Categorizers CAT Team Recurring ORPS Report Vote Utility Strikes - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

Categorizers CAT Team Recurring ORPS Report Vote Utility Strikes

Description:

Brookhaven Science Associates. U.S. Department of Energy ... CY 2004; Electrical Utility (Encased in Concrete Floor) Conduit Strike, Domestic ... – PowerPoint PPT presentation

Number of Views:51
Avg rating:3.0/5.0
Slides: 29
Provided by: joycemo
Category:

less

Transcript and Presenter's Notes

Title: Categorizers CAT Team Recurring ORPS Report Vote Utility Strikes


1
Categorizers (CAT) Team Recurring ORPS Report
Vote Utility Strikes
2
AGENDA!
  • Purpose
  • Facilitation
  • Rules of the Meeting
  • Categorizers
  • Observers
  • Qtr. ORPS Performance Analysis Results
  • Utility Strike Events
  • R Reporting Criteria
  • R Report Requirements
  • Presentation by Ray Costa
  • Q A Session
  • Categorizer Vote
  • The Path Forward
  •       

3
Rules of the Meeting
  • This meeting is primarily for the Categorizers
  • Free flow discussion among Categorizers allowed
  • Observers
  • Must raise hand and be acknowledged prior to
    speaking
  • We must remain focused on the relevant issues!

4
ORPS Quarterly Performance Analysis and Summary
3rd Quarter CY 2004
  • 20 utility strikes occurred from January 1, 2000
    to September 30, 2004
  • 6 reportable to ORPS
  • 3 utility strikes occurred in CY 2004
    Electrical Utility (Encased in Concrete Floor)
    Conduit Strike, Domestic Water Main Strike (not
    reportable in ORPS), and Comm Cable Severed
    During Excavation Work (not reportable in ORPS).

5
ORPS Quarterly Performance Analysis and Summary
3rd Quarter CY 2004
  • Procedure Not Used or Used Incorrectly was
    assigned as a cause for 4 of the 6 occurrences.
  • PE Excavation Procedure (EP-ESH-801) was cited
    as a procedure to be revised in 3 different
    occurrence reports 2000, Strike Underground
    Electric Cables - Roll up Report, 2002 Minor
    Utility Strike During Horizontal Boring
    Operations, and 2003 Communication Cable Struck
    During Excavation.
  • All 6 occurrences involved a contractor or
    subcontractor performing work.

6
R Reporting Criteria
  • The following are questions that should be
    considered as indicators or contributing
    attributes to a recurring event.
  • Did the trending data for the series/group of
    events indicate a significant negative trend?
  • Were there a significant number or percentage of
    implementation failures discovered to indicate
    that one or more components of the program were
    not effective in ensuring successful completion
    of the task or activity?
  • Have multiple control failures within the
    boundaries of a single occurrence taken place
    indicating a common breakdown in a program or
    area of a program?
  • Have small and apparently isolated series/groups
    of events been seen within various aspects of an
    overall program that collectively indicate a
    program weakness when viewed from a site
    perspective?
  • Have failures been discovered that indicate
    during implementation of a particular program, or
    portion of a program, that one or more components
    of the program were not effective in ensuring
    successful completion of the task or activity?
  • Was there a common underlying cause or weakness
    in controls that necessitated corrective actions?

7
R Reporting Criteria
  • Did the group of related events indicate a series
    of common work process breakdowns or a series of
    common quality criteria issues?
  • Did related series/groups of events breach
    multiple, but not necessarily all, barriers
    protecting workers, the public, or the
    environment from potential or actual adverse
    impacts of an event?
  • Did related series/groups of events, having the
    same underlying cause or having contributed to or
    were the unavoidable consequence of the
    underlying problem, occur within a single
    facility or operation?
  • Did a causal factor of the series/group of events
    indicate a lack of management involvement, or
    breakdown in management controls, or errors in
    decisions/directions by managers that resulted in
    systemic problems or violation of safety rules?
  • In Short . . .

