Title: Benicia-Martinez Bridge Main Span Contract


1
Benicia-Martinez BridgeMain Span Contract
  • Financial Status of Project
  • May 2004

2
(No Transcript)
3
(No Transcript)
4
(No Transcript)
5
Substructure Issues
  • Cause
  • Fish issue
  • Differing site conditions
  • Effect
  • Change methods for installing Permanent Steel
    Casing (PSC)
  • Delays
  • Escalation
  • Inefficiencies
  • Change method for constructing CIDH

6
Superstructure Issues
  • Cause
  • Fish issue
  • Steel Congestion
  • LCA/Lightweight Concrete
  • Effect
  • Delays
  • Re-sequencing the work
  • Escalation
  • Inefficiencies

7
December 2002 Forecast
Changes from Original Budget
Fish Issue 134M Hard Driving 26M
Rock Sockets 40M
Superstructure 20M
8
May 2004 Forecast
Changes from Dec02 Forecast
Fish Issue ( 10M) Hard Driving 0M
Rock Sockets 120M
Superstructure 25M
9
Moving Forward
10
(No Transcript)
11
Bechtel Project Review
  • Major Questions Addressed
  • Is Caltrans cost estimating methodology
    reasonable?
  • What options are available to reduce project
    costs?

12
Bechtels Project Review Findings
  • Cost estimating methodology appears reasonable.
  • Terminating and re-bidding remaining work would
    not be cost effective and would be more risky.
  • Negotiating a fixed price contract adjustment for
    remaining work is best approach.

13
RM 1 Funding Plan
  • RM 1 funding plan has financial capacity to fund
    overruns
  • Financial transactions (fund swaps)
  • Reducing bridge rehabilitation program funding
  • 50 million in RM 2 expenditure plan

14
RM 1 Toll Bridge Program Budget ( mil.)
Bridge Adopted Budget Forecast Budget Forecast Project Contingency Forecast Total Budget Difference
Benicia-Martinez 652.8 1019.9 37.8 1057.8 405.0
Carquinez 479.8 484.9 14.9 499.8 20.0
San Mateo-Hayward Widening 217.5 211.4 6.0 217.5
I-880/92 Interchange 133.8 137.7 11.6 149.3 15.5
Richmond-San Rafael Trestle 35.4 35.4 35.4
Richmond-San Rafael Deck 53.4 42.0 11.4 53.4
Bayfront Expressway 36.0 35.2 0.8 36.0
Other 10.1 10 0.1 10.1
TOTAL 1,618.8 1,976.5 82.6 2,059.3 440.5
15
Recommendation
  • Amend the total Benicia-Martinez Bridge project
    budget by 405 million for a total project cost
    of 1,057.8 billion.
  • Main Span Construction 338 million
  • Support Costs 50 million
  • Project Contingency 17 million
  • Total Budget Amendment 405 million
  • Allocate 366.4 million in toll funds to the
    Benicia-Martinez project contingent upon Caltrans
    executing a change order.