Title: Operational Readiness


1
Operational Readiness Airport Transfer(ORAT)
Suvarnabhumi Airport Serirat Prasutanond
Executive Vice President (Special
Affairs)Airports of Thailand Public Company
Ltd.ICAO TCB Seminar 13th January 2004
2
ORAT - Suvarnabhumi Airport
Topics of Presentation
  • Introduction - Airports of Thailand Public
    Company Ltd. - ICAO TCB support
  • New Bangkok International Airport
  • ORAT Programme
  • Trial Operations
  • Relocation

3
ORAT - Suvarnabhumi Airport
An introduction - Airports of Thailand Public
Company Ltd.
4
ORAT - Suvarnabhumi Airport Introduction
  • Operational Readiness and Airport Transfer (ORAT)
    Programme
  • ICAO TCB support
  • to achieve successful opening of Suvarnabhumi
    Airport

5
ORAT - Suvarnabhumi Airport Introduction
  • ICAOs Roles
  • provide ORAT advice assistance to AOT
  • identify plans, tasks and needs and initiate
    activities to ensure ORAT Programme
    implementation
  • integrate external parties into overall ORAT
    Programme
  • develop concepts trial operations relocation
  • assist in development testing of airport
    systems, facilities procedures, and operational
    trials

6
ORAT - Suvarnabhumi Airport New Bangkok
International Airport

Video Preview on Suvarnabhumi Airport
7
ORAT - Suvarnabhumi AirportNew Bangkok
International Airport
  • Key features of Suvarnabhumi Airport
  • World-class airport with terminal capacity for
    45 MPA (Phase 1)
  • Single largest terminal in the world
  • In-line security screening system
  • State-of-the-art BHS
  • Advanced IT-based system (AIMS)
  • Dual runways for all types of aircraft
  • All-weather navigational aids
  • ICAO Category 10 fire-fighting capability

8
ORAT - Suvarnabhumi AirportNew Bangkok
International Airport
Overview Airport Development - PTC/Concourses
9
ORAT - Suvarnabhumi AirportNew Bangkok
International Airport
Current Status - Passenger Terminal Building
22nd October 2003, w.molitor
22nd October 2003, w.molitor
10
ORAT - Suvarnabhumi AirportNew Bangkok
International Airport
Current Status - Concourses
Pictures provided by NBIA, PR Department ,
November 2003
11
ORAT - Suvarnabhumi Airport
Private Investments/Privatized Packages
  • Privatized Packages
  • (Concessionaires
  • selected by NBIA)
  • District Cooling System and Power Plant
  • Medical facility
  • Car rental facility
  • Petrol Station
  • Aircraft refuelling Facilities (fuel hydrant
    system)
  • THAI Airways
  • Cargo Mail
  • Catering
  • Customer Services
  • Aircraft Maintenance
  • Ground Services
  • Operations Centre
  • Privatized Packages
  • (Concessionaires
  • selected by AOT)
  • 2nd 3rd Catering Facilities
  • Into-plane Services
  • Car parking
  • Aircraft refuelling systems (except hydrants)
  • AEROTHAI
  • Control Tower
  • ATC Services
  • Bangkok
  • Airways
  • Cargo Mail
  • Ground
  • Services



12
ORAT - Suvarnabhumi Airport Responsibilities of
Parties
  • Integrated Partnership

13
ORAT - Suvarnabhumi Airport
  • Goals of ORAT Programme
  • Involvement and commitment of all airport users
  • Resolution of operational interface issues
  • Successful trial operations and relocation
  • Timely inauguration
  • Efficient operation from Day One
  • Higher quality and service level standard

14
ORAT - Suvarnabhumi Airport
prevent failure!!!





15
ORAT - Suvarnabhumi Airport Phases
ORAT Phases


Planning
Construction Phases
Design
Planning
Construction
Functional Implementation
Commissioning
  • 30.03.2005

