Title: Approaching the design of ILC conventional magnets for the RDR
1Approaching the design of ILC conventional
magnets for the RDR
- Cherrill Spencer, ILC
- 25th April 2006
2 Current General Layout of a 500Gev ILC
Schematic borrowed from Fred Asiri of
Conventional Facilities new labels added.
31 km overall
superconducting linac
Part of e source, e booster auxiliary source
Beam Deliveries 2 Interaction Regions
e- Damping Ring
TWO e Damping Rings
Cherrills rough count totals 12,600 magnets
150 styles! About 600 quads in the main linacs
75 others will be superconducting. So approx
11,925 conventional magnets.
3 Recall our philosophies for
designing and costing NLC magnets, power supplies
power cables
- NLC magnet designing and estimating of costs
took place from 1999 to 2003 - Recall our approaches for NLC and consider which
might be appropriate for the ILC magnet
designing and costing exercise towards writing
the RDR - First cost estimate in 1999 had to be done in a
few months like we have to now, then we revised
our counts and costs several times over next 4
years. - Look at some old NLC presentation slides from
July 2000 next 12 slides
4Roles Responsibilities of the Magnet
Cost-estimating Group 1/3
- ROLES
- Define technical scope of all magnets, power
supplies, cables and cable trays - Develop NLC-wide design, manufacturing and QC
philosophies - Develop NLC-wide permanent electromagnet
costing guidelines - incorporating Management Grp guidelines
- Develop cost estimating processes to fit in with
current WBS structure -includes validation - Apply cost estimating processes
- Check our costs been assigned correctly in the
appropriate WBS elements
5Roles and Responsibilities page 2/3
- RESPONSIBILITIES
- Following magnet team engimators are responsible
for estimating the MS and labor costs for all
activity phases up to, but not including
installation of listed items - Ponce Rodriguez- all areas DC cables, magnet
related IC cables, all cable trays - Wes Asher- Power Supplies auxiliary equip for
damping rings beam delivery - Steve Lowe- all PCD coordination drafting
- Val Nesterov- Power Supplies auxiliary
equipment for injector main linac - Bobby McKee- Magnets for damping rings
- Carl Rago- Magnets for injector main linac
- ( No-one) - Magnets for beam delivery
- Cherrill Spencer- responsible for developing or
interpreting costing guidelines, negotiating
treaty points, acquiring validating data,
scrutinizing team member estimates, checking how
our estimates are assigned in the WBS
6 Roles and Responsibilitiespage 3/3
- plus cost estimates for the controlling
electronics of the permanent magnet field tuners
come from Mike Browne, CD. - The magnet cost estimating group are NOT
responsible for costing - Subsystem mechanical assembly drawings
- e.g. magnet plus support drawings
- Any system drawings containing magnets
- installation costs exact treaty point being
clarified with the Installation TSET - Movers and supports
- BPMs
- Vacuum chambers
- System engineering beyond typical magnet, PS or
cables subsystem engineering design tasks that
make sure our components fit/work with other
beamline components
7Define Magnet Technical System
- 1. Understand how magnets and power supplies and
cables fit into the WBS. - 2. Respond to functional requirements. Create
descriptions and technical specs. - 3. Define boundaries of a generic magnet and a
generic PS. Make and document treaty points
with other TSET teams. - 4. Count how many magnets in each beamline, count
styles, count PS, cables. - 5. Develop detailed lists of parts that must be
included in a magnet or PS cost estimate.
8NLC-wide Magnet Design Philosophy
- NLC magnets are approx 50 water or air cooled
conventional electromagnets can be powered by
off-the-shelf PS, and approx 50permanent magnets - All engineering, drafting, magnetic
measurements done by NLC employees - Our major technical challenges
- Produce 5600 magnets over 7 years
- Make them extremely reliable
- Minimize cost while maintaining performance
- To meet these challenges we will
- Identify failure modes using FMEA,design in
reliability - Have uniform standards for common materials such
as ferrite, steel, conductor, cooling hoses - Have standard designs for common parts such as
terminal blocks, coil retainers, manifolds - Have a restricted list of approved off-the-shelf
parts water fittings, insulation, epoxies
9NLC-wide Magnet Manufacturing Philosophy
- Most electromagnets will be fabricated in other
countries, some by commercial companies or SLAC
or other HEP labs. - Most permanent magnets will be assembled at FNAL
by non-shop technicians - Need to make an early start on specifying steel
and identifying steel vendors, ditto permanent
magnetic materials - Choose materials to mitigate E.SH concerns
- Will have tightly coordinated controlled
- material procurement tracking
- fabrication processes
- drawing release revision
- Will have on-site high capacity comprehensive
incoming magnet inspection and measurement
facility. ALL magnets will be QAd and
magnetically measured.
