Justin Greenhalgh - RAL - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Justin Greenhalgh - RAL

Description:

Effort required: PPESP request, mid-term review, current plan ... Mechanical components tendered, companies shortlisted, contract to be placed before end 2002 ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 26
Provided by: alo5
Category:

less

Transcript and Presenter's Notes

Title: Justin Greenhalgh - RAL


1
CMS ECAL Endcaps Effort requirements in
Engineering Department and Instrumentation
Department (collectively, TD)
  • Justin Greenhalgh

2
Summary
  • Overview of EE
  • Scope of project in TD
  • Team members
  • Project status
  • List of tasks to completion in outline
  • List of tasks in detail
  • Effort required PPESP request, mid-term review,
    current plan
  • Effort for each task, by year, and by team member
  • Summary comments

3
The CMS calorimeter
BARREL
The 53 degree crack
LOCATION OF HE
Preshower
ENDCAP
4
HE
EE
SE
5
Exploded view and parts
6
Picture of original electronics arrangement
7
Supercrystal parts
Arrangement of a few Super Crystal Parts
8
SC - Concept
Super Crystal with Positional Spacer
9
TD Project scope - included
  • Supercrystals
  • Manufacture of 50 of full supercrystals
    (alveolars and crystals supplied by others)
  • Handover of parts and expertise to others for the
    other 50
  • Major mechanics
  • Design of backplate, ring flange, positional
    spacers, environmental shield, moderators, other
    internal components
  • Procurement and supply of above
  • Electronics
  • Participation in ECAL joint VFE design
  • Customisation to suit EE. Design supply
    housings, cooling, etc.
  • Project co-ordination
  • Many interfaces to other work areas including
    assembly installation
  • Ensure ECAL is aware of what needs to be done
    outside our scope

10
TD project scope - excluded
  • Supercrystals
  • Supply of crystals (ETH) alveolars (Russia)
    VPTs (PPD)
  • Electronic test eqpt for regional centre (PPD)
  • Partial supercrystals (Russia)
  • Major mechanics
  • Some support with design and analysis from Russia
  • Dee assembly (IC/CERN)
  • Electronics
  • Support with completion of HV design from PPD
  • VFE cards (ECAL)
  • Other areas
  • Slow controls (ECAL) services outside EE (ECAL)
  • Installation (ECAL)
  • Radiation testing and TIS clearance (PPD)

11
Team members in TD
  • Justin Greenhalgh
  • Management of TD resources and activities in
    other areas
  • Thermal and structural performance oversight
  • Brian Smith
  • Supercrystals
  • John Hill
  • Major mechanics, mechanical integration issues
  • Tony Lodge
  • Electronics
  • Others - Design and technician support

12
Project status - overview
  • Supercrystals
  • Design OK, parts mostly on order, gearing up for
    production in summer 2003 but subject to
    confirmation of external funding
  • Major mechanics
  • Design passed review, production drawings in
    hand, due to carry out tender action
    spring/summer 2003
  • Electronics
  • CMS critical path item
  • EE working as part of ECAL effort to make a joint
    design for the VFE mechatronics
  • tests hoped in test beam summer 2003, production
    electronics required March 2005

13
Project status - supercrystals
  • Successful review November 2000
  • Mechanical components tendered, companies
    shortlisted, contract to be placed before end
    2002
  • Production facility about 50 kitted out
  • Production due to start summer 2003
  • BUT
  • crystals still not ordered,
  • HV cards design still not fixed,
  • other details to finalise

14
Project status - major mechanics
  • EDR succesful in Sept 2002
  • Production drawings being made
  • Ring flange almost complete
  • Backplate in hand
  • Pos spacers next
  • Agreed to freeze backplate and ring flange and
    treat those as design constraints for the
    mechatronics

15
Project status - Electronics
  • Strategy is to work with the ECAL community to
    ensure that the agreed design is EE-compatible
  • Two promising potential designs for housing the
    electronics
  • Fundamental principle is that it must be possible
    to install and test the cooling before the
    electronics is fitted
  • After many delays on the FPPA chip design, a
    second, more promising, design is now being
    pursued in parallel (using 0.25 micron
    technology)
  • TD staff member Tony Lodge is now working about
    50 at CERN, the arrangements being under
    continuous review
  • CERN mechanical designer is due to start work on
    EE-specific design issues

16
Outline list of tasks from now to completion in TD
  • procure mechanical parts for supercrystals,
  • produce about 300 supercrystals, transfer
    expertise to other regional centres
  • complete design of major mechanical items,
    procure them
  • participate in completion of ECAL mechatronics
    design
  • (level of input negotiable)
  • complete EE-specific mechatronics design
  • (level of input depends upon how applicable the
    ECAL design is to EE)
  • See Project Specification paper - latest version
    was superseded by developments in the
    mechatronics area.

17
Tasks from now to completion - supercrystals
  • Oversee production of SC mechanics
  • Complete preparation of regional centre at RAL
  • Resolve remaining details temperature sensors,
    support bracket for fibres.
  • Resolve HV card and umbilical design, procure.

18
Tasks from now to completion - major mechanics
  • Completion of production drawings for backplate,
    ring flange, positional spacers, moderators
  • Oversee completion of drawings for environmental
    shield by Russian colleagues
  • Tender action - documents, company visits, etc
  • Oversee manufacture
  • Interface with assembly and installation teams

19
Tasks from now to completion - mechatronics
  • Work with ECAL to arrive at a mechatronics design
    which can be applied (perhaps in two variants) to
    the barrel and the endcaps.
  • Currently effort is being used to look at the
    services external to EE, because they influence
    the design inside.
  • Future
  • Install the new electronics in the test bench
    E zero prime model. Includes making any
    required mods to suit EE
  • Test beam runs to establish noise performance
  • Fix noise problems
  • Make engineering model of final design, produce
    drawings
  • Oversee production

20
Effort requirements - PPESP vs midterm review
21
Effort requirements - midterm review vs current
situation
22
Effort requirements in detail for each task
23
Effort requirement year-by-year
24
Effort requirement year-by-year (staff)
25
Summary
  • The scope of project includes making significant
    parts but we (TD/PPD) cannot afford to assemble
    or install the Dees.
  • There have been significant delays - to the VFE
    electronics and the crystal delivery, eg.
  • A major exercise was undertaken in early 2001 to
    fully re-cost activities to completion.
  • Some work was passed to PPD and a significant
    increase in TD resources was sought at the
    mid-term review.
  • Since then there have been yet further delays but
    we have
  • Minimised effort usage where design work was
    blocked
  • Sought to use ECAL-wide resources as far as
    possible, by collaborating on the joint
    mechatronics design (just starting to pay off)
  • replanned to live within the mid-term-review
    effort budget
Write a Comment
User Comments (0)
About PowerShow.com