INTEGRATIVE MANUFACTURING PLANNING AND CONTROL SYSTEMS

1 / 125
About This Presentation
Title:

INTEGRATIVE MANUFACTURING PLANNING AND CONTROL SYSTEMS

Description:

Auto Regressive Moving Average (ARMA) Models: ARMA(m,n) ... ARMA(2,1) xt = f1 xt-1 f1 xt-2 at - q1at-1. 26. AGGREGATE PRODUCTION PLANNING: ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 126
Provided by: Prof302

less

Transcript and Presenter's Notes

Title: INTEGRATIVE MANUFACTURING PLANNING AND CONTROL SYSTEMS


1
INTEGRATIVE MANUFACTURING PLANNING AND CONTROL
SYSTEMS
  • ME 445INTEGRATED MANUFACTURING SYSTEMS

2
MANUFACTURING PLANNING AND CONTROL SYSTEM
  • The primary objective of an manufacturing
    planning and control system (MPCS) in any
    organization is to ensure that the desired
    products are manufactured
  • at the right time,
  • in the right quantities,
  • meeting quality specifications, and
  • at minimum cost.

3
The manufacturing planning and control system
(MPCS) in a company is achieved by integrating
the activities as
  • determining product demand,
  • translating product demand into feasible
    manufacturing plans,
  • establishing detailed planning of material flows,
  • capacity to support the overall manufacturing
    plans, and
  • helping to execute these plans by such actions as
  • detailed cell scheduling
  • purchasing

4
The benefits achieved through the use of
integrated MPCS are
  • reduced inventories
  • reduced capacity
  • reduced labor costs
  • reduced overtime costs
  • shorter manufacturing lead time
  • faster responsiveness to internal and external
    changes as
  • machine and other equipment failure
  • product mix
  • demand changes
  • etc.

5
The major elements of a integrated MPCS are
  • Demand management
  • Aggregate production planning
  • Master production scheduling
  • Rough-cut capacity planning
  • Material requirement planning
  • Capacity planning
  • Order release
  • Shop floor scheduling and control

6
A Basic Frame Work of MPCS
Customer Orders
Demand Management
Aggregate Production Plannig
Engineering Design
Master Production Schedule
Engineering Changes
Rough-Cut Capacity Planning
Material Requirement Planning
Bill of Materials
Inventory Management
Detailed Capacity Planning
Process Planning
Shop-Floor Control
Purchasing
Vendors
Finished Products
7
DEMAND MANAGEMENT
  • Demand for products is the driving force for any
    production activity.
  • Demand management is therefore an important input
    to production planning.

8
  • Demand management contains activities as
  • demand forecasting
  • order transaction entry
  • customer-contact activities
  • physical distribution management

9
  • Demand forecasting
  • Forecasting is concerned with estimating future
    demand ( or requirement) for products.
  • Forecasting is necessary for production planning.

10
  • There are three approaches to forecasting
  • The qualitative approach
  • The explanatory approach
  • The descriptive approach

11
  • 1. Qualitative approaches rely on the opinion of
    experts to predict certain events of interest.
  • Example What kind of technological
    breakthroughs are possible in the field of
    personal computers by the year 2020?
  • There are some prediction techniques for long
    range planning, like, 5, 10, 15 or 20 years.

12
  • 2. Econometric models are example for
    explanatory approaches. Causal relationship is
    an important aspect of this approach.
  • Example Growth in economic activity increases
    employment, which in turn increases the buying
    power of the people, which in turn increases the
    demand.
  • Econometric models have been used successfully
    for planning and resource allocations for
    national economies.

13
  • 3. Descriptive approaches to forecasting include
    statistical models.
  • The basic assumption in these approaches is that
    the underlying demand-generating process is an
    extension of its past performance into the near
    term future. Planning horizon normally varies
    from months to a year.
  • The demand history in the form of time series
    is used to predict the future.

14
  • Moving average
  • A simple time series model may be
  • xt a0 et a0 constant (average
  • value)
  • et a random variable with zero mean and
    variance of st2 (error)
  • xt demand observations through
    period t (t 1, 2, .., T)

15
The forecast for any future period considering
only N recent observations is given by
  • Mt average of the most recent N observation

16
EXAMPLE
  • In the last 7 days the demand for spark plugs
    (in boxes) for four cylinder cars was
  • x120, x226, x319, x424, x523, x621, x728.
  • Each box contain 250 spark plugs. Develop a
    forecast for the 8th day.

