Next European Dipole (NED) Status Report - PowerPoint PPT Presentation

About This Presentation
Title:

Next European Dipole (NED) Status Report

Description:

The DOE has agreed to fund the US-LHC Accelerator Research Program (LARP) with a ... Example of Double Cantilever Beam (DCB) fracture test (courtesy S. Canfer, CCLRC) ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 27
Provided by: cdr53
Category:

less

Transcript and Presenter's Notes

Title: Next European Dipole (NED) Status Report


1
Next European Dipole (NED) Status Report
Arnaud Devred CEA/DSM/DAPNIA/SACM
CERN/AT/MAS on behalf of the NED
Collaboration CARE Steering Committee
Meeting 5 September 2005
2
Some very good news
for our American colleagues!
  • The DOE has agreed to fund the US-LHC
    Accelerator Research Program (LARP) with a budget
    of 11 M for FY06 (approved by Congress but not
    yet signed by the President.
  • This budget level should be kept constant for a
    few years (until 2009?)
  • For FY06, it will be divided up into 5 M for
    magnets, 4 M for accelerator-related RD and 2
    M for management (shared between FNAL, BNL, LBNL
    and SLAC).
  • The goal of the magnet part of LARP is to build
    by 2009 one or two 4-m-long, 90-mm-aperture, 200
    T/m quadrupole magnet prototypes.

3
Some pretty sad news
for the NED collaboration!
  • The EUROMAG NEST Adventure proposal has been
    turned down by the EU on the ground that it was
    not adventurous enough
  • Hence, we are back to square one regarding the
    funding of the model magnet manufacturing and
    test

4
NED Programme
  • The NED Programme is articulated around four
    Work Packages and one Working Group
  • 1 Management Communication (MC),
  • 2 Thermal Studies and Quench Protection
    (TSQP),
  • 3 Conductor Development (CD),
  • 4 Insulation Development and Implementation
    (IDI),
  • 5 Magnet Design and Optimization (MDO) Working
    Group.
  • It is carried out by a collaboration made up of
    8 institutes CCLRC/RAL, CEA, CIEMAT, CERN,
    INFN/Genova and INFN/Milano, Twente University
    (TEU) and Wroclaw University of Technology (WUT).

5
MC Work Package
  • We have held three Steering Committee (SC)
    meetings since the beginning of the year
  • 20 January at CERN
  • 14 April at CERN
  • 7 July at WUT
  • Next SC meeting will be held at CERN during the
    CARE general meeting next ESAC meeting will be
    held at CERN before or after the planned
    HHH/WAMDO (April 2005).
  • Second quarterly report will be completed by the
    end of the week.
  • All relevant documents are stored into EDMS and
    posted on the NED website
  • http//lt.tnw.utwente.nl/project.php?projectid9

6
TSQP Work Package
  • The TSQ Work Package includes two main Tasks
  • development and operation of a test facility to
    measure heat transfer to helium through conductor
    insulation
  • (CEA and WUT Task Leader B. Baudouy, CEA),
  • quench protection computation
  • (INFN-Mi Task Leader G. Volpini).

7
Heat Transfer Measurement (1/3)
  • The first part of the Task was to design and
    build a new double bath cryostat.
  • CEA wrote detailed specifications that were
    handed out to WUT in June 2004.
  • WUT performed a call for tender in the Summer of
    2004 and selected Kryosystem in Poland to
    manufacture the cryostat.

Schematic of NED cryostat (courtesy F. Michel, B.
Baudouy and B. Hervieu, CEA)
8
Heat Transfer Measurement (2/3)
  • A first reception test of the cryostat was
    carried out on Kryostems premises the 3rd week
    of April 2005, which revealed a few problems.
  • WUT reacted very promptly and worked in close
    collaboration with CEA to correct these problems.
  • A second reception test was carried out the 2nd
    week of July 2005 (including thermal and leak
    tests in liquid helium at 4.2 K), which was
    deemed successful.
  • The cryostat will be delivered to CEA/Saclay on
    19 September, for final implementation and
    commissioning.
  • The 6-month delay with respect to the initial
    schedule is not expected to any deleterious
    impacts on the overall NED Programme.

