JPL Cost Risk Analysis Approach That Incorporates Engineering Realism Updated again for AIAA meeting - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

JPL Cost Risk Analysis Approach That Incorporates Engineering Realism Updated again for AIAA meeting

Description:

All 3 are important when adding distributions through Monte Carlo simulation. ... These values are then combined to form the S-curve by the Monte Carlo tool. ... – PowerPoint PPT presentation

Number of Views:32
Avg rating:3.0/5.0
Slides: 19
Provided by: JPL60
Category:

less

Transcript and Presenter's Notes

Title: JPL Cost Risk Analysis Approach That Incorporates Engineering Realism Updated again for AIAA meeting


1
JPL Cost Risk Analysis Approach That Incorporates
Engineering Realism - Updated again for AIAA
meeting
  • AIAA Economics Technical Committee Meeting -
    January 24, 2007
  • Leigh Rosenberg
  • Corey Harmon
  • Keith Warfield
  • (Previous versions given at 2006 NASA Cost
    Symposium, 2006 ISPA Annual Conference, JPL Risk
    Workshop)

2
Presentation Outline
  • Introduction
  • Use of S-Curves
  • NASA Cost Estimating Handbook Approach
  • JPL Cost Engineering Group Methodology
  • Case Study
  • Current Issues/Future Work

3
Introduction
  • Why are we interested in cost risk analysis?
  • Decision makers want to know the likelihood of
    achieving a particular cost estimate
  • Single point cost estimates fail to capture
    uncertainty in the estimate and cannot provide
    proper context for comparison to other estimates
  • The methodology needs to be well understood and
    justifiable in order to generate likelihood
    statistics (usually, an S-curve) that reflects
    reality

4
Introduction - Continued
  • What is cost risk? Risk due to economic factors,
    rate uncertainties, cost estimating errors, and
    statistical uncertainty inherent in the estimate.
  • What is an S-curve? An S-curve is a statistical
    tool (cumulative density function -- CDF) that
    can portray cost risk.
  • The S-curve should make engineering sense and be
    able to provide realistic inputs to decision
    makers.

5
Introduction - Continued
  • There are 3 elements contributing to risk that
    should be evaluated
  • Uncertainty in cost estimation algorithms
    (accounted for by using validation statistics as
    a basis for standard deviations),
  • Uncertainty in the inputs to the algorithms
    (technical risk),
  • Correlation between WBS elements (cost increase
    in 1 subsystem usually equates to an increase in
    other subsystems).
  • All 3 are important when adding distributions
    through Monte Carlo simulation. If they are not
    assessed, then the resultant S-curve can
    understate the variance of the final cost
    estimate. The S-curve will be too steep
    (unrealistically low variance).

6
Convolution of Different Cost Risk Factors
From NASA Cost Estimating Handbook p.158
7
S-Curves Need to be Realistic
8
2004 NASA Cost Estimating Handbook (CEH)
Approach(Cost Estimating Tasks, pgs. 95-96)
  • CEH discusses method 1 and method 2 for
    generating S-curves.
  • Method 1 Three-point cost distribution
    (typically triangular (min, max, most likely))
    assigned to each WBS element identified as a
    significant risk. Monte Carlo tool then
    transforms individual distributions into a
    project cost S-curve.
  • Method 2 For each WBS element identified as a
    significant risk,worst case (99th percentile)
    costs are elicited instead. These values are then
    combined to form the S-curve by the Monte Carlo
    tool.
  • JPL Cost Engineering Group (CEG) does not exactly
    conform to either.
  • CEG uses a log-normal distribution instead of
    three-pointed. Log-normal eliminates problem of
    guessing at highest possible cost for missions
    that usually have significant unknown unknowns
    and that are using new technologies. Log-normal
    also closely resembles distributions of actual
    costs that were studied at JPL.
  • 99th percentile (and other high percentages) are
    not used by CEG because project designers are
    usually far too optimistic in the early design
    stages.

9
CEG Methodology - Distributions
  • CEG uses log-normal distributions
  • Eliminates problem of guessing at highest
    possible cost
  • Fits historical cost growth of JPL missions
  • Assumes point estimate is the mean of distribution

Cost Growth of JPL Missions
Cost Growth within a JPL Project
10
Cost Growth History
  • Used to validate average variance to be used in
    cost risk analysis
  • Recent study based on 15 JPL projects
  • Tracked cost growth from proposal/Phase A
    estimate, to actuals and/or estimates through
    2005.

