean Tent (Performed
post-TV) - Results
- RE RS fully characterized and all exceedences
documented - CE fully characterized and all exceedences
documented - RF Hat Coupler Leakage tested and verified
- Conclusions
- All appropriate Waivers generated and evaluated
as acceptable - See Special Topic at the end of this section
22Magnetic Survey Test
- Configuration
- Basis of Test Procedure was ACE, TRMM, WIND,
Polar and XTE - Static magnetic field measure via fixed
magnetometers setup by GSFC Magnetics Group. Test
conducted by GSFC MAG - Performed in Building 29 SSDIF
- Performed during period of low activity in
facility to reduce background magnetic noise
levels - Spacecraft suspended by crane using specially
designed sling that minimized use of magnetic
parts and which maximized distance from crane
hook (14ft) - Results
- Total Static (DC) magnetic field of Satellite
fully characterized - Conclusion
- DC Magnetic dipole of 9Am2 is higher than
expected - Magnetic Torque Bars have sufficient margin to
compensate -- analysis in process
23RF Compatibility Test
- Configuration (S-Band X-Band RF Hat Coupler to
Compatibility Test Van) - Demonstrated the operational capability of the
command, telemetry and tracking data
communications interface between the Ground
Network (GN), Space Network (TDRSS), and Mission
Operations Center - Spaceflight Tracking Data Network (STDN-408.1)
Procedure used - Phase 1 RF Network Compatibility Testing WOA-410
- Measure the physical characteristics (Group
delay, frequency, Bit Error Rate, carrier
suppression) of the EO-1 RF System SN/GN via
CTV only - Phase 2 RF End-to-End System Test RF TDRSS
Compatibility Test WOA-590 (CTV used as the
interface between the spacecraft MOC) - Verify that the MOC has the capability of
commanding the spacecraft and receiving real-time
playback housekeeping telemetry through the GN - Verify that real time housekeeping telemetry may
be received by the MOC at 2Kbps over the SN
24RF Compatibility Test
- Results
- All S-Band X-Band characteristics verified
- Awaiting final CTV Test report
- Conclusion
- EO-1 RF Subsystem is compatible with the Ground
Network Space Network
25Thermal Balance /Thermal Vacuum Test
- Configuration (Building 7 Thermal Test Chamber
238) - EO-1 Satellite fully configured (LFSA not
electrically integrated non-flight
calorimeters) with all flight MLI Thermal
blankets installed - Demonstrate that the EO-1 Satellite and payloads
can operate satisfactorily in all functional
modes for the mission, at 10C beyond the hot
cold extremes predicted for orbit - Perform a complete Comprehensive Performance Test
the hot cold plateau (distributed). Perform
additional Performance tests throughout TB/TV - Demonstrate the EO-1 satellite operates
satisfactory in safe hold (24 hours) - Demonstrate satisfactory operation of the EO-1
Spacecraft and payload thermal control systems - Verify the EO-1 Spacecraft and payload thermal
models - Verify the EO-1 Satellite meets contamination
requirements - Assess Instrument self-contamination and outgas,
if necessary - Provide opportunity for MOC to run flight
operations procedures
26Thermal Balance Thermal/Vacuum Test
27Thermal Balance Thermal Vacuum Test
28Thermal Balance Thermal Vacuum Test
- Results
- All objectives met
- Nadir Deck Heater Service Anomaly (see Special
Topics) - Demonstrated nominal operation of EO-1 Spacecraft
and payloads at temperature extremes - Demonstrated TCS for Satellite and payloads
- Excellent correlation with Satellite Thermal Math
Model - Contamination of EO-1 Satellite demonstrated to
be well within limits however ALI out-gassing
phenomenon which occurred during payload testing
materialized at Satellite level. Impacts initial
On-Orbit bake-out planned - Conclusion
- EO-1 Satellite qualified for On-Orbit operation
- Post Thermal Vacuum Functional test was nearly
flawless
29Alignment
- Pre Environmental
- Alignment Characterization performed at the
Spacecraft Bus level to establish primary
