PSR Section 3 - PowerPoint PPT Presentation

1 / 52
About This Presentation
Title:

PSR Section 3

Description:

1773 tests: bus buster/SEU and optical performance (special GSE) ... Spacecraft lifted off dolly and suspended by chamber crane ... – PowerPoint PPT presentation

Number of Views:86
Avg rating:3.0/5.0
Slides: 53
Provided by: mikeperryt
Category:
Tags: psr | buster | dolly | section

less

Transcript and Presenter's Notes

Title: PSR Section 3


1
Section 3 Verification Process
. . . Mark Perry Swales Aerospace
2
Verification Process Agenda
  • Environmental Test Approach
  • Verification Matrix
  • Satellite Environmental Test Flow
  • Satellite Environmental Test Documentation
  • Summary of Satellite and Component Test Time
  • Functional and Performance Testing
  • Environmental Testing Overview
  • LV Separation Shock / Vibration
  • Acoustics
  • EMI/EMC
  • Magnetic Survey
  • RF Compatability
  • Thermal Balance/Thermal Vacuum
  • Alignment
  • Mass Properties
  • X-Band Near Field Assessment
  • End to End Instrument Optical Testing

3
Environmental Test Approach
  • EO-1 Verification Process is described in the
    EO-1 Verification Plan and Environmental
    Specification (SAI-SPEC-158)
  • Verification Matrix identifies the box and system
    level testing
  • Some flight box level testing was deferred to
    observatory level testing based on qualification
    by similarity or a second in a series of like
    hardware
  • System level environmental testing was with all
    flight hardware with exception of the flight
    battery or where configuration did not allow
    example the solar array was not included with the
    Observatory during Thermal Vacuum
  • Satellite Environmental Flow comprised the
    following
  • Shock (2) Firings
  • Vibration - 3 axis sine sweep at protoflight
    levels (1.25 x flight limits)
  • Acoustic at protoflight levels
  • EMI/EMC
  • Thermal Balance
  • Thermal Vacuum

4
Final System Level Spacecraft Verification
5
Spacecraft Verification Flow
5/3
5/11
7/14
7/15
7/24
7/26
7/26
7/30
7/31
8/5
8/5
8/6
7/16
7/23
1773 Sensitivity Test
1st CPT (PreShip to GSFC) SA Deployment on S/C
OTDR F/O measurements, S/W Tests
Partial 2nd CPT MOC Tests
Acoustic Test
Weigh Satellite 3 Axes Vibration 2 Shock Tests -
Modal Tap Test AST/IRU Alignment
CPTMOC
Acoustic
CPT
F/O
Modal/Align
Vib/Shock
F/O S/W
8/7
8/8
8/29
9/4
9/5
9/16
9/17
10/1
10/1
10/20
10/30
10/21
8/17
8/19
EMI/ EMC Radiation Emissions Test
M5, RSN, PSE S/W Test Regression Test
TB/TV 4 Cycles - CPT HOT - CPT Cold - MOC
Simulation - Safe Hold 24 Hrs - 1773
Sensitivity - Functional Test
Alignment Measurement
RF Compatibility CPT0-CPT11
S/C Timing Test 1773 Margin Test Functional
Test ACE/XPA/PSE S/W
ACE/XB S/W Load Test
Alignment
RF Compatibility and CPT
EMC
F/O, Timing
S/W
S/W Test
TB TV
11/1
Pre-Ship
11/9
11/17
11/8
11/18
11/30
12/11
11/29
Verification Flow -CPT -F/O Sensitivity -Modal
Survey -Alignment Measurements -Weigh
S/C -Vibration -Shock -Acoustic -RF
Compatibility -EMC/RE -Thermal Balance -Thermal
Vac -Instr End to End - Magnetic Survey
(Static) -EMC/CE -Pre-Ship CPT -Mass Properties
ALI Hyperion ETE Test Hyperion VNIR
Characterization XB NF Test
1773 Bus Buster MOC SIMS
Magnetic Survey RCS Press/Leak EMI/EMC CE Test
Self Compatibility
Pre-Ship CPT
Mass Properties
Ship to WTR
Instrument ETE X-Band Characterize
S/W, MOC Test
EMC
Mass PROPS
CPT
6
Verification Documentation
  • EO-1 Verification Plan Environmental
    Specification SAI-SPEC-158
  • CPT SAI-PROC-679A
  • F/O Sensitivity TD WOA-462
  • 1773 Sensitivity TD WOA-496
  • Alignment SAI-PLAN-206
  • Modal Test SAI-PLAN-341
  • Shock Test SAI-PLAN-341 SAI-PROC-739
  • Vibration Test SAI-PLAN-307 SAI-PROC-739
  • Acoustic Test SAI-PLAN-320
  • RF Compatibility SAI-PLAN-XXX, WOA-410/590 (STDN
    - 408.1)
  • Mass Properties SAI-PLAN-319 (Test Postponed)
  • TB/TV SAI-PLAN-273 SAI-PROC-619
  • Instrument End-to-End SAI-PLAN-358
  • Magnetic Test SAI-PROC-768
  • EMI/EMC Test SAI-PROC-752
  • X-Band Near Field Test SAI-PLAN-368

