Title: Categorizers CAT Team Recurring ORPS Report Vote Utility Strikes
1Categorizers (CAT) Team Recurring ORPS Report
Vote Utility Strikes
2AGENDA!
- Purpose
- Facilitation
- Rules of the Meeting
- Categorizers
- Observers
- Qtr. ORPS Performance Analysis Results
- Utility Strike Events
- R Reporting Criteria
- R Report Requirements
- Presentation by Ray Costa
- Q A Session
- Categorizer Vote
- The Path Forward
-
3Rules of the Meeting
- This meeting is primarily for the Categorizers
- Free flow discussion among Categorizers allowed
- Observers
- Must raise hand and be acknowledged prior to
speaking - We must remain focused on the relevant issues!
4ORPS Quarterly Performance Analysis and Summary
3rd Quarter CY 2004
- 20 utility strikes occurred from January 1, 2000
to September 30, 2004 - 6 reportable to ORPS
- 3 utility strikes occurred in CY 2004
Electrical Utility (Encased in Concrete Floor)
Conduit Strike, Domestic Water Main Strike (not
reportable in ORPS), and Comm Cable Severed
During Excavation Work (not reportable in ORPS).
5ORPS Quarterly Performance Analysis and Summary
3rd Quarter CY 2004
- Procedure Not Used or Used Incorrectly was
assigned as a cause for 4 of the 6 occurrences. - PE Excavation Procedure (EP-ESH-801) was cited
as a procedure to be revised in 3 different
occurrence reports 2000, Strike Underground
Electric Cables - Roll up Report, 2002 Minor
Utility Strike During Horizontal Boring
Operations, and 2003 Communication Cable Struck
During Excavation. - All 6 occurrences involved a contractor or
subcontractor performing work.
6R Reporting Criteria
- The following are questions that should be
considered as indicators or contributing
attributes to a recurring event. - Did the trending data for the series/group of
events indicate a significant negative trend? - Were there a significant number or percentage of
implementation failures discovered to indicate
that one or more components of the program were
not effective in ensuring successful completion
of the task or activity? - Have multiple control failures within the
boundaries of a single occurrence taken place
indicating a common breakdown in a program or
area of a program? - Have small and apparently isolated series/groups
of events been seen within various aspects of an
overall program that collectively indicate a
program weakness when viewed from a site
perspective? - Have failures been discovered that indicate
during implementation of a particular program, or
portion of a program, that one or more components
of the program were not effective in ensuring
successful completion of the task or activity? - Was there a common underlying cause or weakness
in controls that necessitated corrective actions?
7R Reporting Criteria
- Did the group of related events indicate a series
of common work process breakdowns or a series of
common quality criteria issues? - Did related series/groups of events breach
multiple, but not necessarily all, barriers
protecting workers, the public, or the
environment from potential or actual adverse
impacts of an event? - Did related series/groups of events, having the
same underlying cause or having contributed to or
were the unavoidable consequence of the
underlying problem, occur within a single
facility or operation? - Did a causal factor of the series/group of events
indicate a lack of management involvement, or
breakdown in management controls, or errors in
decisions/directions by managers that resulted in
systemic problems or violation of safety rules? - In Short . . .
8Note R Report Requirements
9- Utility Strike Evaluation
- Ray Costa
- FO ESHTQ
- Interim Manager
10Agenda
- History
- Definitions
- Data Analysis
- Corrective Actions
- Lessons Learned
- Summary
11History
- November 2003
- Jim Tarpinian, ALD ESHTQ requested Andy
McNerney, ALD FO, to have Plant Engineering
evaluate utility strike data presented to ORPS
Categorizers - Requested Plant Engineering to
- Evaluate the data and provide further information
on any trends or recurring conditions that exist
between these events - Answer the following questions
- Is there evidence verifying that the corrective
actions from the utility strike events was
completed? - Is the effectiveness of corrective actions
evaluated in the Plant Engineering
self-assessment process? - Does Plant Engineering review and apply the
Lessons Learned Communications they receive?
12Terminology and Challenges
- Excavation
- Digging into soil with heavy equipment and/or
with a shovel or pick - Challenges
- Accurate location of known utilities
- Abandoned utilities not identified on maps or not
known to exist - Army era utilities poorly documented on Camp
Upton drawings - Many drawings date back to the 1940s, are hand
drawn and do not accurately locate utilities - Not all utilities added by non-Plant Engineering
projects provided to update utilities maps - Penetration
- Digging into cement or masonry with power tools
(e.g., jack hammer, saw, drill) and/or with a
hand chisel - Challenges
- Utilities can be located close to one another in
a small area, i.e., congested - Rebar buried in cement, makes it hard to locate
utilities accurately - And those challenges noted in excavation apply
here as well
13The Data
- To understand what is happening over a 5 year
period we need to time phase the events - We need to identify the activity that led to the
utility strike - Look at causes to identify trends
14All Utility Strikes
15Plant Engineering Utility Strikes by Activity
16Plant Engineering Activities Resulting in
Utility Strikes
- Totals over last 5 years
- Excavation 12
- Vehicle Accidents 3
- Penetrations 2
- Excavation is the highest contributor and needs
closer analysis for possible trends
17Whats in the Ground at BNL?