17
The 7-day moving average is
18
The forecast for the next day is
19
Now suppose the actual demand for the 8th day is
34 then x1 is dropped and x8 is added to obtain
the new moving average. Accordingly,
20
Therefore, the forecast for the next day is
21
Exponential smoothing
  • In exponential smoothing more weight is attached
    to the recent data and the weight decreases with
    the age of the old data.

where xT the actual demand for period
T ST smoothed statistic for period T ST-1
average of the demand of the first (T-1)
period a weight (usually between 0.1 and 0.3)
22
EXAMPLE
  • ABC Company manufactures a large variety of
    high-pressure steel cylinders for its domestic
    and defense market.
  • ABC wishes to forecast the number of cylinders
    per week for one of their recent product.
  • The data is as follows

23
Forecast the demand for the 11th week using
exponential smoothing by using a 0.2
24
  • Auto Regressive (AR) models
  • AR(m) model
  • xt f1 xt-1 f1 xt-2 fn xt-m at
  • AR(1) model
  • xt f1 xt-1 at
  • Model for IBM stocks (random walk)
  • xt 0.999 xt-1 at

25
Auto Regressive Moving Average (ARMA) Models
  • ARMA(m,n)
  • xt f1 xt-1 f1 xt-2 fn xt-m at
  • q1at-1 -q2 at-2 -- qn at-n
  • ARMA(2,1)
  • xt f1 xt-1 f1 xt-2 at - q1at-1

26
AGGREGATE PRODUCTION PLANNING
  • In a high-variety, discrete manufacturing
    environment, demand for product may fluctuate
    considerably.
  • On the other end, the resources of the company
    (number of machines, number of workers, etc.)
    remain constant during the planning horizon
    (normally 12 months).
  • The best approach to obtain feasible solutions
    is to aggregate the information being processed.

27
  • For aggregation purposes the product demand
    should be expressed in a common measurement unit
    such as production hours.
  • Production planning is concerned primarily with
    determining optimal production, inventory, and
    work force levels to meet demand fluctuation.

28
  • Basic strategies to absorb the demand
    fluctuations are
  • Maintain uniform production rate and absorb
    demand fluctuations.
  • Maintain work force but change the production
    rate by permitting planned overtime, idle time
    and subcontracting.
  • Change the production rate by changing the size
    of the work force through planned hiring and
    layoffs.
  • Explore the possibility of planned backlogs if
    customers are willing to accept delays in
    delivery of products .
  • A suitable combination of these strategies should
    be explored to develop an optimal aggregate
    production plan.

29
EXAMPLEData on the expected aggregated sales of
three products, A, B, and C, over planning
horizon of six 4-week periods are as follows
30
Data on the aggregate demand forecast in
cell-hours is given in the table below
31
  • The company has developed machining cell-hours
    as a common unit for aggregation purposes.
  • Product A 2 cell-hours/unit
  • Product B 2 cell-hours/unit
  • Product C 1 cell-hours/unit
  • The company has the regular production capacity
    of 300 units/period.
  • Overtime is allowed up to 60 units/period.
  • Requirements exceeding overtime capacity may be
    satisfied by subcontracting.

32
  • Two alternative production policies are
    developed as follows
  • PLAN 1 Produce at the constant rate
  • of 350 units/period for the
  • entire planning horizon
  • PLAN 2 Produce at the rate of 400
  • units/period for the first 4 periods and
    then at the rate of 250 units/period for the
    subsequent periods.
  • Analyze these two aggregate production plans.

33
PLAN 1 Uniform Regular Production Rate Policy
34
PLAN 2 Varying Regular Production Rate Policy
35
MASTER PRODUCTION SCHEDULE
  • The primary use of an aggregate production plan
    is to level the production schedule so that the
    production costs are minimized.
  • However, the output of an aggregate plan does
    not indicate individual product. This means that
    the aggregated plan must be disaggregated into
    individual product. The result of such a
    disaggregation methodologies is what is known as
    master production schedule.