9
Heat Transfer Measurement (3/3)
Cryostat with thermal shields
Lambda plate
Inner view of cryostat with Instrumentation
(Courtesy M. Chorowski, WUT)
He II heat exchanger
10
Quench Computation (1/3)
  • INFN-Mi has undertaken a detailed analysis of
    the thermal and electrical behaviors of NED-type
    accelerator magnets during a quench.
  • The computation was started considering the
    conservative, 88-mm-aperture, cos?, layer
    design developed by D. Leroy.
  • It studied the influence of
  • magnet length (1, 5 and 10 m),
  • operating current (15, 22 and 29 kA),
  • external dump resistance (15, 25 and 35 m?),
  • quench detection delay (30, 40 and 50 ms),
  • quench protection heater length.
  • It also compared the results obtained by two
    different codes QLASA at INFN-Mi and QUABER at
    CERN.

11
Quench Computation (2/3)
  • The results show that, for the entire parameter
    space, the magnet is quite safe to operate,
    thereby justifying the choice of wire and cable
    parameters made early on.

Quench simulation results on 10-m-long,
88-mm-aperture, cos?, layer design (Courtesy M.
Sorbi INFN-Mi)
12
Quench Computation (3/3)
  • Similar computations have now been started on
    the more innovative, 160-mm-aperture, slot
    design also proposed by D. Leroy.
  • The quench computation task is near completion.

88-mm-aperture, layer design (Courtesy D. Leroy,
CERN)
160-mm-aperture, slot design (Courtesy D. Leroy,
CERN)
13
CD Work Package
  • The CD Work Package includes two main Tasks
  • conductor development
  • (under CERN supervision L. Oberli has now taken
    over D. Leroy as the official Task Leader),
  • conductor characterization
  • (CEA, INFN-Ge, INFN-Mi, and TEU Task Leader A.
    den Ouden, TEU).
  • It is the core of the programme and absorbs
    about 70 of the EU allocated funding.

14
Conductor Development (1/2)
  • As a conclusion of preliminary design studies
    carried out in 2003 and 2004 under the
    supervision of D. Leroy, the following
    specifications were derived for NED Nb3Sn strands
  • diameter 1.250 mm,
  • eff. filament diameter lt 50 mm,
  • Cu-to-non-Cu ratio 1.25 0.10,
  • filament twist pitch 30 mm,
  • non-Cu JC 1500 A/mm2 _at_4.2 K 15 T,
  • minimum critical current 1636 A at 12 T,
  • 818 A at 15 T,
  • N-value gt 30 at 4.2 K and 15 T,
  • RRR (after heat treatment) gt 200.
  • (It is also requested that the billet weight be
    higher than 50 kg.)

15
Conductor Development (2/2)
  • Based on these specifications, a call for tender
    was issued by CERN in June 2004 and two contracts
    were awarded in November to 2004 to Alstom/MSA in
    France (Enhanced Internal Tin process) and SMI
    in the Netherlands (Powder in Tube Process).
  • After discussion with CERN, the two companies
    agreed to work out their development program into
    two successive RD Steps (referred to as STEP 1
    and STEP 2) followed by final cable production.
  • A tentative schedule was established as follows
  • STEP 1 Summer 2005,
  • STEP 2 Summer 2006,
  • Final production December 2006.

16
Conductor Characterization (1/2)
  • The NED-type conductor characterization
    represents a real challenge, given the
    unprecedented performances that are expected
    (e.g., a critical current of 1600 A at 4.2 K and
    12 T on a 1.25-mm wire, to be compared to the
    timid 200 A presently achieved on 0.8 mm ITER
    wires).
  • To validate sample preparation and measurement
    processes, the laboratories involved (CEA, TEU
    and INFN) have launched a cross-calibration
    program reminiscent of the ITER/EDA
    cross-calibration program carried out in the
    mid-1990s.
  • Since the Summer of 2004, three rounds of
    calibration wires have been prepared and
    circulated among the various partners.

17
Conductor Characterization (2/2)
  • TEU and INFN have now achieved a good
    convergence.
  • The problems at CEA have been identified and are
    being solved.
  • All 3 partners should be ready when the first
    wires become available.

