Title: West Yorkshire Local Transport Plan Briefing December 2006
1West Yorkshire Local Transport Plan Briefing
December 2006
2Content
- Introduction and Background Context
- 2) West Yorkshire Local Transport Plan 2006 to
2011 - - Policy, Strategy and the Shared Priorities
- - Resources
- - Capital Programme
- - Performance Management
-
- 3) Going Forward and the Wider Picture
3Introduction
- Five year transport strategy and investment plan
- Principal mechanism for obtaining funding from
the DfT for local transport improvements and
maintenance - Developed in partnership with Metro and the five
West Yorkshire district authorities - LTP2 adopted in March 2006 (2006-2011)
- Produced in accordance with Government guidance
and built on successful achievements of LTP1
4Successful actions during LTP1 (2001-2006)
- Successful road safety programme
- Good progress in highway network maintenance
- Reductions in the backlog of bridges and
structures maintenance and strengthening - Significant improvements to the public realm,
including enhanced pedestrian facilities - Delivery of successful off-road cycle routes
- Good progress on school travel
5Successful actions continued
- Step change in bus facilities on core routes,
including accessibility improvements and new bus
lanes - Investment in bus and rail stations
- Launch of the largest real time passenger
information system in the country covering South
and West Yorkshire - Improvements to accessibility through new
MetroConnect services
6Key transport impacts of LTP1
- Traffic growth constrained
- Road safety improved
- Better road conditions
- Profile of transport raised at sub-regional and
regional levels - Role of rail into urban centres increased for
commuters and shoppers - Role of bus increased on some urban routes
- Social inclusion improved
7LTP1 Resources
- 138.5million allocated to West Yorkshire for
integrated transport improvements which included
29.5million for Leeds - 149million allocated to West Yorkshire for
maintenance work which included 48million for
Leeds - Capital also spent on transport/highway
infrastructure from capital receipts or
prudential borrowing - Further funding provided from the DfT for
advanced works for Supertram, IRR Stage 7 and ELLR
8Differences between LTP1 and LTP2
- Centrally agreed shared priorities for LTP2s
- Resource assumptions
- Bonus funding
- Targets
- PSA target for congestion
- Local Area Agreements
- SEA
9LTP2 - Policy, strategy and the shared priorities
- Prepared in accordance with Government guidance
and informed by wide ranging consultation - Structured around the nationally agreed shared
priorities for transport - Accessibility
- Congestion
- Road Safety
- Air Quality
- Plus
- Asset Management
- Quality of Life
10Accessibility - Context
- Social Exclusion Unit Report (2003) Making the
Connections - Access to key services
-
- Health / Education / Work / Food
- Reasonable access
- Cost / Time / Distance / Safe
11Accessibility Planning - Strategy
- Local accessibility assessments
-
- Public transport accessibility mapping
- Discussions with partners
- Consultation with user/interest groups
- Issue identification
- Accessibility Strategy and Action Plan
12Congestion - Context
- A top priority from the public consultation
- GPS data used to identify congestion hotspots
- Causes and impacts of congestion have been
analysed to inform strategy - development
-
13Congestion - Strategy
- Strategies to address congestion consist of
measures to - Encourage smarter travel choices
- Manage the demand for travel
- Improve the highway network
- Make the best use of existing capacity
- Promote sustainable land use planning
-
14Safer Roads - Context
- West Yorkshire on track to meet national road
safety targets for 2010 - Challenge to maintain this level of improvement
- Motorcycling casualties are cause for concern
- Analysis of the causes of casualties and
casualties by area are carried out to inform
strategy and scheme development
15Safer Roads - Strategy
- Strategies to address road safety consist of
- physical measures to improve local safety
- enforcement measures
- education, training and publicity initiatives
-
16Air Quality and Vehicle Emissions - Context
- Environmental impacts can include
- - poor air quality
- - noise pollution
- - climate change
- UK transport sector accounts for 24 of UK CO2
- - major consideration for future policy
- 7 traffic related AQMAs in Leeds plus 7 AOC
- Problems exacerbated by road congestion
17Air Quality and Vehicle Emissions - Strategy
- Strategies to improve air quality, reduce
emissions and mitigate and adapt to climate
change include - measures which address congestion
- maintenance/asset management techniques
18Asset Management and Maintenance - Context
- Vital to delivering all of the shared priorities
- Management and maintenance of the road surface
and transport infrastructure within the boundary
of the highway - Highway network no longer deteriorating
principal roads showing an improvement in
condition - Transport Asset Management Plans being developed