- 11 miles of steam condensate piping
- 45 miles of potable water piping
- 19.7 miles of sanitary piping
- 1.6 miles of chilled water piping
- 1.6 miles of compressed air piping
- 9 miles of storm water collection piping
- In addition to
- Electric cables
- Telecommunications cables
- Network cables
- Fire Alarms cables
- Security Alarms cables
- Abandoned and unknown utilities
18Plant EngineeringExcavations Activity Vs.
Utility Strikes
19Plant Engineering Excavation Utility Strikes
20Plant Engineering Root Causes of Excavation
Utility Strikes
21What the Data Shows
- No injuries resulted from any of these utility
strikes - Utility marking and permit violations were the
major contributors in 2000 2001 - Corrective actions appear to be effective
- No repeats from 2002 to present
- All corrective actions have been completed and
appear to have been effective in reducing utility
strikes - Abandoned and poorly documented legacy utilities
are the primary cause and are very difficult to
locate
22Corrective Actions Taken
- Procedure
- Clarification of toning process
- Clarification of responsibilities
- Permit refinement
- Lessons learned incorporated
- Marking instructions and re-inspections added
- Created a Configuration Control procedure to
address legacy issues and map errors - Design standards updated to standardize burial
depths - Require the updating of site utility maps (hard
copies) as unidentified utilities are found - Training
- Lessons Learned communicated and shared
- Disciplinary actions taken
- Contractors
- Formal warnings issued
- Safety Inspection Report issued to contractor and
Project Manager - Negative impact on performance rating
- Recovery of cost of repairs from contract
23Proactive Actions
- Revised procedures to add expiration date to
digging permits (2001) - Training on utility locating instruments held on
site by Staking University (2001) - Standardized the process for how utilities are
documented on contract drawings (2001) - Sent Plant Engineering representatives to the
Big Dig conference (2002) - Re-established Excavation and Penetration
Committee (2002) - Purchased hydro-vacuum (2002)
- Revised procedures to have contractor sign that
he has reviewed the digging permit and marked-up
utility drawings with the project manager prior
to the start of work (2003) - Excavation safety is regular agenda item at
monthly Plant Engineering ESH Committee Meeting - Digitizing old hand drawings to aid in
researching legacy issues (on-going) - Continually evaluating new equipment to locate
unknown utilities (on-going) - Continually evaluating the excavation and
penetration processes to improve them (on-going)
24Corrective Action Process
- Every Plant Engineering ORPS results in a
critique and corrective actions - Status of ORPS reviewed monthly, at Division
Quarterly Reviews, and during DOE / Plant
Engineering Quarterly Construction Reviews - Every non-ORPS results in an Investigative
Incident and corrective actions as appropriate - All corrective actions tracked to completion by
ATS or FOs FATS equivalent - FO FATS equivalent
- Notification of action sent to lead person
- Due notice sent 90 days before due date and every
month until closed - Overdue report sent to Division Manager and
responsible Manager quarterly - Trending in process Tier Is complete for Plant
Engineering - All Plant Engineering Corrective Actions
resulting from Utility Strikes have been completed
25Verification of Corrective Actions
- Job Site Inspections
- Planned as part of Tier I program
- Management walkthroughs
- Safety Inspections performed by Plant Engineering
Contractor Safety Inspectors - Over 900 safety inspections per year
26Assessments
- Excavation Safety Assessment performed by
Independent Oversight (IO) in July 2003 - Reviewed documentation
- Interviewed personnel
- Observed excavations in progress
- IO found
- Processes to control excavation work and ensure
the safety of workers are in place as required by
both DOE and OSHA - Identified several strengths in work control and
excavation safety including - Plant Engineering Division being established as
the single Lab-wide point-of-contact for digging
permits and the identification and marking of
underground utilities - Implementation of training for Competent Persons
- Proactive involvement of appropriate expertise in
the review of excavation work plans - The institution of an Excavation Safety Committee
striving to minimize utility strikes - Areas for improvement
- Predominantly subject area improvements
- Plant Engineering needed to add OSHA Trenching
and Excavation to JTA requirements - Training being performed, not in JTA
27Lessons Learned
- BNL shares lessons learned with all site
personnel via e-mail, bulletin, and other
available channels - Lessons learned pertinent Plant Engineering
operations are distributed via e-mail by Plant
Engineerings ESH Coordinator or ESHTQ Manager - Additional lessons learned from other than BNL
sources are identified and distributed - Lessons learned are posted in Plant Engineerings
buildings, as appropriate on ESH Bulletin Boards - Supervisors share lessons learned with their
staff as a toolbox meetings
28Summary
- No persistent trends identified over the last
three years - Corrective actions appear to be effective as
demonstrated in reduction of utility strikes over
the last 3 years - Undocumented utilities provide the potential for
additional strikes - Constantly updating utility maps to reflect what
we know - Digitizing old drawings and overlaying on BNL
photogrametry to improve searches of legacy
issues - Continuing to evaluate state-of-the-art utility
location equipment to locate the unknown