7
Additional S/C Testing
  • Testing not included in original Verification
    Plan
  • ALI Hyperion End to End Testing (Optical
    Testing)
  • Hyperion VNIR Characterization
  • 1773 Bus Buster Test
  • MV Stress Testing
  • S/C Timing Test
  • X-Band Near-Field Test
  • Post-Environmental Flash Test of Solar Arrays

8
Projected Power On Time
9
EO-1 Functional and Performance Testing
10
CPT Design and Description
  • Goal is to test every function and to measure
    performance for each subsystem and for the
    complete EO-1 system
  • With the exception of some RF and RCS testing,
    all tests are conducted from ASIST STOL
    procedures to facilitate repeatability and reduce
    errors
  • The CPT contains about 100 individual tests.
    These tests were planned to perform as much
    parallel testing as possible without sacrificing
    the integrity of the individual tests.
  • All nominal and critical commands (about 500)
    tested during the CPT
  • The rest of the on-orbit commands are tested
    outside the CPT, such as during
    software-acceptance tests
  • Additional commands, which were used for
    integration, development, test and diagnosis,
    will be deleted from the database.
  • The CPT is comprised of 12 sections, as defined
    in SAI-PLAN-659A

11
CPT Sections
  • Sections 0 and 1 Power-on defaults, launch,
    ascent, deployment, and sun acquisition
  • Sections 2, 5, and 6 Exhaustive s/c tests ACS,
    Power, CDH, RF, S/A drive, deployment
    redundancy
  • Section 3 Non-imaging instrument and WARP
  • Section 4 EFF
  • Sections 7 and 8 Exhaustive imaging
  • Sections 9 and 10 Restart, safemode, and
    load- shedding
  • Section 11 Orbit-timeline

12
Non-CPT System Performance Tests
  • These are special tests that are incompatible
    with the CPT
  • Require special satellite configuration which
    would inhibit other tests
  • Require special GSE
  • Limitations such as maximum pressure cycling
  • Specific Non-CPT Tests
  • End-to-end optical tests verify instrument
    alignment and optics (require EO-1 in a
    horizontal attitude)
  • 1773 tests bus buster/SEU and optical
    performance (special GSE)
  • X-band ACS-to-X-band pointing tests and
    near-field test (special GSE)
  • GPS constellation tests requires special GSE and
    is incompatible with other systems tests using
    ephemeris and time.
  • ACS virtual satellite (simulates ACS components)
    software testing
  • FDC testing TSMs, RTSs, WARP, PSE, and ACS
  • Solar-array mechanical deployment (to exercise
    the s/a array drive and associated software, the
    s/a is not mounted during CPT)
  • RCS pressure testing propulsion tank is limited
    to a few cycles
  • Heater tests requires cold-soak
  • MOC simulation tests system tests in additional
    operational scenarios
  • LFSA and PPT (category III payloads) tested
    separately
  • Flash test of solar arrays (requires special
    equipment and location)

13
Baseline CPT
  • Conducted August 31st to September 4th
  • Generated 160 problem reports, dominated by
    procedure errors
  • 120 PRs defined as procedural errors
  • 20 software errors
  • 3 GSE problems
  • 14 incorrect limits and data-base errors
  • 8 open PRs, 5 are pending verification as of 8
    December 1999
  • Main deficiency of baseline CPT was that final
    flight s/w was not ready
  • PSE (FDCmisc.), HK RSN (GPSmisc.), and TSM/RTSs
    are biggest changes
  • Mitigated by two later CPTs (12/6/99 and 2/00),
    which use final flight software
  • Subsystem reports and analysis
  • Initial problems, mostly software, already
    identified, corrected, and verified
  • Reports and analysis nearly complete all known
    results are nominal no problems discovered that
    require hardware modification

