Field testing of individual pitch control on the NREL CART2 wind turbine - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Field testing of individual pitch control on the NREL CART2 wind turbine

Description:

Principle is to use IPC instead of teetering to reduce out of plane blade & hub loads. ... IPC can replace teeter hinge on 2-bladed turbine (reduces 1P loads in ... – PowerPoint PPT presentation

Number of Views:171
Avg rating:3.0/5.0
Slides: 19
Provided by: justine4
Category:

less

Transcript and Presenter's Notes

Title: Field testing of individual pitch control on the NREL CART2 wind turbine


1
Field testing of individual pitch control on the
NREL CART-2 wind turbine E. Bossanyi and A
Wright Garrad Hassan Partners Ltd., NREL
Presented at EWEC 2009, Marseille
2
Context
  • Work carried out as part of the EU 6th Framework
    integrated project UPWIND.
  • Over many years, simulations have demonstrated
    that Individual Pitch Control (IPC) can be an
    effective means of reducing wind turbine fatigue
    loading.
  • To date, no publishable field test data is
    available to prove that IPC actually lives up to
    expectations in reality.
  • Using the public-domain CART-2 and CART-3
    research turbines at NREL, this project provides
    a way to achieve the field validation which is
    needed to provide the confidence to design new
    turbines which rely on the load reductions which
    IPC can provide.

3
The NREL Turbines
  • Two turbines available 42m diameter, 660 kW
  • Although not representative of modern multi-MW
    designs, turbines are adequate for proof of
    principle
  • Research turbines advantage of being very
    accessible with minimum fuss
  • CART-2 2-bladed aiming for measurements in
    spring 2009
  • Turbine ready and operational
  • Relevant 2-Bladed turbines still a definite
    option for large offshore machines
  • Uses conventional strain gauges, but very robust
    well calibrated
  • Fast pitch actuator should be suitable for IPC
  • CART-3 3-bladed aiming for measurements in
    spring 2010
  • Turbine ready but awaiting completion of the
    control system by NREL

4
Programme
  • July 2008 Principles agreed
  • CART-2 testing Spring 2009 (should already be
    underway)
  • CART-3 testing one year later
  • October - November 2008 CART-2 algorithm design
    completed and tested in simulations.
  • Delay awaiting final DOE signature of
    confidentiality agreement. Once this is in
    place
  • Transfer of algorithm to NREL
  • Further NREL proving simulations
  • Still hoping to start field tests before end of
    current wind season!
  • Summer 2009 CART-3 algorithm design to start.
  • Spring 2010 CART-3 field testing.

5
CART-2 turbine
  • Teetered rotor, but teeter will be locked with
    teeter brake. Principle is to use IPC instead of
    teetering to reduce out of plane blade hub
    loads.
  • Bladed model completed.
  • CART-2 control algorithm designed by GH
  • Optimal power production over nominal speed range
  • Speed regulation by interacting torque and
    collective pitch control
  • Drive train damping filter in torque controller
  • F/A tower damping by collective pitch control
  • 1P individual pitch control to reduce rotating
    and non-rotating loads
  • 2P individual pitch control not required
  • Simulation testing completed.

6
Simulation at 18 m/sTower F/A damping Tower
base bending moment (My)
  • Significant reduction of fore-aft tower vibration
    and fatigue loading at 1st tower frequency.

Tower 1st fore-aft mode
7
Simulation at 18 m/s IPC Blade root out of
plane bending moment (My)
  • 1P out of plane loads virtually eliminated on
    rotating components.
  • Teeter hinge no longer needed!

Rotation frequency (1P)
8
Simulation at 18 m/s IPC Rotating hub moment
(My)
  • 1P out of plane loads virtually eliminated on
    rotating components.
  • Teeter hinge no longer needed!

Rotation frequency (1P)
9
Simulation at 18 m/s IPC Yaw moment (Yaw
bearing Mz) non-rotating frame
  • 1P (rotating) becomes 0P and 2P on non-rotating
    components.
  • 0P compensates for wind shear and direction
    change reduces peak loads.
  • Large reduction in 2P fatigue loading.

Blade passing frequency (2P)
Low frequency (0P)
10
Simulation at 24 m/s IPC Yaw moment (Yaw
bearing Mz) non-rotating frame
  • Reduction at 0P helps to reduce peak yaw nod
    moments.
  • Reduced 3P also helps.
  • Reduced 3P means lower fatigue loads.

11
Simulation at 18 m/s Pitch activity
  • IPC requires extra pitch action
  • Additional pitching is concentrated at 1P

Rotation frequency (1P)
12
Simulation at 18 m/s Pitch activity
13
IPC 2 Blades vs 3 blades
  • Control action calculated in non-rotating frame
    two axes, just the same for any number of blades.
  • Number of blades is embodied in the rotational
    transformations
  • For 2-blades, non-rotating fatigue loads (2P) are
    reduced.
  • For 3 blades, non-rotating fatigue loads are at
    3P. Reducing these requires additional (2nd
    harmonic) IPC at 2P (rotating), to reduce
    non-rotating loads at 1P and 3P. (Higher
    harmonics are also possible, but probably
    unnecessary.)

14
2nd Harmonic IPC
  • The CART-3 turbine will provide the opportunity
    for field testing of both 1P and 2P IPC
  • The CART-3 algorithm is not yet designed, but a
    similar algorithm has already been designed for
    the Upwind 5MW reference turbine.

15
1st and 2nd Harmonic IPCUpwind 5MW reference
turbine (3 bladed)
  • Rotating loads reduced at
  • 1P
  • 2P
  • Non-rotating loads reduced at
  • 0P (and 2P)
  • 3P (and 1P)

1st harmonic IPC
2nd harmonic IPC
16
1st and 2nd Harmonic IPCUpwind 5MW reference
turbine (3 bladed)
  • Extra pitch action at
  • 1P
  • 2P

17
Conclusions
  • IPC can replace teeter hinge on 2-bladed turbine
    (reduces 1P loads in rotating components).
  • IPC on 2-bladed turbine also reduces 2P fatigue
    loading on non-rotating components.
  • On 3-bladed turbine, 2nd harmonic (2P) IPC is
    needed to reduce the 3P fatigue loads on
    non-rotating components.
  • CART-2 field measurements to start soon, with 1P
    IPC and tower fore-aft damping.
  • CART-3 field measurements next year, with 1P and
    2P IPC and tower fore-aft damping.
  • 2P IPC proven in simulations for 5MW Upwind
    turbine.

18
Acknowledgements
  • This work has been carried out under the 6th
    Framework Integrated Project Upwind. The
    support of the European Commission is gratefully
    acknowledged.
Write a Comment
User Comments (0)
About PowerShow.com