36
  • Master production schedule does not present an
    executable manufacturing plan. Because the
    capacities and the inventories have not been
    considered in this stage.
  • Therefore, further analysis for the material and
    capacity requirements is required to develop an
    executable manufacturing plan.

37
ROUGH-CUT CAPACITY PLAN
  • The objective of rough-cut capacity planning is
    to ensure that the master production schedule is
    feasible.
  • For each product family the average amount of
    work needed and key work centers unit can be
    calculated from each items bill of materials and
    from production routings (process planning
    sheets).

38
EXAMPLE
  • Consider two families of steel cylinders and the
    resource profile developed in standard hours of
    resources per 200 units of end-product family as
    follows

39
  • The available resources are compared with the
    resource requirements profile obtained for all
    the work centers considering all the product
    families.
  • If the available resources are less than
    required, then decisions related to overtime,
    subcontracting, hiring workers must be made.

40
MATERIAL REQUIREMENTS PLANNING
  • The material requirements planning system is
    essentially an information system consisting of
    logical procedure for managing inventories of
    component assemblies, subassemblies, parts, and
    raw materials in a manufacturing environment.
  • The primary objective of an MRP system is to
    determine how many of each item in the bill of
    materials must be manufactured or purchased and
    when.

41
  • The key concept used in determining material
    requirements are
  • Product structure and bill of materials
  • Independent versus dependent demand
  • Parts explosion
  • Gross requirement
  • Common-use items
  • Scheduled receipts
  • On-hand inventories
  • Net requirements
  • Plant order releases
  • Lead time

42
Product structure and Bill of Materials
  • Product is the single most important identity in
    an organization. A product may be made from one
    or more assemblies, subassemblies and components.
  • A bill of material is an engineering document
    that specifies that the components and
    subassemblies required to make each end item
    (product).

43
EXAMPLE
E1 End item
Level 0 (end item)
S1 (1)
S2 (2)
Level 1 (subassemblies)
C1 (1)
C2 (2)
C3 (2)
C4 (3)
C5 (1)
Level 2 (components)
Material M1 (1)
Material M2 (1)
Material M3 (2)
Material M4 (2)
Material M5 (1)
Level 3 (raw materials and other components)
44
Independent versus Dependent Demand
  • The demand for the end item originates from
    customer order and forecasts.
  • Such a demand for end items and spare parts is
    called independent demand. The demand by a parent
    item for its components is called dependent
    demand.

45
EXAMPLE
  • X independent demand (number of end item)
  • Y number of components for each end item
  • XY dependent demand (number of subassembly
    demanded)

46
Parts Explosion
  • The process of determining gross requirements
    for component items, that is requirements for the
    subassemblies, components, and raw materials for
    a given number of end-item units is known as
    parts explosion.
  • Part explosion represents the explosion of
    parents into their components.

47
Gross Requirements of Component Items
  • Gross requirement of component items is the
    total number of component items required to
    manufacture the end products. Gross requirement
    of component items is computed by using the
    information from the product information and the
    bill of materials.

48
EXAMPLE
  • If the demand for end-item E1 is 50, determine
    the gross requirements for the item components.

49
Level 0 (end item)
E1 End item
Level 1 (subassemblies)
S1 (1)
S2 (2)
C1 (1)
C2 (2)
C3 (2)
C4 (3)
C5 (1)
Level 2 (components)
Material M1 (1)
Material M2 (1)
Material M3 (2)
Material M4 (2)
Material M5 (1)
Level 3 (raw materials and other components)
Demand of S1 1 x demand of E1 50 units Demand
of S2 2 x demand of E1 100 units Demand of C1
1 x demand of S1 50 units Demand of C2 2 x
demand of S1 100 units Demand of C3 2 x
demand of S2 200 units Demand of C4 3 x
demand of S2 300 units Demand of C5 1 x
demand of S2 100 units
50
Common-Use Items
  • They are the component items which are used
    different subassemblies of different
    end-products. These items must be added to have
    more economic purchasing.

