SABER Overview and Management, Costs and Schedule - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

SABER Overview and Management, Costs and Schedule

Description:

In March 2006 held a User Workshop run by R. Siemann and C. Joshi defined focus ... Yearly Operational Costs for SABER (4 month run/yr) (FY2006 k ... – PowerPoint PPT presentation

Number of Views:71
Avg rating:3.0/5.0
Slides: 33
Provided by: see65
Category:

less

Transcript and Presenter's Notes

Title: SABER Overview and Management, Costs and Schedule


1
SABEROverview and Management, Costs and
Schedule
  • John Seeman
  • Assistant Director
  • Particle and Particle-Astrophysics Directorate
  • SLAC
  • December 6, 2006

2
Overview
  • There was a constant demand for electron and
    positron beams in the Final Focus Test beam
    (FFTB) from a wide variety of accelerator physics
    users.
  • However, the FFTB has recently been removed to
    make room for the Linac Coherent Light Source
    (LCLS).
  • The FFTB accelerator beam capabilities can be
    relocated in a straight forward way to an area of
    the SLC South Arc tunnel called SABER (South Arc
    Beam Experimental Region).
  • The existing electron longitudinal bunch
    compressor at the 1/3 point in the linac can be
    modified to compress positron bunches, as well,
    opening world-unique new opportunities for
    accelerator research.
  • A bypass line from Sector 20 to the end of the
    Linac can be built to deliver beams to SABER,
    independent of LCLS.

3
History of SABER Design Effort
  • In 2003 P. Krejcik proposed a SLC South Arc
    Instrument Section solution for an FFTB
    replacement.
  • In 2004 P. Emma proposed B-Target Room solution.
  • In June 2005 P. Drell charged the Accelerator
    Systems Division to develop the detailed
    accelerator options, organized by R. Erickson.
  • In March 2006 held a User Workshop run by R.
    Siemann and C. Joshi defined focus topics of
    experimental accelerator physics and endorsed the
    South Arc Option, now called SABER.
  • First draft SABER White Paper Spring 2006.
  • August 2006 SABER White Paper submitted to DOE
    HEP.
  • DOE Germantown visit for SABER in August 2006.
  • SABER DOE review December 2006.

4

Initial SABER Layout Possibilities

ESA
LCLS tunnel
ESB B Target Room
South Arc
5
Historical Beam Line Possibilities
  • 1) SLC South Arc (SABER)
  • 2) SLC North Arc (NABER)
  • 3) B-Target Room (BTR)
  • 4) End Station A (ESA)
  • 5) Reinstall FFTB in LCLS tunnel where FFTB was
    before.
  • 6) PEP-II North Injection Transport (NIT)
  • 7) PEP-II South Injection Transport (SIT)

6
Conclusions of 2005 study
  • SLC North Arc does not have an Instrument Section
    and no easy experimenter entrance.
  • ESA dipole bends are too strong and quadrupoles
    too weak to allow small emittance beams to pass.
    ? Complete overhaul!
  • B-Target-Room (BTR) would be ideal but no
    transport exists now. It would take many years
    (4) (assuming modest funding) before the first
    beam would go through.
  • LCLS tunnel construction and operation allows no
    access until late 2009 or 2010 at the earliest.
  • PEP-II Injection lines have bends that are too
    strong for emittance preservation and the energy
    is too low.
  • SLC South Arc was designed for low emittance
    preservation and the basic hardware exists. This
    transport provides same beam quality as BTR.
    Experimenters can access region with LCLS and
    PEP-II running. Good shielding. Only modest but
    adequate experimenter space.

7
Present ProposalSLAC Overview with SABER in SLC
South Arc
  • SABER consists of three main components
  • (1) Experimental area with final focus and beam
    dump in SLC South Arc tunnel.
  • (2) Linac Pulse Compressor upgrade to compress
    positron bunches.
  • (3) Bypass Line to deliver e- or e beams to
    SABER, bypassing the LCLS.

