Title: TEM/TPS%20MRR%20Part%202
1TEM/TPS MRR Part 2
GLAST Large Area Telescope B. Estey,
Production SLAC esteyb_at_slac.stanford.edu (650)
926-8531
2Parts, Materials, and Processes
- EEE Parts
- All EEE parts have been approved for use by the
Program Parts Board - Status of TEM Parts Qualification (highlighted
yellow itemspart approved, not in use)
3Parts, Materials, and Processes
- EEE Parts
- Status of TEM Parts Qualification , contd
(highlighted yellow itemspart approved, not in
use)
4Parts, Materials, and Processes
- EEE Parts, contd
- Status of TPS Parts Qualification (highlighted
yellow itemspart approved, not in use)
5Parts, Materials, and Processes
- EEE Parts, contd
- Status of TPS Parts Qualification, contd
(highlighted yellow itemspart approved, not in
use)
6Parts, Materials, and Processes
- EEE Parts, contd
- Status of TPS Parts Qualification, contd
(highlighted yellow itemspart approved, not in
use)
7Parts, Materials, and Processes
- Materials
- All Materials have been approved by the Program
MPRB in accordance with LAT-SS-00107, LAT
Mechanical Parts Plan - GLAST/LAT Material Usage Agreement 002 (MAR DID
No. 313 LAT Document LAT-TD-04756-01)-
Approved 9/13/04 - Processes
- All processes have been reviewed and approved by
the Program MPRB in accordance with LAT-SS-00107,
LAT Mechanical Parts Plan
8Procurement Status
- Assembly Subcontractor
- GTC Corp. was awarded the contract to provide the
assembly service and some environmental testing
for all levels of the TEM/TPS (Reference
LAT-PS-03078, SOW LAT TPS and LAT-PS-02615, SOW
LAT TEM) - GTC Corp. is located in Albuquerque, New Mexico
- EEE Parts
- All EEE parts are SLAC furnished and have been
procured for the TEM and TPS - Outstanding receipt of Novacap Capacitors
expected 9/16/04 - Part no. 1210B563K251YHTM
- Outstanding receipt of balance of tantalum
capacitors expected 9/20/04 - Part nos. CWR11FH475KDB and CWR11FH105KDB
- Metal Fab Parts and Fasteners
- All Metal Fab parts and Fasteners are SLAC
furnished and have been procured for the TEM and
TPS - Outstanding receipt of TPS Box Bases,
LAT-DS-00995 expected 9/16/04 - Outstanding receipt of TEM Connector Plates,
LAT-DS-01026, expected 9/17/04 - Outstanding receipt of balance of Heat Sinks,
TPS, LAT-DS-04101, expected 9/24/04 - Outstanding receipt of balance of Cable Harness
Support, TPS, LAT-DS-03598, expected 9/24/04 - PWBs
- The PWBs for TEM and TPS are SLAC furnished and
have been contracted to DDI - Fabrication complete on Qual 2, balance of PWBs
to be fabricated pending successful data review
of TEM and TPS Module performance
9Procurement Status
- FPGA Programming
- Programming of the FPGAs has been contracted to
ACTEL - Programming complete on Qual 2, balance of
FPGAs to be programmed pending successful data
review of TEM and TPS Module performance - Materials
- Assembly materials are furnished by GTC Corp. in
accordance with drawing requirements (adhesives,
conformal coating, wire, primer, etc.)