19Asset Management and Maintenance - Strategy
- The asset management strategy has nine key
elements which include - General maintenance programmes e.g. roads,
footways, lighting, winter maintenance, bus stops
etc - Highways structures strengthening/maintenance
- Operation/maintenance of UTMC and CCTV systems
20LTP2 resources
- Revised funding arrangements
- - Minor schemes, indicative 5 year figures
- - Major schemes, regional prioritisation
- West Yorkshire capital expenditure settlement for
2006/07 - Integrated Transport block, 28.491m
- - 5.871 for Leeds
- - includes 5 bonus for 2004/05 LTP delivery
- - indicative figures rising to 34m by 2010/11
- Maintenance, 33.310m for cways and bridges
- - 10.346 for Leeds (inc 1.7 for PRN structs)
- - indicative figure for 2010/11 10.2m ( PRN)
-
21LTP2 Integrated Transport plan
Expenditure estimates for Key areas,
2006-11- Bus infrastructure (stops etc) 4.1
m Bus priority measures 12.1m Cycling 2
m Public transport interchange 1.3m Local
safety schemes 2.9m Road crossings (inc
refurbs) 2.6m Local road schemes 1.7m Traf
fic mgmnt. (UTC area safety) 3.6m Walking
(and access) schemes 2.3m
22LTP2 Major schemes
- Inner Ring Road Stage 7 - 50million scheme
commenced May 2006 - East Leeds Link Road - 32.5million scheme
commenced November 2006 - A65 Kirkstall Road Quality Bus Corridor
20.7million scheme - programme entry granted
July 2006
23Performance Management
- Four elements
- Financial Management
- Scheme Monitoring
- Progress towards targets
- Policy Review
-
24Targets
- 27 targets
- 14 mandatory and 13 local
- Address the shared priorities
- Most are West Yorkshire wide targets
- Have to set a target for 2010/11 and
trajectories/milestones for intervening periods
25Mandatory targets
- Common to all LTPs - DfT set minimum standard
- Main areas
- Accessibility
- Bus patronage, punctuality and satisfaction
- Safety (overall and child KSIs)
- Congestion journey times also PSA target -
traffic flows to main urban areas - Mode share for journeys to school
- Air Quality NO2 in AQMAs
- Overall cycling levels
- Highway footway maintenance
26Local targets
- Set to address our priorities
- Satisfaction with new LTP funded PT facilities
- Peak period cycle trips to Leeds, Wakefield
Halifax - AM peak period modal split
- Peak period rail patronage to Leeds
- Additional safety targets (pedestrian KSIs)
- Additional Air quality targets (network wide NOx
and CO2) - Asset management targets carriageways,
structures and bus shelters -
27Monitoring
- 46 Key and Background Indicators
- Use specific data collection exercises (mode
split), data from other sources (BVPI) and
national statistics - Annual Monitoring Report produced
- Also scheme monitoring to evaluate effectiveness
of measures -
28Example Congestion Monitoring
- Indicator Journey time per person mile on key
routes - Traffic flow data from ATCs
- Car speeds from iTIS
- Bus speeds from surveys (AVL data?)
- Bus and car occupancy surveys
-
29Reporting
- Required to report on mandatory targets annually
showing progress against milestones - Targets to be stretched if trends suggest it will
be achieved before 2010/11 - Progress will be considered by DfT when assigning
resources -
30Environmental Management
- WY Transport Emissions Group established
- Need to liaise with partners i.e. Highways
Agency, bus operators etc - Looking to include environmental considerations
on design briefs and in-house EIA screening tool
being developed - More consideration needed to
- - noise impacts
- local air quality
- CO2 emissions?
31Going Forward
- Post Supertram solutions
- Short term strategy needs to deliver quick wins
and build public and business confidence - - Strategic bus park and ride sites
- - Targeted bus priority measures and whole
route improvements - - Links into regeneration areas, e.g. AVL
- - Improving the rail network
- - Bus Rapid Transit (BRT)
- City centre strategy
- - Parking strategy
- - Road network developments
- - Public transport gateways
32 Key workstreams
- City centre transport strategy to address
- Access and development issues
- South Leeds roads strategy
- Holbeck urban village
- Beeston and Holbeck
- Strategy support for regeneration areas for
- Renaissance Leeds
- Aire Valley Leeds
- EASEL
- West Leeds Gateway
-
- A6120 route strategy development
- Airport access
33Leeds City Region Transport Vision
- As part of City Region Development Plan sets out
longer term vision for the transport network - Connecting the core centres in West Yorkshire and
the wider Leeds City Region - Wider connectivity to
- - Neighbouring City Regions
- - London
- - International gateways (i.e. airports
ports) - Provides an investment plan and bid
34Summing up
- New LTP provides 5 year strategic programme
- Vision for transport to serve the whole city
- Remaining key issues relate to major projects
- Post Supertram strategy
- Rail and bus investment
- Major highway priorities
- Funding and resources
- - LTP
- - Regional Transport Allocation
- - Transport Innovation Fund
35Questions and discussion http//www.wyltp.com/