(2)
e
e-
(3)
(1)

8
Three basic SABER areas
  • Final Focus Makes a small beam spot (lt10
    microns) for experimenters. Similar design and
    layout as FFTB final focus.
  • Sector 10 compressor for e Allows the
    production of positrons by e- and the delivery of
    short bunch length e to the experimenter. Same
    design and layout as present e- compressor.
  • Bypass line Allows independent operation from
    LCLS. Similar design and layout as PEP-II
    injection bypass lines.
  • ? The technology is the same as the former FFTB,
    SLC arcs, and existing PEP-II injection bypass
    lines.
  • ? Minimal design and engineering needed!

9
SABER Design Team
  • Head R. Erickson
  • Mechanical engineers L. Bentson, D. Blankenship,
    S. DeBarger, N. Li, H. Shin
  • Area Manager A. Baker
  • Optics Y. Nosochkov, M. Woodley
  • Alignment C. LeCocq
  • Beam dynamics K. Bane, P. Emma
  • Radiation physics J. Bauer, A. Prinz
  • Personnel Protection System P. Bong, K. Turner
  • Experimental region M. Hogan, D. Walz
  • Physics consultants R. Iverson, P. Krejcik, T.
    Fieguth
  • Budget J. Seeman

10
Basic SABER Beam Parameters
  • Beam Energy 28 GeV
  • Single bunch per pulse
  • 30 Hz (120 Hz possible)
  • Charge per bunch 1 x 109 to 2-3.5 x 1010
  • Bunch length 30 microns
  • Transverse spot size at experiment lt10 microns
  • Energy spread 0.5 to 4

11
South Arc Tunnel
(Hogan, Erickson)
Beam Instrument Section
User experiments to be set up in this area.

12
Positron Compressor Chicane
  • The Sector 10 chicane can be modified to be
    symmetric for electrons and positrons.

e
e-
(Bentson)
13
Bypass Line
  • A Bypass Line from Sector 20 to the South Arc
    will allow delivery of 28 GeV electrons to SABER
    without passing through the last third of linac.
  • SABER will then be independent of LCLS
    operations.
  • An optics design has been fully worked out.
  • Value engineering is ongoing to minimize the
    cost.
  • The proposal is to reuse a PEP-II injection
    bypass line to save costs (5 M). (To be
    modified in Fall 2008 after the PEP-II run ends.)

14
Bypass Transport Line will be like the PEP-II
lines
SABER Bypass could go here
PEP-II injection Lines (SABER Bypass could go
here)

e return line
Linac
15

Nosochkov

16

Example of new design Bypass Line Quadrupole
Design for 30 GeV

N. Li
August 2005
17
Proposed SABER Schedule
  • Fall 2006 Restore safety systems, repair vacuum
    pumping and install temporary beam dump.
  • February-March 2007 Inject initial 28 GeV beam
    through SLC Arc to future SABER region for
    checkout of existing hardware. (Compressed e- or
    non-compressed e but large beams.)
  • Spring 2007 Start SABER relocation work.
  • August 2007 Complete relocation of SABER final
    focus. Install initial experimental area. Provide
    first e- beam to SABER compressed and focused.
    (Assumes full SABER funding 2.5 M in FY2007.)
  • FY2008 Deliver e- compressed focused beam to
    SABER. Deliver non-compressed positrons.
  • Fall 2008 Installation of positron compressor
    chicane in Linac Sector 10. Some Bypass Line
    work.
  • Winter 2009 Positron beam, fully compressed and
    focused to experimental region as beam time
    allows.
  • Fall 2009 Bypass Line assembly and installation.
  • FY2010 and beyond Four full months of SABER
    operation every year.

18

SLAC Tentative Beam Schedule

19
LCLS Injector with 135 MeV Spectrometer

SABER Beam (before bypass)
LCLS Beam
20
Initial beam specifications

21
SABER Management
  • The management of SABER will be done with a
    similar mechanism to ongoing Accelerator
    Improvement Projects (AIP)
  • AIP Management Mechanism
  • Divide work into stand alone pieces.
  • Define proposed technical scope and budget for
    each piece.
  • DOE approves the proposals.
  • A task manager is assigned.
  • Monthly reviews are held covering technical
    issues, budget, man power, and schedule.
  • Monthly budget statements are reviewed by task
    personnel, upper management and DOE.
  • There is a formal task closeout with DOE when
    each task is finished.