14
Functional Test
  • Used between moves and after environmental tests
    to verify all EO-1 functions
  • Performed after transportation to GSFC and
    planned for after transport to launch site
    (omitted if CPT performed).
  • Performed between vibration and TV tests and
    after TV test.
  • Performed (with some modification) at the launch
    pad
  • Objective is to test every wire and connection on
    EO-1
  • Much of the software is tested as a by-product
  • The functional test is a subset of the CPT tests
  • Maximum use of well-developed tests
  • The functional does not include tests that are
    exclusively performance tests

15
System Testing During Thermal/Vacuum Test
  • Each CPT section conducted at both hot and cold
    plateaus
  • Since hot/cold plateaus are only 24 hours long,
    CPT was not continuous at each plateau
  • Functional conducted during pumpdown and at the
    end, just before chamber break
  • 150 PRs, 80 are closed and verified as of 8
    December 1999
  • All critical PRs closed
  • Nadir-deck heater short was only hardware anomaly
  • Several new software errors discovered
  • Some procedure errors discovered

16
Post-Environmental CPT Preliminary Results
  • Conducted December 6-9, 1999
  • All flight hardware and software configuration
    except
  • LFSA not mounted
  • Will probably modify HK RSN software
  • Will fuse LVPC non-critical power services
  • Several table parameters to be modified for
    flight (telemetry filter, TSM, RTS)
  • Except as noted in PRs, all results reviewed to
    date are nominal
  • 20 PRs initial assessment (through CPT5)
  • 6 were procedure or operator errors (already
    corrected)
  • 4 were nominal conditions initially perceived as
    problems
  • 4 GSE problems (3 FEDS and 1 GPS simulator)
  • No hardware problems
  • 5 PRs were software problems
  • Unexpected safehold entry due to M5 warmstarts (2
    PRs)
  • Deployment may re-start if HK RSN has a warm
    start (statistics are 1-in-50 known cause not
    necessary to fix)
  • Unexpected WARP error (status?)
  • 1 RTS-table error
  • 1 not investigated

17
Environmental Testing Overview
18
LV Separation Shock
  • Test Configuration (Building 7 Test Cell 040 )
  • Flight-Type Payload Attach Fitting Clamp Band
    System (Boeing)
  • Spacecraft supported from crane and PAF dropped
    on to foam pad
  • Spacecraft fully configured and powered in
    launch mode
  • Hyperion and LFSA not electrically integrated
    (not powered during launch)
  • Thirty one tri-axial accelerometers used to
    monitor shock levels
  • Time History plots
  • Shock response Spectra Plots, Q10, 100-2000Hz
  • Two Firings performed
  • Results
  • All responses, with exception of two on Nadir
    deck, well within specified environments
  • Conclusions
  • Environment benign
  • Aliveness test indicated no anomalies

19
Vibration Test
  • Test Configuration (Building 7 Test Cell 040 )
  • Flight-Type Payload Attach Fitting Clamp Band
    System (Boeing)
  • MAP Spacecraft vibration test fixture (force ring
    transducers)
  • Spacecraft fully configured and powered in
    launch mode
  • Thirty three tri-axial accelerometers used to
    monitor shock levels
  • Three axis sine sweep vibration to protoflight
    levels (1.25 x Flight Limit Loads)
  • Results
  • No physical damage to structure No shift in
    Frequency pre- versus post-vib
  • Conclusions
  • Spacecraft Structure qualified for flight
  • Coupled Loads Analysis model updated and
    submitted to Boeing for VLC base banding
    (fundamental freq. increased over predicts)
  • Verification Coupled Loads results confirm all
    margins positive
  • Aliveness test indicated no anomalies

20
Acoustic Test
  • Configuration (Building 7 Acoustic Chamber)
  • Spacecraft lifted off dolly and suspended by
    chamber crane
  • Thirty three tri-axial accelerometers used to
    monitor shock levels
  • Spacecraft fully configured and powered in
    launch mode
  • Boeing Delta 7320-10 Levels (Overall 141.1 dB)
  • Protoflight levels (one minute duration)
  • Results
  • No physical damage to structure
  • Protoflight level achieved (within tolerance)
  • Responses well within specified component test
    levels
  • Conclusions
  • Spacecraft Structure qualified for flight
  • Aliveness test indicated no anomalies