11
Overrun vs. Original Project Budget for JPL
Missions (w/Res, no LV)
The variance in overruns has been large.
12
Cost Engineering Group Methodology
  • Point estimates are usually generated at the
    subsystem level by PMCM or PCAT.
  • Distributions are applied to subsystem-level
    point estimates.
  • Standard deviation is typically 25-35
  • Based on comparisons of model costs to actual
    costs with the observed uncertainty used as the
    variance.
  • For WBS items that are not well defined, a higher
    variance may be used
  • Log-normal distribution assumed
  • Log-normal eliminates problem of guessing at
    highest possible cost for unique space missions
  • Log-normal closely resembles observed cost
    distributions.
  • Correlation applied prior to adding distributions
    together
  • Correlation has been found to be 40-60 between
    all WBS items
  • Correlation is present since subsystem designs
    are usually related to each other to some degree.
  • Examples dual redundancy on one subsystem
    generally means dual redundancy for the other
    subsystems on the same spacecraft. A schedule
    delay on one subsystem is a schedule delay for
    all the other subsystems.
  • Such a correlation gives a variance that is
    consistent with results found in comparisons to
    the results of JPL missions/proposal cost
    studies.
  • PMCM - JPL Parametric Mission Cost Model
  • PCAT - JPL Project Cost Analysis Tool

13
Cost Engineering Group Methodology - Continued
  • Total WBS cost is calculated through Monte Carlo
    simulation
  • Original project estimate, and 70 (or other
    chosen) level of confidence estimate are then
    found on generated S-curve
  • Reserves are recommended to move estimate to 70
    level of confidence, in accordance with NASA
    requirements (2004 NASA CEH, pg. 93)
  • Note Since input technical ranges are not
    usually included the resultant curve could
    understate the resulting standard deviation. PMCM
    does allow for input ranges and distributions.

14
Case Study Methodology
  • Used _at_Risk software package.
  • Variances assigned according to Input Reserve
    Risk provided in example.
  • Monte Carlo simulation is run on each cost
    element.
  • 5000 iterations
  • Correlation matrix set to 60 between all WBS
    items
  • S-Curve Analysis
  • Original project estimate is at a 39 level of
    confidence (LOC)
  • 16 reserves recommended for project estimate to
    achieve 70 LOC
  • Standard deviation of S-curve is 16
  • Caveats
  • Case study includes launch vehicle. This cost is
    usually outside the control of the project.
  • Model or technical uncertainty not determinable
    in case study.
  • Deriving risk from project budget omits technical
    evaluation of risk. Technical risk should be
    based on the design should be determined before
    budget is compiled. Purpose of cost risk
    assessment is to determine risk of the budget
    proposed, not from the budget.

15
Case Study Inputs
16
Case Study Cost Risk S-Curve (CDF)
17
S-Curves with Same Assumptions
  • Using identical assumptions, results are nearly
    identical for various methods
  • Difference between results is from underlying
    assumptions, not the methodology used to
    calculate the s-curve

18
Current Issues
  • Use of other distributions (i.e. triangular,
    normal)
  • Triangular requires upper lower bounds which
    are usually not calculable on outputs and may put
    an artificial upper bound on an estimate.
  • Normal may allow for unusual/impossible case of a
    below zero cost.
  • Inclusion of model technical variance needs to
    be more widely better implemented.
  • Variance ranges need to be defined for all WBS
    elements.
  • Example New technology or instrument 50
    variance
  • Better correlation statistics are needed.
  • Start with determining general correlations
    between level 1 WBS items (PM, MA, S/C, etc.)
  • Can use historical data gathered from CADRe
    and/or Team X to generate a JPL-specific
    correlation matrix.
  • In FY 2007, there is a NASA HQ CAD task at JPL
    to study this.
  • Additional improvements
  • Develop statistics on the growth uncertainty of
    the input parameters to PMCM from historic actual
    data. This will provide a factual basis for
    estimating uncertainty on technical inputs.
Write a Comment
User Comments (0)
About PowerShow.com