8
Note R Report Requirements
9
  • Utility Strike Evaluation
  • Ray Costa
  • FO ESHTQ
  • Interim Manager

10
Agenda
  • History
  • Definitions
  • Data Analysis
  • Corrective Actions
  • Lessons Learned
  • Summary

11
History
  • November 2003
  • Jim Tarpinian, ALD ESHTQ requested Andy
    McNerney, ALD FO, to have Plant Engineering
    evaluate utility strike data presented to ORPS
    Categorizers
  • Requested Plant Engineering to
  • Evaluate the data and provide further information
    on any trends or recurring conditions that exist
    between these events
  • Answer the following questions 
  • Is there evidence verifying that the corrective
    actions from the utility strike events was
    completed?
  • Is the effectiveness of corrective actions
    evaluated in the Plant Engineering
    self-assessment process?
  • Does Plant Engineering review and apply the
    Lessons Learned Communications they receive?

12
Terminology and Challenges
  • Excavation
  • Digging into soil with heavy equipment and/or
    with a shovel or pick
  • Challenges
  • Accurate location of known utilities
  • Abandoned utilities not identified on maps or not
    known to exist
  • Army era utilities poorly documented on Camp
    Upton drawings
  • Many drawings date back to the 1940s, are hand
    drawn and do not accurately locate utilities
  • Not all utilities added by non-Plant Engineering
    projects provided to update utilities maps
  • Penetration
  • Digging into cement or masonry with power tools
    (e.g., jack hammer, saw, drill) and/or with a
    hand chisel
  • Challenges
  • Utilities can be located close to one another in
    a small area, i.e., congested
  • Rebar buried in cement, makes it hard to locate
    utilities accurately
  • And those challenges noted in excavation apply
    here as well

13
The Data
  • To understand what is happening over a 5 year
    period we need to time phase the events
  • We need to identify the activity that led to the
    utility strike
  • Look at causes to identify trends

14
All Utility Strikes
15
Plant Engineering Utility Strikes by Activity
16
Plant Engineering Activities Resulting in
Utility Strikes
  • Totals over last 5 years
  • Excavation 12
  • Vehicle Accidents 3
  • Penetrations 2
  • Excavation is the highest contributor and needs
    closer analysis for possible trends

17
Whats in the Ground at BNL?
  • 11 miles of steam condensate piping
  • 45 miles of potable water piping
  • 19.7 miles of sanitary piping
  • 1.6 miles of chilled water piping
  • 1.6 miles of compressed air piping
  • 9 miles of storm water collection piping
  • In addition to
  • Electric cables
  • Telecommunications cables
  • Network cables
  • Fire Alarms cables
  • Security Alarms cables
  • Abandoned and unknown utilities

18
Plant EngineeringExcavations Activity Vs.
Utility Strikes
19
Plant Engineering Excavation Utility Strikes
20
Plant Engineering Root Causes of Excavation
Utility Strikes
21
What the Data Shows
  • No injuries resulted from any of these utility
    strikes
  • Utility marking and permit violations were the
    major contributors in 2000 2001
  • Corrective actions appear to be effective
  • No repeats from 2002 to present
  • All corrective actions have been completed and
    appear to have been effective in reducing utility
    strikes
  • Abandoned and poorly documented legacy utilities
    are the primary cause and are very difficult to
    locate

22
Corrective Actions Taken
  • Procedure
  • Clarification of toning process
  • Clarification of responsibilities
  • Permit refinement
  • Lessons learned incorporated
  • Marking instructions and re-inspections added
  • Created a Configuration Control procedure to
    address legacy issues and map errors
  • Design standards updated to standardize burial
    depths
  • Require the updating of site utility maps (hard
    copies) as unidentified utilities are found
  • Training
  • Lessons Learned communicated and shared
  • Disciplinary actions taken
  • Contractors
  • Formal warnings issued
  • Safety Inspection Report issued to contractor and
    Project Manager
  • Negative impact on performance rating
  • Recovery of cost of repairs from contract