21
EMI/EMC Test
  • Configuration
  • Spacecraft fully configured with exception of
    solar array removed
  • Radiated Emissions Testing Radiated
    Susceptibility (GEVS Range/ELV) Testing
    performed in GSFC EMI facility (performed pre TV)
  • Power Profile Testing Conductive Emissions
    Testing performed in EO-1 Clean Tent (Performed
    post-TV)
  • Results
  • RE RS fully characterized and all exceedences
    documented
  • CE fully characterized and all exceedences
    documented
  • RF Hat Coupler Leakage tested and verified
  • Conclusions
  • All appropriate Waivers generated and evaluated
    as acceptable
  • See Special Topic at the end of this section

22
Magnetic Survey Test
  • Configuration
  • Basis of Test Procedure was ACE, TRMM, WIND,
    Polar and XTE
  • Static magnetic field measure via fixed
    magnetometers setup by GSFC Magnetics Group. Test
    conducted by GSFC MAG
  • Performed in Building 29 SSDIF
  • Performed during period of low activity in
    facility to reduce background magnetic noise
    levels
  • Spacecraft suspended by crane using specially
    designed sling that minimized use of magnetic
    parts and which maximized distance from crane
    hook (14ft)
  • Results
  • Total Static (DC) magnetic field of Satellite
    fully characterized
  • Conclusion
  • DC Magnetic dipole of 9Am2 is higher than
    expected
  • Magnetic Torque Bars have sufficient margin to
    compensate -- analysis in process

23
RF Compatibility Test
  • Configuration (S-Band X-Band RF Hat Coupler to
    Compatibility Test Van)
  • Demonstrated the operational capability of the
    command, telemetry and tracking data
    communications interface between the Ground
    Network (GN), Space Network (TDRSS), and Mission
    Operations Center
  • Spaceflight Tracking Data Network (STDN-408.1)
    Procedure used
  • Phase 1 RF Network Compatibility Testing WOA-410
  • Measure the physical characteristics (Group
    delay, frequency, Bit Error Rate, carrier
    suppression) of the EO-1 RF System SN/GN via
    CTV only
  • Phase 2 RF End-to-End System Test RF TDRSS
    Compatibility Test WOA-590 (CTV used as the
    interface between the spacecraft MOC)
  • Verify that the MOC has the capability of
    commanding the spacecraft and receiving real-time
    playback housekeeping telemetry through the GN
  • Verify that real time housekeeping telemetry may
    be received by the MOC at 2Kbps over the SN

24
RF Compatibility Test
  • Results
  • All S-Band X-Band characteristics verified
  • Awaiting final CTV Test report
  • Conclusion
  • EO-1 RF Subsystem is compatible with the Ground
    Network Space Network

25
Thermal Balance /Thermal Vacuum Test
  • Configuration (Building 7 Thermal Test Chamber
    238)
  • EO-1 Satellite fully configured (LFSA not
    electrically integrated non-flight
    calorimeters) with all flight MLI Thermal
    blankets installed
  • Demonstrate that the EO-1 Satellite and payloads
    can operate satisfactorily in all functional
    modes for the mission, at 10C beyond the hot
    cold extremes predicted for orbit
  • Perform a complete Comprehensive Performance Test
    the hot cold plateau (distributed). Perform
    additional Performance tests throughout TB/TV
  • Demonstrate the EO-1 satellite operates
    satisfactory in safe hold (24 hours)
  • Demonstrate satisfactory operation of the EO-1
    Spacecraft and payload thermal control systems
  • Verify the EO-1 Spacecraft and payload thermal
    models
  • Verify the EO-1 Satellite meets contamination
    requirements
  • Assess Instrument self-contamination and outgas,
    if necessary
  • Provide opportunity for MOC to run flight
    operations procedures

26
Thermal Balance Thermal/Vacuum Test
27
Thermal Balance Thermal Vacuum Test
28
Thermal Balance Thermal Vacuum Test
  • Results
  • All objectives met
  • Nadir Deck Heater Service Anomaly (see Special
    Topics)
  • Demonstrated nominal operation of EO-1 Spacecraft
    and payloads at temperature extremes
  • Demonstrated TCS for Satellite and payloads
  • Excellent correlation with Satellite Thermal Math
    Model
  • Contamination of EO-1 Satellite demonstrated to
    be well within limits however ALI out-gassing
    phenomenon which occurred during payload testing
    materialized at Satellite level. Impacts initial
    On-Orbit bake-out planned
  • Conclusion
  • EO-1 Satellite qualified for On-Orbit operation
  • Post Thermal Vacuum Functional test was nearly
    flawless