reference frame - Map Master Reference Cube (MRC) and S/C primary
datums - Map Secondary Reference Cube (SRC) on IRU to IRU
Primary Reference Cube - Map MRC to SRC
- Alignment Performed at Satellite Level
- ALI AC co-aligned to within 2 Arc-minutes
- Post Environmental
- IRU/SRC to AC co-alignment verified following
vibration (no measurable movement - lt15 arcsec) - AC to AST alignment verified post vibration
(measurable rotation shift assessed) - IRU SRC will be mapped to the S/C MRC AST
reference cubes at WTR - ALI HSA reference cubes will be mapped to the
S/C MRC at WTR - AST to S/C MRC will be mapped to the S/C MRC at
WTR
30Mass Properties
- Configuration (performed prior to shipment using
Miller Mass Props Table) - EO-1 Satellite mass has been measured several
times throughout environmental program - 98.4 of components measured (Hydrazine Fuse
Plugs) - Projected total mass of 573 Kg is 15 Kg under
flight allocation (588 Kg) - Detail Solid model (PRO-E model) used to
calculate CG and inertia values prior to
verification on Miller Table - X Y CG values to be measured Z CG value to be
calculated using Solid Model - Results
- Total Mass allocation met
- CG requirement is projected to be within
established requirement
31X-Band Phase Array Near Field Test
- Configuration (Performed in Building 29 SSDIF)
- Performed at component and Satellite level
- Satellite level testing performed while in
Horizontal Configuration on Arronson Table - Satellite fully configured
- Verify Antenna Pattern Effective Isotropic
Radiated Power (EIRP) - Verify Attitude Control System can dynamically
command the antenna to known beam positions - Results
- Antenna pattern consistent with component level
pre-environmental - EIRP measured at 57 dBm meets requirement
- Demonstrated ACS can dynamically command antenna
beam to known position - Conclusion
- X-Band Phase Array performance verified at the
Satellite level
32X-Band Phase Array Near Field Test
NF Scanner in Position in Front of the XPAA
During NF3
33End-To-End Instrument Test
- Objective
- Demonstrate that the ALI and Hyperion survived
the environmental test program without
degradation to the imaging quality. - Hyperion VNIR characterization test exercises the
Hyperion/WARP interface at high scene signal
levels and provides data to determine the
presence of signal dependent noise - Configuration also allows verification of the ALI
aperture cover redundant deployment mechanism
(HOPAs) - Configuration also allowed for the change out of
the HSA connector post prior to start of test - Configuration (Satellite mounted on Aronson table
in SSDIF) - ALI Hyperion ambient imaging test and Hyperion
VNIR characterization - Satellite mounted on Aronson table in the
horizontal configuration (X down), instruments
aligned to the MIT/LL optical bench (used at
MIT/LL during ALI instrument level verification)
34End-To-End Instrument Test
- Results
- ALI aperture cover mechanisms and HOPAs were
inspected and verified to the extent possible
(note one PR was written subsequent test
verified remaining HOPAs) - ALI and Hyperion optical performance is
consistent with pre-satellite environmental
performance measured at MIT/LL and TRW - no
significant change in image quality - Hyperion VNIR characterization was performed
successfully, but max signal level limited to
approx. 1500 counts. Analysis in progress. ALI
reports NO effect from Hyperion observing noisy
scene (chopper test). - Conclusion
- Both ALI and Hyperion optical performance
NOMINAL. No effect from S/C environmental testing
35End-to-End Instrument Test
36Special Topic EMI / EMC Testing Rationale
37EMI/EMC Testing Requirements
- Based on MIL-STD-461C in accordance with the
procedures of MIL-STD-462 and amplified by the
following documents - NASA/GSFC GEVS, BOEING MELV Mission Spec. and WTR
MSPSP - Provides guidance on acceptable EMI/EMC levels
for the launch site environment - MSFC On-Orbit RF Environment Doc.
