Title: Need for Prefabricated Bridge Elements and Systems for Accelerated Bridge Construction
1Need for Prefabricated Bridge Elements and
Systems for Accelerated Bridge Construction
WASHTO-X Webinar June 17, 2008
By Vasant Mistry Federal Highway
Administration vasant.mistry_at_fhwa.dot.gov
2Topics
- Update on FHWA Survey on ABC
- Standardizing Prefabricated Bridge Elements and
Systems (PBES) - Available Tools and Resources
3Accelerated Bridge Construction
- is to build the bridge first before you set
cones, - then quickly move it into place like in hours
or a weekend!
4Update on FHWA Survey on Accelerated Bridge
Construction
5States using systematic economic process
6Applying ABC for construction of new structures
7Applying ABC for rehabilitation of existing
structures
8Standardizing Prefabricated Bridge Elements and
Systems
9Precast Abutments
10Precast Abutments
11Precast Piers
12Precast Piers
13Precast deck on precast concrete girders
14Precast Decks on Steel Framing
15Precast Decks
16FRP Decks
17Total Bridge Prefabrication
18Total Bridge Prefabrication
19Superstructure Prefabricationwith Continuity
20Superstructure Prefabricationwith Continuity
21Retaining Walls
- Mechanically Stabilized Earth Walls
- Precast Gravity Walls
- Precast Cantilever
22Available Tools and Resources
- Learn more
- www.fhwa.dot.gov/bridge/prefab
- Tools
- Decision-Making Framework for the Use of
Prefabricated Bridges - Self-Propelled Modular Transporters (SPMT) Manual
- Connection Detail Catalog for PBES
- FHWA ABC Workshops for DOTs
- FHWA Contacts
- Vasant Mistry at Vasant.Mistry_at_dot.gov
- Kathleen Bergeron at Kathleen.Bergeron_at_dot.gov
23Prefabricated Bridge Elements and Systems (PBES)
- PBES offers significant advantages over
Cast-in-place construction - Reduction in onsite construction time
- Reduction in Traffic and Environmental impact
- Lower First and Life-Cycle Costs
- Improves Safety and Quality
-
24Thank You
Accelerated Bridge Construction