29
Alignment
  • Pre Environmental
  • Alignment Characterization performed at the
    Spacecraft Bus level to establish primary
    reference frame
  • Map Master Reference Cube (MRC) and S/C primary
    datums
  • Map Secondary Reference Cube (SRC) on IRU to IRU
    Primary Reference Cube
  • Map MRC to SRC
  • Alignment Performed at Satellite Level
  • ALI AC co-aligned to within 2 Arc-minutes
  • Post Environmental
  • IRU/SRC to AC co-alignment verified following
    vibration (no measurable movement - lt15 arcsec)
  • AC to AST alignment verified post vibration
    (measurable rotation shift assessed)
  • IRU SRC will be mapped to the S/C MRC AST
    reference cubes at WTR
  • ALI HSA reference cubes will be mapped to the
    S/C MRC at WTR
  • AST to S/C MRC will be mapped to the S/C MRC at
    WTR

30
Mass Properties
  • Configuration (performed prior to shipment using
    Miller Mass Props Table)
  • EO-1 Satellite mass has been measured several
    times throughout environmental program
  • 98.4 of components measured (Hydrazine Fuse
    Plugs)
  • Projected total mass of 573 Kg is 15 Kg under
    flight allocation (588 Kg)
  • Detail Solid model (PRO-E model) used to
    calculate CG and inertia values prior to
    verification on Miller Table
  • X Y CG values to be measured Z CG value to be
    calculated using Solid Model
  • Results
  • Total Mass allocation met
  • CG requirement is projected to be within
    established requirement

31
X-Band Phase Array Near Field Test
  • Configuration (Performed in Building 29 SSDIF)
  • Performed at component and Satellite level
  • Satellite level testing performed while in
    Horizontal Configuration on Arronson Table
  • Satellite fully configured
  • Verify Antenna Pattern Effective Isotropic
    Radiated Power (EIRP)
  • Verify Attitude Control System can dynamically
    command the antenna to known beam positions
  • Results
  • Antenna pattern consistent with component level
    pre-environmental
  • EIRP measured at 57 dBm meets requirement
  • Demonstrated ACS can dynamically command antenna
    beam to known position
  • Conclusion
  • X-Band Phase Array performance verified at the
    Satellite level

32
X-Band Phase Array Near Field Test
NF Scanner in Position in Front of the XPAA
During NF3
33
End-To-End Instrument Test
  • Objective
  • Demonstrate that the ALI and Hyperion survived
    the environmental test program without
    degradation to the imaging quality.
  • Hyperion VNIR characterization test exercises the
    Hyperion/WARP interface at high scene signal
    levels and provides data to determine the
    presence of signal dependent noise
  • Configuration also allows verification of the ALI
    aperture cover redundant deployment mechanism
    (HOPAs)
  • Configuration also allowed for the change out of
    the HSA connector post prior to start of test
  • Configuration (Satellite mounted on Aronson table
    in SSDIF)
  • ALI Hyperion ambient imaging test and Hyperion
    VNIR characterization
  • Satellite mounted on Aronson table in the
    horizontal configuration (X down), instruments
    aligned to the MIT/LL optical bench (used at
    MIT/LL during ALI instrument level verification)

34
End-To-End Instrument Test
  • Results
  • ALI aperture cover mechanisms and HOPAs were
    inspected and verified to the extent possible
    (note one PR was written subsequent test
    verified remaining HOPAs)
  • ALI and Hyperion optical performance is
    consistent with pre-satellite environmental
    performance measured at MIT/LL and TRW - no
    significant change in image quality
  • Hyperion VNIR characterization was performed
    successfully, but max signal level limited to
    approx. 1500 counts. Analysis in progress. ALI
    reports NO effect from Hyperion observing noisy
    scene (chopper test).
  • Conclusion
  • Both ALI and Hyperion optical performance
    NOMINAL. No effect from S/C environmental testing

35
End-to-End Instrument Test
36
Special Topic EMI / EMC Testing Rationale
37
EMI/EMC Testing Requirements
  • Based on MIL-STD-461C in accordance with the
    procedures of MIL-STD-462 and amplified by the
    following documents
  • NASA/GSFC GEVS, BOEING MELV Mission Spec. and WTR
    MSPSP
  • Provides guidance on acceptable EMI/EMC levels
    for the launch site environment
  • MSFC On-Orbit RF Environment Doc.
  • Provides a summary report on radiated emissions
    expected at the EO-1 mission orbit
  • Litton SSO Doc. AM-149-0020(155)
  • Provides a specific tailoring of MIL-STD-461C
    limits to the EO-1 spacecraft
  • SAI-SPEC-158, EO-1 Verification Plan and
    Environmental Spec.
  • Specifies the requirements for verification and
    test of the EO-1 spacecraft and its components
    and subsystems