51
On-Hand Inventory, Scheduled Receipts, and Net
Requirements
  • On-hand inventory is the available items in
    stock from the previous period.
  • Scheduled receipt is the items already been
    ordered but not been received from the vendors
    yet.
  • Net requirements is found by subtracting the
    on-hand inventory and scheduled receipts from the
    gross requirements.

52
Planned Order Release
  • Planned order releases refer to the process of
    releasing a lot of every component item for
    production or purchase. Determination of lot size
    is an economic issue. The trade off is between
    the inventory holding costs and the set up costs.
  • Lot sizes in MRP system are determined for
    component items for each stage sequentially
    starting with level 1, then level 2 and so on.

53
Lead Time and Lead Time Offsetting
  • The lead time is the time it takes to produce or
    to purchase a part.
  • The lead time depends on
  • setup time
  • production time
  • lot size
  • sequence of machines on which operations are
    performed
  • queuing delays
  • The purchasing lead time is the time between
    placing an order with a vendor and receipt of the
    order.
  • The manufacture or purchase of component items
    must be offset by at least their lead times to
    ensure availability of these items for assembly
    into their parent items at the desired time.

54
EXAMPLE
55
(No Transcript)
56
(No Transcript)
57
(No Transcript)
58
Economic Order Quantity
  • In order to balance the costs of keeping the
    items in inventory and the costs of setup, the
    concept of Economic Order Quantity (EOQ) is
    introduced.
  • Normally, the ordering policy is set as
    displayed below, where the demand is fairly
    constant

59
Economic Order Quantity
60
  • Based on this kind of inventory policy, the total
    annual inventory cost may be written as

Where TIC total annual inventory
cost (/year) Q order quantity
(pieces/order) Ch holding cost
(/piece/year) Csu cost of setup (/setup or
/order) Da annual demand (pieces /year) Da/Q
number of orders per year (batches of parts
produced per year)
61
  • The holding cost Ch is generally taken to be
    directly proportional to the value of the item
    that is,
  • Ch h Cp
  • where
  • Cp cost per piece (/piece)
  • h annual holding cost rate(year-1)

62
  • The setup cost Csu includes the cost of idle
    production equipment during the changeover time
    between batches, as well as whatever labor costs
    are involved in the setup changes. Thus,
  • Csu Tsu Cdt
  • where
  • Tsu setup or changeover time between
    batches, (hr)
  • Cdt cost rate of machine downtime, (/hr)

63
  • In cases where parts are ordered from an outside
    vendor, the price quoted by the vendor usually
    includes a setup cost, either directly or in the
    form of quantity discounts.
  • Cdt should also include the internal costs of
    placing the order to the vendor.
  • If the cost of production of a part is Cp ,
    then, the annual cost of part production will be
    DaCp.

64
  • Then, the annual total cost is

By taking the derivative of both sides, we obtain
the economic order quantity (EOQ) formula, which
minimizes the sum of carrying costs and setup
costs
where EOQ economic order quantity
(number of parts that should be produced
in the batch)
65
EXAMPLE
  • Annual demand rate is 12,000 units. One unit of
    product costs 10.00 and the holding cost rate is
    24/year. Setting up to produce a batch of
    products requires changeover of equipment, which
    takes 4 hr. The cost of equipment downtime plus
    labor is 100/hr.
  • Determine the economic order quantity and the
    total inventory costs for this case.

66
Solution
  • Setup cost
  • Csu 4 x 100 400
  • Holding cost per unit
  • Ch 0.24 x I0.00 2.40
  • Using these values and the annual demand rate in
    the EOQ formula, we have

67
  • Total inventory costs are given by the TIC
    equation

The annual total production costs TC 12,000
x 10 4800 124,800
68
CAPACITY PLANNING
  • The output of MRP does not produce an executable
    manufacturing plan, because it contains material
    requirement information only but does not contain
    information about the manufacturing capacity of
    the plant.

69
  • To develop an executable manufacturing plan, it
    is essential to establish the feasibility of the
    planned order releases obtained from the MRP
    system.

70
  • Capacity planning is concerned with ensuring the
    feasibility of production plans by determining
    resources such as labor and equipment with a view
    to developing what is known as an executable
    manufacturing plan.