23
Proactive Actions
  • Revised procedures to add expiration date to
    digging permits (2001)
  • Training on utility locating instruments held on
    site by Staking University (2001)
  • Standardized the process for how utilities are
    documented on contract drawings (2001)
  • Sent Plant Engineering representatives to the
    Big Dig conference (2002)
  • Re-established Excavation and Penetration
    Committee (2002)
  • Purchased hydro-vacuum (2002)
  • Revised procedures to have contractor sign that
    he has reviewed the digging permit and marked-up
    utility drawings with the project manager prior
    to the start of work (2003)
  • Excavation safety is regular agenda item at
    monthly Plant Engineering ESH Committee Meeting
  • Digitizing old hand drawings to aid in
    researching legacy issues (on-going)
  • Continually evaluating new equipment to locate
    unknown utilities (on-going)
  • Continually evaluating the excavation and
    penetration processes to improve them (on-going)

24
Corrective Action Process
  • Every Plant Engineering ORPS results in a
    critique and corrective actions
  • Status of ORPS reviewed monthly, at Division
    Quarterly Reviews, and during DOE / Plant
    Engineering Quarterly Construction Reviews
  • Every non-ORPS results in an Investigative
    Incident and corrective actions as appropriate
  • All corrective actions tracked to completion by
    ATS or FOs FATS equivalent
  • FO FATS equivalent
  • Notification of action sent to lead person
  • Due notice sent 90 days before due date and every
    month until closed
  • Overdue report sent to Division Manager and
    responsible Manager quarterly
  • Trending in process Tier Is complete for Plant
    Engineering
  • All Plant Engineering Corrective Actions
    resulting from Utility Strikes have been completed

25
Verification of Corrective Actions
  • Job Site Inspections
  • Planned as part of Tier I program
  • Management walkthroughs
  • Safety Inspections performed by Plant Engineering
    Contractor Safety Inspectors
  • Over 900 safety inspections per year

26
Assessments
  • Excavation Safety Assessment performed by
    Independent Oversight (IO) in July 2003
  • Reviewed documentation
  • Interviewed personnel
  • Observed excavations in progress
  • IO found
  • Processes to control excavation work and ensure
    the safety of workers are in place as required by
    both DOE and OSHA
  • Identified several strengths in work control and
    excavation safety including
  • Plant Engineering Division being established as
    the single Lab-wide point-of-contact for digging
    permits and the identification and marking of
    underground utilities
  • Implementation of training for Competent Persons
  • Proactive involvement of appropriate expertise in
    the review of excavation work plans
  • The institution of an Excavation Safety Committee
    striving to minimize utility strikes
  • Areas for improvement
  • Predominantly subject area improvements
  • Plant Engineering needed to add OSHA Trenching
    and Excavation to JTA requirements
  • Training being performed, not in JTA

27
Lessons Learned
  • BNL shares lessons learned with all site
    personnel via e-mail, bulletin, and other
    available channels
  • Lessons learned pertinent Plant Engineering
    operations are distributed via e-mail by Plant
    Engineerings ESH Coordinator or ESHTQ Manager
  • Additional lessons learned from other than BNL
    sources are identified and distributed
  • Lessons learned are posted in Plant Engineerings
    buildings, as appropriate on ESH Bulletin Boards
  • Supervisors share lessons learned with their
    staff as a toolbox meetings

28
Summary
  • No persistent trends identified over the last
    three years
  • Corrective actions appear to be effective as
    demonstrated in reduction of utility strikes over
    the last 3 years
  • Undocumented utilities provide the potential for
    additional strikes
  • Constantly updating utility maps to reflect what
    we know
  • Digitizing old drawings and overlaying on BNL
    photogrametry to improve searches of legacy
    issues
  • Continuing to evaluate state-of-the-art utility
    location equipment to locate the unknown
Write a Comment
User Comments (0)
About PowerShow.com