38
Critical EO-1 Subsystems that were tested prior
to S/C IT
39
EO-1 Spacecraft-Level EMI/EMC Test Results
40
Spacecraft EMI Tests Were Performed to Verify
Compliance With Mission Requirements, and
Subsystem Waivers
  • RF Hat Coupler Leakage Test
  • Verified acceptable RF levels with transmitters
    radiating into hat couplers (80-90 dB?V/M S-band,
    62.7 dB ? V/M X-band)
  • RS testing at GEVS levels
  • Verified acceptable susceptibility (up to 5 V/M)
    from 1KHz to 12 GHz
  • RS testing at WTR/MELV levels
  • Verified acceptable susceptibility (up to 24 V/M)
    from 14KHz to 40 GHz
  • NB/BB RE testing, per MIL-STD-461C
  • Verified acceptable emissions levels(exceedences
    observed reflect GSE and instrument noise)
  • Radiated Self-compatibility testing
  • Verified S-Band receivers compatibility with
    X-Band transmitter
  • Transient Tolerance test
  • Verifies power bus ripple spec. (1.5 Vpp) under
    worst-case operating modes
  • Power Profile test
  • Verifies spacecraft self-compatibility under
    various modes of operation

41
EO-1 EMI/EMC Testing Summary
  • Subsystem testing, per MIL-STD-461/ LSSO
    AM-149-0020(155) exceedences observed, but will
    not effect performance (waivers generated)
  • Satellite testing is compliant per GEVS, MSPSP
    and Boeing MELVS specs
  • Some exceedences were observed at RE satellite
    level tests, but does not affect satellite or
    instrument performance at the launch site, or
    on-orbit
  • Based on testing to date, satellite operates
    nominally with all subsystems and instruments in
    worst-case modes

After reviewing the satellite performance and the
test data, the project concludes that the
satellite is ready for shipment to the launch
site.
42
Waivers
43
Waivers
44
Waivers
45
Waivers
46
Waivers
47
Waivers
48
Special Topic Electrical Testing of Deployables
49
Electrical Testing of Deployables
  • Reason for Topic
  • Verification of sufficient testing of deployables
  • Summary of Topic
  • Deployables tested at subassembly level (S/A on
    test stand with flight HOPS), and spacecraft
    level (S/A on spacecraft, spacecraft initiating
    deployment). Final testing to include
    deployments and verifications of fusing/wiring
    changes.
  • Ramifications of Topic
  • Adequate testing of the HOP actuator interfaces
    ensure proper deployment of the solar array
    on-orbit
  • Recent configuration change due to the addition
    of redundant fusing requires additional testing

50
Electrical Testing of Deployables
  • Previous testing of Deployables at S/C level
  • Array deployed multiple times on test-stand using
    EGSE to activate Flight HOPS
  • Array deployed at Swales prior to shipment to
    GSFC (old wiring) with the spacecraft performing
    an end-to-end validation
  • Array pop and catch at GSFC following vibration
    and acoustic testing (old wiring) with the
    spacecraft performing an end-to-end validation
  • Multiple testing of electrical deployment
    circuits using HOP simulator (old wiring) which
    fully tests circuits and software
  • Testing of electrical deployment circuits during
    TVAC (old wiring) using HOP simulator

51
Electrical Testing of Deployables
  • Planned testing of Deployables at S/C level
  • Following completion of new wiring the entire
    flight interface will be tested to verify
    functionality of both primary and redundant paths
    on the flight hardware using GSE which simulates
    the HOP loads (12/3/99)
  • All fuse plugs will be tested with the system,
    verifying actuator motion on both primary and
    redundant sides (week of 1/10/00 or earlier)
  • The remaining solar array deployment will be
    conducted with the flight fuse plugs installed,
    on the redundant side with no EGSE in the loop
    (at launch site)
  • Conclusions
  • Remaining testing planned will guarantee system
    functionality on-orbit
  • Finish with pop and catch at VAFB on February
    23, 2000

52
EO-1 Deployment History
Write a Comment
User Comments (0)
About PowerShow.com