71
  • The process of capacity planning is complex and
    involves a number of decisions
  • Exploring overtime/multiple shifts/subcontracting
    options
  • Developing alternative process plans for
    effective resource utilization
  • Splitting lots
  • Increasing or decreasing employment levels to
    respond to capacity changes
  • Inventory options
  • Increasing capacity by adding capital equipment
    such as machine tools

72
ORDER RELEASE
  • Once an executable manufacturing plans are
    obtained, the orders are released to the shop
    floor.
  • Order release documents should include
  • Material inventories allocated to the order.
  • Routing sheets having information on
  • operation sequences,
  • machines,
  • work centers,
  • tool and fixture allocations,
  • batch sizes,
  • standard machine time allowed for each operation,
    etc.
  • Appropriate shop floor records such as cards,
    move cards, and part lists for assembly jobs.

73
  • The order release triggers a number of
    activities at the shop floor
  • Scheduling of job orders on the work centers.
  • Sequencing of jobs on a work center.
  • Allocation of jigs and fixture.
  • Loading of work centers considering optimal
    cutting conditions (cutting speeds, feed rates,
    depth of cuts).
  • Coordination of material handling, storage,
    warehousing, and machine tools.

74
SHOP FLOOR CONTROL
  • When the planned orders are released to the shop
    floor for manufacturing, the primary objective is
    to deliver the product
  • at the right time,
  • in the right quantities,
  • meeting quality specifications.
  • But some unexpected event (machine breakdown for
    example) may cause delays.
  • In order to take action (changing the scheduling
    for example), the up to date information from the
    shop floor must be send to the management a fast
    and a steady manner.

75
  • A number of methods are used for data collection
    in industries, such as
  • Hand written reports.
  • Manual data entry terminals.
  • Bar code readers and sensors such as optical and
    magnetic reading devices that automatically
    update an items progress through the shop floor.
  • Voice data entry system.

76
  • The major functions of a shop-floor control
    system are
  • to schedule job orders on the work centers,
  • to sequence the jobs in order on a work center,
  • to provide accurate and timely order status
    information.

77
  • The work order status information includes
  • order batch sizes
  • job completion
  • remaining jobs and operations
  • The work order status information is used
  • To monitor the progress of manufacturing
    activities.
  • To determine priorities for scheduling jobs in
    the shop in response to changes in job order
    status.
  • To maintain and control work in process.
  • To provide output data for capacity control
    purposes.

78
Operation scheduling
  • There are two major activities to be performed
    when work orders are released to the shop floor
  • The work orders are assigned to the work centers
    such that due dates are satisfied. Allocation of
    jobs to work centers is referred to as machine
    loading.
  • The sequence of each work order through each work
    center is determined. This process is referred to
    as job sequencing.

79
  • The objectives of operation scheduling are
  • Meeting due dates.
  • Minimizing manufacturing throughput time.
  • Minimizing work-in-process.
  • Maximizing work center utilization.

80
  • To achieve these objectives may be conflicting
    sometimes.
  • For example if we add extra machining centers
  • Meeting due dates improves
  • Minimizing manufacturing throughput time improves
  • Minimizing work-in-process improves
  • Maximizing work center utilization get worse

81
  • The loading time is calculated as
  • Loading time setup time Q unit run time
  • The average manufacturing throughput time (MTT)
    is calculated as
  • MTT setup time Q unit run time move and
    queue time

82
EXAMPLE
Develop a detailed scheduling and loading plan.
83
(No Transcript)
84
Job Sequencing and Priority Rules
  • Normally, the total number of jobs exceed the
    number of work centers. Therefore, priority rules
    should be develop to determine the sequencing of
    machining operations.

85
  • Some of the simple rules used in industry are
  • 1. First-come, first served (FCFS) rule assign
    jobs on a first-come, first- served bases.
  • This rule is blind with respect to all other
    information such as due date and urgent jobs.

86
  • 2. Shortest processing time (SPT) rule gives the
    highest priority to the job with the shortest
    processing time.
  • This rule results in the shortest manufacturing
    lead time, therefore, lowest work-in process
    inventory.

87
  • 3. Earliest due date (EDD) rule gives the highest
    priority to jobs with the earliest due date.