10Manufacturing Facilites
- Assembly contract has been awarded to General
Technology Corporation, located in Albuquerque,
New Mexico - Capabilities Overview
- DS/Multilayer PC Boards assembled to Mil-Spec
- Thru-hole and Surface Mount Technology (SMT)
- Electro/mechanical Assembly
- Cables and Harnessing
- Conformal Coating
- Testing (Including ESS)
- Facilities Overview
- 72,000 ft2 Custom Built Manufacturing Facility
- TEM/TPS assembly and test to be performed in an
environmentally controlled area with monitoring
capabilities for temperature and relative
humidity - Facility complies with the ESD control
requirements specified in ANSI/ESD 20.20-1999 - Manufacturing
- Engineering
- Test
- Stockroom
- Administration
- Certifications
- GTC performs to the intent of the following
certifications assuring quality assembly
11Manufacturing Process Flow- GTC
- Materials notes
- Receiving inspection will be performed on all
materials supplied by the customer using
documents supplied - All discrepancies shall be documented and relayed
to the customer in 24 hours from their discovery - All moisture sensitive materials used in the
manufacturing of the TEM will be stored and
handled in accordance with GTC-2025A -Moisture
Sensitive Component Handling, Use of Dry Room
Storage. - Materials issued in the production of TEM/TPS for
assembly will be traced in a manner that would
enable traceability from the assy S/N to the
individual part /piece and production lot/date
code. - Every TEM and TPS assembly will have its own
traveler issued to facilitate traceability of IC
serial numbers installed on that particular CCA.
12Manufacturing Process Flow-GTC
Inspect
Receive KIT
Not OK
Contact SLAC/ Resolve issue
OK
Clean and bake PCB
Issue Kit To prod.
13Manufacturing Process Flow-GTC
- SMT area notes
- Operators will record all IC serial numbers and
location at which they are installed on a
particular CAA for traceability purposes. All
ICs used in the production of TEM assemblies are
serialized. - Operators will inspect and measure the solder
paste height on every print at 3 predetermined
locations. The results will be recorded in the
SMT printer log along w the printing parameters
14Manufacturing Process Flow-GTC
Inspect/ Measure
Set Up PP and SP
Screen print Solder side
Inspect Kit
OK
Not OK
Clean
1st art. Inspection
PP all SMT components
Inspect
OK
Reflow
Contact SLAC Correct root cause
Not Ok
ok
Clean
Not OK
Touch up
15Manufacturing Process Flow-GTC
Inspect
Install connectors
Solder connectors
OK
Not OK
Touch up
Clean
Contact SLAC MRB
Move to test
16Manufacturing Process Flow-GTC
Pass
Pass
Stake HW components Touch-up
Functional test
Fail
ICT Top/Bt
Fail
Touch up
Contact SLAC MRB
17Manufacturing Process Flow-GTC
- Module assy/conformal coating/thermal cycling
CCA level Thermal cycling
No
Touch up Conformal coat
Contact SLAC MRB
Functional test
OK
Apply Kapton to Back side of CCA
Inspect
Conformal coat.
Apply thermal Adhesive And mount CCA in Chassis
base
Move to next op.
18Manufacturing Process Flow-GTC
Vacuum de-gas Adhesive cure
Install chassis Top cover
Inspect
ok
Stake HW
Functional test
Module Assy level Thermal Cycling
no
Contact SLAC MRB
Functional test
Move to next op.
19Manufacturing Process Flow-GTC
- Top assembly/final test/final inspection
Assemble TEM/TPS
Stake HW
Functional Test
Top Assy level Thermal Cycling
Source inspection EIDP review
Vibration test
Functional test
Final functional test
Pack ship to SLAC
20Configuration Management
- Required changes to documentation during the
manufacturing phase at GTC will be immediately
documented on an NCMR and forwarded to SLAC for
disposition - All outstanding changes to documents will be
incorporated and a new revision released into LAT
DOCs prior to final inspection at each
manufacturing level (CCA, Module, Top Assembly)
21Configuration Management
- All change notices will include full disposition
of hardware
Disposition of Hardware
22GTC Test Requirements
Figure 1. Vibration Levels, Duration, and Spectra
23GTC Qualification and Acceptance Test Matrix
24Production Schedule
25Production Schedule
26Production Schedule
27Issues/Concerns
- Actel FPGAs pose a reliability concern
- Maxim 724 is rated at 2.6-32.0V, we are biasing
to operating at 1.5V. Parts were not screened for
this application, PCB reviewing screening
requirements.