Trial Operations
AOT and other agencies
  • 01.09.2005

Relocation
  • 29.09.2005

Start of Operations
16
ORAT - Suvarnabhumi Airport - Responsibilities
Developers NBIA, THAI, AEROTHAI, etc...
WHO?
Operation
of Functions
HOW?
Facilities Systems
WHO?
Operational Interface Coordination
Operation
of Systems
HOW?
Interaction (Procedures) Human Resources
WHO?
Maintenance
of Facilities
HOW?
Airport Operator, Airlines, CIQ etc. 40,000
airport staff
17
ORAT - Suvarnabhumi Airport Committees
18
ORAT - Suvarnabhumi Airport Functional Planning
Airport Operation Functions Matrix (Matrix
contains 600 Airport Functions)

Core Processes 1. Airport Access 2. PAX
Crew Handling 3. Baggage Handling 4. Cargo
Mail Handling 5. Aircraft Handling 6.
Aircraft Control 7. Administration
Management 8. Facilities System Management
9. Airport Security 10. Commercial Optimization
Customer Services 11. Environmental
Integration
  • Task of Functions Matrix
  • Splits the Airport into manageable parts and
  • helps us to identify and coordinate
  • Interfaces
  • Responsibilities
  • Operational planning activities
  • Optimize each function prior to start of
  • operations

19
ORAT - Suvarnabhumi Airport - Trial Operation
Trial Operations
20
ORAT - Suvarnabhumi Airport - Trial Operation
Misleading directional signage Underground
Parking
Passenger Flow
Gate Allocation
Immi
Fire-fighting
CIQ
BHS
Safety hazard - sharp edges
21
ORAT - Suvarnabhumi Airport - Trial Operation
Pre-requisites for Trial Operation
Procedures
Facilities
Trained Staff
Systems
Scenarios
Trials
Equipment
Verification Assessment
Start of Operation
22
ORAT - Suvarnabhumi Airport - Relocation
KLIA

Relocation
Meticuluously planned and implemented to
accomplish task
HKIA
Denver
Munich
23
ORAT - Suvarnabhumi Airport Relocation
Expected Distribution Volume

A - Coordination

B - Coordination


Pre-Move
Post-Move
28/29 Sept.
Main Move
  • A Coordination
  • Only one responsible Removal Forwarder
    pool.
  • Common transport for all parties
  • Fixed calculated time-slots, transport
    ways and procedures
  • B Coordination
  • Removal company of own choice
  • Coordination by ORAT Relocation Planning
    Team

24
ORAT - Suvarnabhumi Airport ORAT Programme

Joint Objective
Smooth Airport Operations from Day One onwards
ORAT
AOT
Thai Airways
Development NBIA
PG other Airlines
AEROTHAI
Facilitation Departm.
Concession
Airport PrivatizedPackages
25
ORAT - Suvarnabhumi Airport
  • Information
  • Internet / Website Links http//www.airportthai.
    com/http//www.bangkokairport.orghttp//www.icao
    .int/icao/en/tcb/TCBhome.htm
  • Contacts AOT Mr. Serirat Prasutanond
  • Executive Vice President (Special
    Affairs) Airports of Thailand Public Comp. Ltd.
  • 333 Cherdwutagard Road, Don Mueang,
  • Bangkok 10210 Tel 66 (0)-2535-1821 Fax 66
    (0)-2535-5511 Email seriratp_at_airportthai.co.th
  • ICAO Bangkok Regional Office, Mr. Shah
    Regional Director Tel 66 (0)-2537-8189 Fax
    66 (0)-2537-8199 Email icao_apac_at_bangkok.icao.
    int ICAO Project Office Mr. Walter Molitor
    Chief Technical Adviser/Team Leader Tel 66
    (0)-2535-7033 Fax 66 (0)-2535-7038 Email
    walter_at_molitor.com
Write a Comment
User Comments (0)
About PowerShow.com