Hydropower a regulatory perspective - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Hydropower a regulatory perspective

Description:

Recognises potential benefits to communities of small scale HEP. Will take positive view of reasonable ... contravene its statutory duties. Applicants should: ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 33
Provided by: chris1278
Category:

less

Transcript and Presenter's Notes

Title: Hydropower a regulatory perspective


1
Hydropower a regulatory perspective
  • Gideon Carpenter
  • Hydrology Water Resources Management

2
EA position on Hydropower
  • Supports Governments targets on renewable energy
  • Recognises potential benefits to communities of
    small scale HEP
  • Will take positive view of reasonable well
    designed proposals to agree sustainable projects.

3
Agency Permitting
  • Impounding licence
  • Abstraction licence
  • Flood defence consent
  • Fisheries consents inc. fish pass approval

4
Impoundment licence
  • Structure that obstructs or impedes flow of
    inland water
  • Examples dams, weirs.
  • Not time limited

5
Abstraction licence
  • Required to remove or abstract water from
  • - a surface source e.g. river, stream, canal
  • - an underground source e.g. borehole.
  • Threshold quantity of 20m3 or 4,400 gallons per
    day.
  • Cost 135 application fee 400 - 900
    advertising fee.
  • Less than 5MW no annual charge.

6
Abstraction licence
  • Self destruct condition 3 years
  • Time limited normally 12 years
  • Presumption of renewal
  • Transferable
  • Abstraction volumes
  • Conditions flow measurement, screening etc.

7
Environmental assessment
  • gt 0.5MW Town Country Planning statutory
    Environmental Impact Assessment
  • lt 0.5MW Environmental report to support
    application.

8
Abstraction Regime
  • How much water can be abstracted?
  • How much water is there?
  • What would the impacts of abstraction be?
  • Environmental importance and sensitivity?

9
Flow estimation
10
Abstraction Regime
  • Impacts on stream flow
  • Flow depletion
  • Flow variability
  • Reduced in-river marginal habitat, flow
    barriers to fish passage

11
Licensing policy
  • Site specific but likely to include
  • Minimum residual flow (Q95)
  • Variable abstraction rate of 25 or 50 of
    available flow
  • Considerations
  • Turbine design and operating flows
  • Length of depleted reach (high/low head scheme?)
  • Environmental sensitivity

12
Hydrology
  • Hydrology flow duration curve.

Mean flow Q30
110 days
Low flow Q95
18 days
13
Hydrograph natural flows
14
Hydrograph Residual flow
15
Depleted reaches
16
Depleted reaches
17
Hydrograph Variable abstraction
18
Control structures
19
Flow measurement
20
Flood Defence Consents
  • for works in, over, under or adjacent to main
    rivers (Water Resources Act 1991)
  • to construct a culvert or flow control structure
    (such as a weir) on any ordinary watercourse
    (Land Drainage Act 1991)
  • Application fee 50

21
Fisheries
  • Passage
  • Screens
  • Turbines

22
Fish passage
  • Fish passes
  • For both upstream and downstream migration
  • may involve retro-fit
  • also likely to be costly

23
Fish screens
  • Physical
  • wedge wire, mesh,bar
  • design and flow velocities
  • Behavioural
  • acoustic, bubble, lighting
  • Fish screens are expensive
  • need maintenance
  • Recent RD

24
Turbines
25
Fish friendly turbines?
  • Crossflow
  • Francis
  • Kaplan
  • Waterwheel
  • Archimedean screw

26
Low head - Archimedean screw
27
To Summarise
  • Impounding licence
  • Abstraction licence
  • Flood defence consent
  • Fisheries consents inc. fish pass approval

28
EA should
  • Provide clear guidance on the licensing process
  • Highlight key issues for environmental assessment
  • Have an understanding of hydropower
  • Be consistent
  • Be positive and pragmatic
  • Provide timely responses, with explanations

29
EA should not
  • collect and analyse supporting data
  • carry out the environmental assessment
  • accept inadequate data or assessments
  • give a binding view based on incomplete
    information
  • design the scheme
  • contravene its statutory duties

30
Applicants should
  • know their site, its environment and their
    objectives for the scheme
  • consider their proposals carefully
  • consider options/alternatives
  • make early contact with the Agency
  • appreciate legislative constraints
  • provide quality environmental assessments
  • provide appropriately detailed plans

31
My suggestions
  • Establish the right key contact in EA
  • Dont expect to do it on the cheap get
    professional advice
  • Think ahead - field measurements for
    hydrological study or environmental monitoring
  • Submit a professional, complete and well
    presented application with good scheme design.

32
Hydropower Good Practice Guide
  • Being developed by EA/Hydropower Working Group
  • Aims to
  • provide Agency/developers with a consistent
    approach, common language and practical advice
  • clarify the Agency position and promote awareness
  • But it wont
  • answer all your day-to-day operational Hydropower
    issues
  • Agency Hydropower Manual(2003) available on
    website
Write a Comment
User Comments (0)
About PowerShow.com