10NLC-wide DC PS Manufacturing Philosophy
- Philosophy driven by large number of systems and
stringent reliability requirements. - Performance goals can be met with SWITCH MODE
power supplies. - Most PS to be built by commercial companies, are
within the 1kW-15kW range now available - Units will be modified production versions
- connectorized to allow replacing failed units
quickly in system (quick-swap) - PS controller provides mechanism to adapt
commercial supplies to NLC applications. - PS controller will be quite different from
existing SLAC (PEPII/SLC/FFTB) designs.
11Develop cost estimating processes- in progress
- Have developed various cost estimating processes
for magnets, PS and cables. - Characteristics of these processes, they
- pay attention to our design and manufacturing
philosophies- permanent methods in progress - are applied consistently across all 3 beam areas.
- use the tremendous hands-on knowledge of our team
members to produce realistic estimates. - currently provide estimates aiming to be 50
confident, learning how to assign in the WBS
structure easily and without error. - are flexible and repeatable so as to quickly
accomodate changes as we refine costs between now
and CDR. - use NLC labor types and hourly rates.
12Some general cost-estimating assumptions
- We will have designed, built, equipped and
staffed these on-site facilities for testing,
final assembly and measurement of all magnets and
power supplies - an incoming magnet testing and magnetic
measurement facility - a magnet fiducialization lab with a CMM
- a PS pre-assembly and test lab
- an electronics rack assembly facility
- Repetitive tasks are identified, number of labor
hours per task agreed upon and used by all - Commonly used parts/materials are identified,
cost of such items agreed upon and used by all - EDI estimates include analysis, design
engineering, some subsystem engineering,
manufacturing engineering, as well as drafting.
13CD0.4 Magnet specific costing guidelines
- Electromagnet Specific Assumptions
- Solid steel cores, low carbon steel prices
- Hollow core copper conductor Potted coils
- SLAC style insulation and epoxy
- Agreed upon list of components
- Fabricated offshore use offshore labor codes
- PS Specific Assumptions
- Every group of same style PS has one quick
spare PS added to cost no 2-for-1 redundancy - Use 1999 catalog price of existing standard
commercial PS reduced by 10 - Same controller cost for every PS system
- DC Power Cable Specific Assumptions
- Cable lengths assume cut cover tunnels and
TEEs shorter cables than in Lehman. - Cable size are gt NEC reduce heat put into
beamline housings.
14Typical Electromagnet Costing Process
- Is a bottom-up process, assume small quantity
- Choose a specd magnet with a layout drawing
- Make a parts list
- Make a drawing list how many, what size.
- Make a BH task list
- Determine materials costs using common prices
- Estimate hours for fabing each part
- For standard parts use NLC list of costs
- use outside vendor estimate or ask SLAC shops
remember they give high estimates - ask Magnet Engineer
- use appropriate labor type, use offshore labor
rates - Calculate fabrication costs, apply learning curve
for higher quantity if not inherently in the
hours estimate - chose learning curve percentage appropriate to
the mix of hand assembly and machining - Estimate drafting hours using NLC list of hours
per drawing by complexity and size. - Compare result with historical data on similar
magnets, both from SLAC or other labs.
15Cable and Tray Costing Process
- For Lehman did detailed, bottom-up beamline by
beamline cost estimates - Material cost based on RS Means Electrical Cost
Data or vendor quotes - Installation labor hours based on above RS Means
- hours/feet length of size X cable Ysize tray. - For CD0.4 has removed many cables completely ,
estimated rest in detail - Engineering estimated at 20 of MS, then divided
between phases - Cable sizes-larger than National Electrical Code
- Injector NEC 2
- DR NEC 1
- Main Linac NEC 5
- Beam Delivery NEC 3
16 MOST CHALLENGING ASPECT OF ILC CONVENTIONAL
MAGNETS MAKING THEM RELIABLE ENOUGH
- Consider the availability requirements of the ILC
as set out in the BCD - A good idea for each engineer to read Chapter 10
of the BCD - Got to this URL and download the Operations and
Reliability chapter - http//www.linearcollider.org/wiki/doku.php?idbcd
bcd_home - Describes a simulation of the whole ILC that has
been developed and the models output tells you
how long the ILC will be down it its components
have certain mean time between failures (MTBF)
and certain times to repair (Mean Time to Repair
MTTR). - OVERALL ILC UPTIME GOAL IS 85 during the
official runs of 9 months per year
17Availability DEFINITIONS
Availability Average ratio of the time that the
system or component is usable to the total amount
of time that is needed.
