Western Cape: Department of Health Public Hearing on Conditional Grants and Capital Expenditure 1st

Description:

A Twelfth of the grants are allocated, monthly, in order to avoid over expenditure ... Improve day-to-day management. R35,669. 231 staff in service. Recruit and ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 12
Provided by: Nnal
Category:

less

Transcript and Presenter's Notes

Title: Western Cape: Department of Health Public Hearing on Conditional Grants and Capital Expenditure 1st


1
Western Cape Department of HealthPublic Hearing
on Conditional Grants and Capital Expenditure 1st
and 2nd Quarter 2007/8
  • 13 November 2007

2
National Conditional Grants1st and 2nd Quarter
2007/8
3
National Tertiary Services Grant Heath
Professional Training and Development Grant
4
National Tertiary Services Grant Heath
Professional Training and Development Grant
  • A Twelfth of the grants are allocated, monthly,
    in order to avoid over expenditure
  • For the NTSG the receiving hospitals provide
    quarterly activity reports which are submitted to
    the National Department of Health and National
    Treasury
  • Annual student surveys are conducted in
    collaboration with the Universities. This is used
    to monitor and plan the HPTDG
  • All monthly financial reports have been
    submitted.

5
Forensic Pathology Services Grant
6
Forensic Pathology Services Grant
7
Forensic Pathology Services Grant
  • The current spending trends reflect the
    following
  • A under spend on Personnel costs of R5 926m,
  • An overspend on Machinery Equipment of R7 471m
  • An overspend on Buildings Fixtures of R31 188m
  • And Goods and Services breaking even
  • Subsequent to the adjustment budget and
    roll-overs the projected overspend for Forensic
    Pathology is estimated to be R2 512m by year end
  • All reports and submissions for 2007/8 have been
    submitted to the National Department of Health

8
HIV and AIDS Grant
9
HIV and AIDS Grant
  • The current reflection of under-spending is
    mainly due to a lag in the transfer payments to
    Non-Government Organizations. These are being
    addressed.
  • There is presently an under-expenditure in
    Personnel costs as all the vacant posts have not
    been filled, however, should all the posts be
    filled this would result in an over expenditure
    by the year end.
  • The price of drugs have decreased resulting in a
    saving in Goods and Services costs
  • All monthly and quarterly reports for 2007/08 to
    date have been submitted to the National
    Department of Health.

10
Hospital Revitalisation Grant Infrastructure
Grantto Province
11
Hospital Revitalisation Grant Infrastructure
Grantto Province
  • All projects are monitored in terms of cost and
    status via a monthly progress control meeting
    between the Departments of Health and Transport
    Public Works.
  • Projects are also monitored via Treasurys
    quarterly infrastructure reports, as well as
    monthly financial reports for both HRP and IGP.
  • HRP has a function responsible for monitoring and
    evaluation of projects as prescribed by National
    Department of Health.
  • HRP submits monthly and quarterly reports to
    National Department of Health.
  • Projections indicate that IGP will break even and
    that HRP will overspend for the current financial
    year. A request for front-loading on next years
    budget has been made to Treasury which will
    alleviate the over expenditure on HRP.
  • The projected over expenditure is mainly due to
    some essential variations required on the
    projects at Worcester and Paarl Hospitals and the
    fact that very good momentum is maintained on
    both projects.