SMI/Toshiba Test Wire (results are within 2)
(Courtesy T. Boutboul, CERN)
18
FE Wire Model
  • In Parallel, INFN-Mi has started to develop an
    ANSYS model of an un-reacted, Alstom/MSA-type
    wire so as to simulate cabling effects.
  • Running such a computation requires a detailed
    knowledge of the mechanical properties of the
    materials making up the wire (in the cold work
    state where they end up prior to the cabling
    operation).
  • To determine these properties, CERN has carried
    out a series of nano-indentation and
    micro-hardness measurements on various wire
    samples, and compared the results with available
    literature data.
  • The next step is to apply this model and the
    appropriate mechanical properties to the wire
    layouts presently considered by Alstom/MSA.

19
IDI Work Package
  • The IDI Work Package includes two main Tasks
  • studies on conventional insulation systems
    relying on ceramic or glass fiber tape and
    vacuum-impregnation by epoxy resin
  • (CCLRC Task Leader E. Baynham),
  • studies on innovative insulation systems
    relying on pre-impregnated fiber tapes and
    eliminating the need for a vacuum impregnation
  • (CEA Task Leader F. Rondeaux).

20
Conventional Insulation (1/2)
  • CCLRC and CEA have developed in collaboration an
    engineering specification (issued in July 2004)
    and a coordinated test programme (issued in
    October 2004).
  • Since then, CCLRC has carried out a number of
    screening tests of candidate materials.
  • The tests are applied to standardized laminates
    representative of inter-turn insulation and
    include
  • electrical breakdown test,
  • short beam shear test,
  • inter-laminar fracture test.

Example of Double Cantilever Beam (DCB) fracture
test (courtesy S. Canfer, CCLRC)
21
Conventional Insulation (2/2)
  • CCLRC has also investigated the issue of
    sizing (a lubricant, usually organic, coated
    onto the fibers of tapes, that need to be removed
    prior to conductor wrapping and winding, thereby
    rendering the fiber tape fragile and easy to tear
    off).
  • Very promising results have been obtained with
    an improved polyimide sizing, produced by
    Hydrosize, NC, and applied by JPS, SC, which
    seems to be able to sustain the required Nb3Sn
    heat treatment without carbonization (thereby
    eliminating the need for de-sizing).
  • More complete evaluation tests are underway.

22
Innovative Insulation
  • The work on innovative insulation has not
    started yet, pending the hiring of a technician
    at the CEA chemistry laboratory, which has been
    delayed until early next year.
  • To compensate for this lack, it was decided last
    spring to reallocate the EU funding of this task
    to hire a postdoc at CEA.
  • A candidate has been identified, who is expected
    to start working this fall.
  • The timing of this task is now becoming critical
    with respect to the overall NED program.

23
MDO Working Group (1/3)
  • The MDO Working Group is made up of
    representatives from CCLRC, CEA, CERN and CIEMAT,
    under the Leadership of F. Toral, CIEMAT.
  • Its main charge is to compare different magnet
    configurations so as to assess their efficiency
    in terms of manufacturability, performance and
    cost.

Cos???layer design (courtesy D. Leroy, CERN)
Intersecting-Ellipses design (courtesy H.
Felice, CEA)
Motor-type design (courtesy F. Toral, CIEMAT)
24
MDO Working Group (2/3)
  • In parallel, work is pursued at CERN so as to
    optimize the baseline, 88-mm-aperture, cos? layer
    design with respect to
  • conductor geometry,
  • iron shape (to reduce saturation effects),
  • ferromagnetic shims (to compensate magnetization
    effects).

(courtesy N. Schwerg, CERN)
25
MDO Working Group (3/3)
  • CCLRC/RAL is also developing a 2D ANSYS model of
    the 88-mm-aperture, cos? layer design so as to
    optimize mechanical support.
  • This model includes sub-models of individual
    coil turns to compute peak stresses in cable
    strands and cable insulation.

(courtesy P. Loveridge, CCLRC)
26
Conclusion
  • A great deal of progress has been made since my
    last presentation (at the CARE general meeting in
    Hamburg last year), leading to a number papers
    presented at various conferences (1 at CEC/ICMC,
    1 at EUCAS and 4 at MT).
  • The cryostat for heat transfer measurements is
    completed and will be delivered to CEA next week.
  • The next few months will be critical for the
    Conductor Development program with the results of
    the STEP 1 wires.
  • The only Task that has not started is the
    Innovative Insulation Task at CEA, but the hiring
    of a Postdoc should help.
  • The funding of the model magnet manufacturing
    remains an open question.
Write a Comment
User Comments (0)
About PowerShow.com