- Provides a summary report on radiated emissions
expected at the EO-1 mission orbit - Litton SSO Doc. AM-149-0020(155)
- Provides a specific tailoring of MIL-STD-461C
limits to the EO-1 spacecraft - SAI-SPEC-158, EO-1 Verification Plan and
Environmental Spec. - Specifies the requirements for verification and
test of the EO-1 spacecraft and its components
and subsystems
38Critical EO-1 Subsystems that were tested prior
to S/C IT
39EO-1 Spacecraft-Level EMI/EMC Test Results
40Spacecraft EMI Tests Were Performed to Verify
Compliance With Mission Requirements, and
Subsystem Waivers
- RF Hat Coupler Leakage Test
- Verified acceptable RF levels with transmitters
radiating into hat couplers (80-90 dB?V/M S-band,
62.7 dB ? V/M X-band) - RS testing at GEVS levels
- Verified acceptable susceptibility (up to 5 V/M)
from 1KHz to 12 GHz - RS testing at WTR/MELV levels
- Verified acceptable susceptibility (up to 24 V/M)
from 14KHz to 40 GHz - NB/BB RE testing, per MIL-STD-461C
- Verified acceptable emissions levels(exceedences
observed reflect GSE and instrument noise) - Radiated Self-compatibility testing
- Verified S-Band receivers compatibility with
X-Band transmitter - Transient Tolerance test
- Verifies power bus ripple spec. (1.5 Vpp) under
worst-case operating modes - Power Profile test
- Verifies spacecraft self-compatibility under
various modes of operation
41EO-1 EMI/EMC Testing Summary
- Subsystem testing, per MIL-STD-461/ LSSO
AM-149-0020(155) exceedences observed, but will
not effect performance (waivers generated) - Satellite testing is compliant per GEVS, MSPSP
and Boeing MELVS specs - Some exceedences were observed at RE satellite
level tests, but does not affect satellite or
instrument performance at the launch site, or
on-orbit - Based on testing to date, satellite operates
nominally with all subsystems and instruments in
worst-case modes
After reviewing the satellite performance and the
test data, the project concludes that the
satellite is ready for shipment to the launch
site.
42Waivers
43Waivers
44Waivers
45Waivers
46Waivers
47Waivers
48Special Topic Electrical Testing of Deployables
49Electrical Testing of Deployables
- Reason for Topic
- Verification of sufficient testing of deployables
- Summary of Topic
- Deployables tested at subassembly level (S/A on
test stand with flight HOPS), and spacecraft
level (S/A on spacecraft, spacecraft initiating
deployment). Final testing to include
deployments and verifications of fusing/wiring
changes. - Ramifications of Topic
- Adequate testing of the HOP actuator interfaces
ensure proper deployment of the solar array
on-orbit - Recent configuration change due to the addition
of redundant fusing requires additional testing
50Electrical Testing of Deployables
- Previous testing of Deployables at S/C level
- Array deployed multiple times on test-stand using
EGSE to activate Flight HOPS - Array deployed at Swales prior to shipment to
GSFC (old wiring) with the spacecraft performing
an end-to-end validation - Array pop and catch at GSFC following vibration
and acoustic testing (old wiring) with the
spacecraft performing an end-to-end validation - Multiple testing of electrical deployment
circuits using HOP simulator (old wiring) which
fully tests circuits and software - Testing of electrical deployment circuits during
TVAC (old wiring) using HOP simulator
51Electrical Testing of Deployables
- Planned testing of Deployables at S/C level
- Following completion of new wiring the entire
flight interface will be tested to verify
functionality of both primary and redundant paths
on the flight hardware using GSE which simulates
the HOP loads (12/3/99) - All fuse plugs will be tested with the system,
verifying actuator motion on both primary and
redundant sides (week of 1/10/00 or earlier) - The remaining solar array deployment will be
conducted with the flight fuse plugs installed,
on the redundant side with no EGSE in the loop
(at launch site) - Conclusions
- Remaining testing planned will guarantee system
functionality on-orbit - Finish with pop and catch at VAFB on February
23, 2000
52EO-1 Deployment History