88
  • 4. Least slack (LS) rule assign the highest
    priority to the job with least slack.
  • The slack is defined as
  • Slack time remaining until due date -
    process time remaining

89
  • 5. Least slack per operation (LSPO) rule assigns
    priority based on the smallest value obtained by
    dividing the slack by the number of number
    remaining operations.

90
  • 6. Critical ratio (CR) rule assigns priority
    based on index defined as follows

where Time remaining until due date due date
- now Lead time setup run move queue
91
  • The least slack, least slack per operation,
    critical ratio, and earliest due date rules
    consider the relative urgency of the jobs.

92
EXAMPLE Today is 10
First-come, first-served (FCFS) rule Sequence
A, B, C, D. Shortest processing time (SPT)
rule Sequence A, C, D, B. Earliest due date
(EDD) rule Sequence A, D, C, B.
93
  • Least slack (LS) rule
  • Slack time remaining until due date -
    process time remaining
  • Slack for A (17 - 10) - 4 3 days
  • Slack for B (29 - 10) - 18 1 days
  • Slack for C (27 - 10) 8 9 days
  • Slack for D (26 - 10) - 12 4 days
  • Sequence B, A, D, C.

94
  • Least slack per operation (LSPO) rule
  • LSPO for A 3/8 0.375
  • LSPO for B 1/18 0.055
  • LSPO for C 9/16 0.5625
  • LSPO for D 4/2 2
  • Sequence B, A, C, D.

95
  • Critical ratio (CR) rule

CR for A (17 - 10)/4 1.75 CR for B (29 -
10)/18 1.05 CR for C (27 - 10)/8 2.125 CR
for D (26 - 10)/12 1.33 Sequence B, D, A, C.
96
JUST IN-TIME PRODUCTION
  • Just-in-time (JIT) is an approach to production
    that was developed in Japan to minimize
    inventories.

97
DefinitionJust-in-time (JIT) manufacturing is a
Japanese management philosophy applied in
manufacturing which involves having the right
items of the right quality and quantity in the
right place and at the right time.
98
  • Inventory ties up investment funds and takes up
    space.
  • To reduce this form of waste, the JIT approach
    includes a number of principles and procedures
    aimed at reducing inventories, either directly or
    indirectly.
  • Indeed, the scope of JIT is so broad that it is
    often referred to as a philosophy.

99
  • Just-in-time procedures have proved most
    effective in high-volume repetitive
    manufacturing, such as the automobile industry.
  • The potential for in-process inventory
    accumulation in this type of manufacturing is
    significant because both the quantities of
    products and the number of components per product
    are large.

100
  • Just-in-time system produces exactly the right
    number of each component required to satisfy the
    next operation in the manufacturing sequence just
    when that component is needed just-in-time.

101
  • To the Japanese, the ideal batch size is one
    part. As a practical matter, more than one part
    are produced at a time, but the batch size is
    kept small. Under JIT, producing too many units
    is to be avoided as much as producing too few
    units.
  • This is a production discipline that contrasts
    sharply with traditional U.S. practice, which has
    promoted use of large in-process inventories to
    deal with problems such as machine breakdowns,
    defective components, and other obstacles to
    smooth production.
  • The U.S. approach might be described as a
    just-in-case philosophy.

102
  • Although the principal aim in JIT is inventory
    reduction, this cannot simply be achieved.
    Several requisites must be pursued to make it
    possible.
  • These include
  • stable production schedules,
  • small batch sizes and short setup times,
  • on-time delivery,
  • defect-free components and materials,
  • reliable production equipment,
  • pull system of production control,
  • a work force that is capable, committed, and
    cooperative, and
  • a dependable supplier base.

103
  • Stable Schedule
  • For JIT to be successful, work must flow
    smoothly with minimum perturbations from normal
    operations. Perturbations require changes in
    operating procedures
  • increases and decreases in production rate,
  • unscheduled setups,
  • variations from the regular work routine, and
    other exceptions.

104
  • Small Batch Sizes and Setup Reduction Another
    requirement for minimizing inventories is small
    batch sizes and short setup times.

105
  • Some approaches used to reduce setup time
    include
  • perform as much of the setup as possible while
    the previous job is still running
  • use quick-acting clamping devices instead of
    bolts and nuts
  • eliminate or minimize adjustments in the setup
    and
  • use group technology and cellular manufacturing
    so that similar part styles are produced on the
    same equipment.