22
Recent AIP Accelerator Improvement
Projects(handled with management tools described
above)
Budget
Completion date
  • X-Y BPM upgrades 825k Done
  • New HER Q5 vacuum chambers 650k Done
  • New HER/LER Q2 chambers 436k Done
  • HER-10 RF station 2800k Feb 2007
  • LER-5 RF station 4380k Feb 2007
  • HER power supply upgrade for higher
    tunes 680k Dec 2006
  • New HER Q4 vacuum chambers 476k Done
  • New IR2 Q2 bellows 150k Feb 2007
  • LER IR HOM absorber 225k Dec 2006
  • HER IR HOM absorber 210k Done
  • LER BPM monitor upgrade 330k Apr 2007
  • LER new high power bellows 300k Done
  • LER NEG vacuum chamber upgrade 250k Done
  • New Longitudinal feedback processor 494k Mar
    2007
  • MCC network upgrade 290k Apr 2007
  • Linac SCOR to MCOR Upgrade 690 Sept 2007

Total cost of these AIP projects is about 4 to 7
M per year. Most tasks will be finished in a few
months. Ready for new tasks.
23

24
Example AIP PEP-II HER RF Station
C. Carter
25
Example AIP PEP-II HER RF Station (Cont)
26
Methodology for Cost Estimates
  • Estimate manpower required using present
    productivity rates (include training, safety, ).
  • Identify all the components needed.
  • Determine materials needed from existing designs
    of constructed components.
  • Check projected costs against actual costs to
    build similar lines last time including
    inflation.
  • Add SLAC burden rates of 6 on materials and
    39 on labor.
  • Add contingency of 25 to 30.

27
SABER Relocation Costs with New Bypass Line

28
Reuse 1 km of PEP-II Injection Bypass Line

Linac Sector 21-30 (exists)
Sector 20 (exists)
51 Line (exists)
South Arc (exists)
Extraction Line (new)
Re-injection Line (new)
Drift Line (exists but 12 ? 30 GeV)
50 m
1000 m
50 m
Drift Line Reuse Vacuum chambers, pumps and
controls Beam position monitors Beam size
monitors Steering corrector magnets Quadrupole
magnets and power supplies New Extra quadrupole
magnets, power supplies, supports, water
29
SABER Relocation Costs with Reused Bypass Line

30
Manpower and Shop Availability
  • The needed mechanical and electrical engineering
    for SABER will come from PEP-II activities which
    are winding down in FY2007. (Several semi-retired
    SLC electrical engineers are willing to work part
    time.)
  • Much of the SABER work are supports and simple
    vacuum chambers. Many of the LCLS supports and
    vacuum chambers are being made with outside
    vendors.
  • SABER installation and shop work dove-tails with
    LCLS work
  • Install SABER final focus in spring-summer 2007
    when LCLS is not installing.
  • e compressor installation in Fall 2008 is a
    relatively small task when LCLS is installing the
    last few items.
  • Install SABER Bypass Line in Fall 2009 when LCLS
    installation is done.

31
Yearly Operational Costs for SABER (4 month
run/yr)(FY2006 k)
e- only
e and e-
  • Linac Sectors 0-20 AC power for
    operations 1075 900
  • SABER beam and transport AC power 281 281
  • Linac Sector 0-20 Operations 900 750
  • SABER Operations and Maintenance 2600 2460
  • Total with burden (non-power sum x 1.33)
    6010 5450

32
Summary
  • SABER has been defined to a level that final
    engineering and shop work can begin.
  • The reuse of one of the PEP-II injection lines
    can significantly reduce the cost of the bypass
    (5 M).
  • There is sufficient manpower and shop effort
    available at SLAC to do the work.
  • This relocation activity can be divided into
    manageable sub-pieces (final focus, compressor,
    and bypass line)
  • Management practices can be the same as those for
    other AIP activities which are of the same size
    and complexity.
Write a Comment
User Comments (0)
About PowerShow.com