MTBF (Mean Time Between Failure) MTBF is a basic
measure of reliability for repairable items. It
can be described as the number of hours that pass
before a component, assembly, or system fails.
Failure rate MTBF-1 l
MTTR (Mean Time To Repair) MTTR is the average
time required to perform corrective repair on the
removable items in a product or system.
Availability of N magnets (Availability of one
magnet) N
Expected Downtime in hours (1-Availability) x
Operation hour/year
18 How total allowed downtime of 17
is distributed among tech systems (assuming 17
15)
Magnets allowed 5 of 17gt0.8
In certain scenario each magnets MTBF has to be
20 million hours
All 12600 magnets allowed to be down 0.8 of ILC
running time. Same as need to be up 99.2 of
time!
19Measuring Electromagnet Availability at Stanford
Linear Accelerator Center
- Obtain magnet failure history (CATER system) for
5 year period (1997-2001) - Categorize data into solid wire and water-cooled
electromagnet types. - Calculate average beam downtime for different
types of magnet from failure data. - Obtain SLAC beamlines runtime schedule for this 5
year period. - Count number of magnets in each SLAC beamline
during specific runtime periods. - Identify magnet failures that shut down the beam
from CATER system report for each runtime period.
CATER is an accelerator failure tracking
database - Calculate magnet operating hours by multiplying
number of magnets by run hours for each period. - Calculate MTBF, MTTR and availability of one
magnet for each period. - Calculate average availability for one magnet
using all or some subset of the SLAC beamlines
data. - This process repeated for switching power supply
failures over same period.
20Summary of SLAC magnet PS failure data
solid magnets with solid wire coils water
magnets with water cooled coils small PS
lt12A, lt50V large PS gt12A,gt50V. Time to
repair is the total hours the beam was down for
the stated failures, so MTTR Time to repair/No.
of failures.
21 How the MTBF value can vary depending
on time period studied, choice of magnets
- From SLAC 1997-2001 data water cooled
electromagnets average MTBF was 1,150,000 hours,
i.e. about 1/20th of what the ILC needs! - But look at a different period and eliminate the
worst offenders - This 2002 dataset does not include any magnets
in the 2 SLC damping rings, which have
notoriously failure-prone magnetsby removing
them from the dataset one can make the average
MTBF vastly longer 12,000,000 hours,. We
understand why the DR magnets fail more
frequently and would avoid making the same design
mistakes in ILC magnets. - IN ANY EVENT, FOR THE ILC, WE CANNOT DESIGN AND
FABRICATE MAGNETS LIKE WE HAVE BEEN DOING FOR THE
PAST 40 YEARS AT SLAC. - We have to carry out a detailed Failure Modes and
Effects Analysis (FMEA) to learn how to revise
our magnet designs and fabrication techniques to
make more reliable magnets
22 When we really get to design the ILC
magnets we will have to do FMEAs on basic magnet
styles
- Failure Mode and Effects Analysis (FMEA) process
considers each mode of failure of every component
of the system, identifies their causes and
ascertains the effects of each failure mode on
system operation (ALL ILC components should have
FMEA done on them). - As we cost estimate the ILC magnets we will have
to account for the cost of doing FMEAs and paying
for some higher quality materials and more
expensive processes. - The causes of the most severe and likely to occur
failures of a standard SLAC water- cooled
electromagnet were identified as (a) water leaks
and corrosion (b) various assembly errors. - Design changes were made in the conductor,
terminals, core numbers of items.
23 FABRICATION FEATURES of E-M QUAD DRIVEN BY
RELIABILITY OR COST NEEDS
- Solid C1006 steel core, 4 quadrants ground on the
outside 4 pieces bolted together and the 4
poletips coil pockets EDMd in the same
operation 0.005mm reproducibility on the
poletips better coil pocket stability and
tolerances. Machining cost less. - Hollow seamless ROUND copper tubing (per ASTM
B75) used for conductor, several advantages
compared to square conductor easier to wind not
prone to twisting does not keystone much
smoother internal surface with many less crevices
and defects where corrosion can start allows
direct attachment to compression fittings. Coil
winding cost less. - New style power terminals commercial motor
disconnects, modified to be brazed onto the
conductor coil leads cheaper and more reliable
than custom made multifunction terminals - Potted coils instead of wet lay-up better
dimensional stability and water resistance. The
reduction in number of coils shorting out from
nearby water leaks worth the higher cost. - Prototype quad was made and has been run for
many hours over 4 year period in a measurement
set-up without any failures