106
  • For the success of JIT production
  • On-time Delivery
  • Zero Defects
  • Reliable Equipment
  • must be established

107
Pull System of Production Control
Process 1
Process 2
Process 3
A push system
Process 1
Process 2
Process 3
A pull system
  • JIT requires a pull system of production control
  • MRP is a push system.

108
JUST IN TIME PHILOSOPHY
  • PULL SYSTEM
  • - ONLY WHAT IS NEEDED IN THE NEXT STAGE OF
    PRODUCTION IS PRODUCED.

109
  • One famous pull system is the Kanban system used
    by Toyota, the Japanese automobile company.
  • Kanban (pronounced kahn-bahn) is a Japanese word
    meaning card. The Kanban system of production
    control is based on the use of cards to authorize
    production and work flow in the plant.

110
  • There are two types of kanbans
  • production kanbans and
  • transport kanbans
  • A production kanban authorizes production of a
    batch of parts. The parts are placed in a
    container, so the batch must consist of just
    enough parts to fill the container. Production of
    additional parts is not permitted.
  • The transport kanban authorizes movement of the
    container of parts to the next station in the
    sequence.

111
QUALITY ASSURANCE
  • Quality is maintained in two ways
  • each worker monitors his or her work and
  • periodic inspections are performed by individuals
    from the quality control function.

112
  • Inspection is necessary at several places in the
    manufacturing process, including
  • Inspection of raw materials
  • Inspection of manufactured product
  • Preprocess
  • In-process
  • Post process

113
  • Inspection of production process
  • parameters
  • Tools
  • Fixtures
  • Production machinery
  • Verification/calibration
  • Inspection fixtures
  • Inspection gauges
  • Inspection machinery

114
  • Ideally, suppliers should provide good products.
  • If the receiving firm can depend on the quality
    of the materials, quality assurance will not have
    to inspect incoming product.

115
  • If inspection is required, statistical sampling
    techniques are often used.
  • These procedures are called acceptance sampling
    and are based on the premise that a random sample
    drawn from a batch is representative of the
    entire batch.
  • Thus, only the sample is inspected in
    determining the quality of the entire batch.

116
  • In many companies where the production of
    high-quality parts is the company policy, workers
    inspect the parts during the production process
    to ensure that the process is under control.

117
  • Some operations involve 100 inspection and some
    use random samples.
  • Statistical process control (SPC) charts may be
    used to assist in monitoring the production
    process.

118
CONTROL CHART
119
  • In recent years there has been growing
    recognition of the value of SPC charts, since
  • 1. Control charts are a proven technique for
    improving productivity.
  • A successful control chart program reduces scrap
    and rework, which are primary productivity
    killers in any operation.
  • If scrap and rework are reduced
  • productivity increases,
  • cost decreases, and
  • production capacity (measured as the number of
    conforming parts per time period) increases.

120
  • 2. Control charts are effective in preventing
    nonconformity.
  • The control chart helps keep the process in
    control, which is consistent with the do it
    right the first time philosophy.
  • It is rarely cheaper to sort out good units from
    bad ones later on than it is to build them
    correctly in the first place.
  • If there is no effective process control,
    operators are being paid to make non-conforming
    product.

121
  • 3.Control charts prevent unnecessary process
    adjustments.
  • A control chart can distinguish between
    background noise and abnormal variation no other
    device, including a human operator, is as
    effective in making this distinction.

122
  • 4.Control charts provide diagnostic information.
  • Frequently, the pattern of points on the control
    chart will contain information of diagnostic
    value to an experienced operator or engineer.
  • This information allows the implementation of a
    change that improves the performance of a process.

123
  • 5. Control charts provide information about
    process capability.
  • The control chart provides information about the
    value of important process parameters and their
    stability over time. This allows an estimate of
    process capability to be made.
  • Since quality is an extremely important
    consideration in global competitive markets, it
    is easy to understand why SPC and control charts
    are being implemented by many firms.

124
(No Transcript)
125
(No Transcript)
Write a Comment
User Comments (0)