1 Chapter 3 Aggregate Planning 2 Production Planning Environment Competitors Behavior Raw Material Availability Market Demand Planning for Production External Capacity (outsourcing) Economic Conditions Current Physical Capacity Current Inventory Current Work Force Required Production Activities 3 Planning Production
Long-range plan (3-10 years) updated yearly
Inputs aggregate forecasts (units) and current plant capacity (hours)
Decision build new plant expand an existing plant create new product line expand contract or delete existing product lines
Level of detail Very Aggregated
Degree of uncertainty High
4 Planning Production
Intermediate-range plan (6 month 2 years) updated quarterly
Inputs aggregate capacity and product decisions from the long-term plan units are aggregated by product line or family and plant department
Decision changes in work force additional machines subcontracting overtime
Level of detail Aggregated
Degree of uncertainty Medium
5 Planning Production
Short-range plan (1 week 6 month) updated daily or weekly
Inputs decisions from the intermediate-term plan units are aggregated by particular product and capacity available hours on a particular machine short range forecast inventory levels work force levels processes
Decision overtime and undertime possibility of not fulfilling all demand subcontracting delivery dates for suppliers product quality
Level of detail Very Detailed
Degree of uncertainty Low
6 Production Planning Example
Small company makes one product plastic cases to hold CDs.
Two different types of mold are used to produce top bottom.
Two halves are manually put together placed in the boxes shipped.
The injection molding machines can make 550 pieces per hour.
A worker can finish 55 cases in 1 hour (10 workers / machine)
Forecasts of demand 80000 cases per month for next year at 4 weeks/month the demand should be 20000 cases per week.
Company runs 5 out of 7 days per week 4000 cases per day needed.
Each worker can not work more than 8 hours per day
4000/8 500 pieces per hour have to be produced.
Plan 1 machine 10 workers 8 hours/day 5 days/week
7 Introduction to Aggregate Planning
Constant production rate can be satisfied with constant capacity.
Work force is constant production rate slightly less that capacity of people machines good utilization without overloading the facilities.
Raw material usage is also constant.
If supplier and customers are also close frequent deliveries of raw material and finished goods will keep inventory low.
How realistic is this example
Strategies to cope with fluctuating demand
-- change the demand -- produce at constant rate anyway -- vary the production rate -- use combination of above strategies 8 Introduction to Aggregate PlanningInfluencing Demand
Do not satisfy demand during peak periods
Capacity lt Peak demand constant production rate
Loss of some sales
Japanese car manufacturers often take this stance
Determine percentage of the market share
Constant production is set at this level
Sales personal expected to sell produced amount
Ease of planning must be compared to lost revenue
9 Introduction to Aggregate PlanningInfluencing Demand
Shift demand from peak periods to non-peak periods / create new demand for non-peak periods
Creating new demand can be done through advertising or incentive programs (automobile industry rebates telephone companys differential pricing system)
Smoothing demand
10 Introduction to Aggregate PlanningInfluencing Demand
Produce several products with peak demand in different periods
Products should be similar so that manufacturing them is not too different
Snowmobiles and jetskis same engines similar body work
Lawn-mowers snowblowers baseball football equipment
11 Medium Range Planning Aggregate Production Planning
Establish production rates by major product groups
by labor hours required or units of production
Attempt to determine monthly work force size and inventory levels that minimizes production related costs over the planning period (for 6-24 month)
12 Relevant Costs Involved
Regular time costs
Costs of producing a unit of output during regular working hours including direct and indirect labor material manufacturing expenses
Overtime costs
Costs associated with using manpower beyond normal working hours
Production-rate change costs
Costs incurred in substantially altering the production rate
Inventory associated costs
Out of pocket costs associated with carrying inventory
Costs of insufficient capacity in the short run
Costs incurred as a result of backordering lost sales revenue loss of goodwill costs of actions initiated to prevent shortages
Control system costs
Costs of acquiring the data for analytical decision computational effort and implementation costs
13 Aggregate Units
The method is based on notion of aggregate units.
They may be
Actual units of production
Weight (tons of steel)
Volume (gallons of gasoline)
Dollars (value of sales)
Fictitious aggregate units
14 Overview of the Problem
D1 D2 . . . DT - the forecasts of demand for aggregate units over the planning horizon (T periods)
Determine Wt - work force levels
Pt - production levels
It inventory levels
Ht number of workers hired in this period
Ft number of workers fired in this period
Ot overtime production in units
Ut undertime worker idle time in units
St number of units subcontracted from outside
to minimize total costs over the T period planning horizon
Forecasts for demand for aggregate units can be obtained by taking a weighted average (using the same weights) of individual item forecasts.
17 Example (continued)
The washing machine plant is interested in determining work force and production levels for the next 8 months
Forecasted demands for Jan-Aug. are
420 280 460 190 310 145 110 125
Starting inventory at the end of December is 200 and the firm would like to have 100 units on hand at the end of August
Find monthly production levels
18 Step 1 Determine net demand.(subtract starting inventory from period 1 forecast and add ending inventory to period 8 forecast)
Month Forecasted Net Predicted Cum. Net
Demand Demand Demand
1(Jan) 420 420-200220 220
2(Feb) 280 280 500
3(Mar) 460 460 960
4(Apr) 190 190 1150
5(May) 310 310 1460
6(June) 145 145 1605
7(July) 110 110 1715
8(Aug) 125 125100225 1940
Starting inventory - 200 and final inventory - 100 units
19 Step 2. Graph Cumulative Net Demand to Find Plans Graphically Draw a straight line from first point 220 to 1940 units in month 8 The slope of the line is the number of units to produce each month. Determine a production plan that doesnt change the size of the workforce over the planning horizon. What to do 20 Monthly Production 1940 / 8 242.5 (rounded to 243/month) Any shortfalls in this solution 21 How can we have a constant work force plan with no stockouts
Using the graph find the straight line that goes through the origin and lies completely above the cumulative net demand curve
22 From the previous graph we see that cum. net demand curve is crossed at period 3 so that monthly production is 960/3 320. Ending inventory each month is found from
Month Cum. Net. Dem. Cum. Prod. Invent.
1(Jan) 220 320 100
2(Feb) 500 640 140
3(Mar) 960 960 0
4(Apr.) 1150 1280 130
5(May) 1460 1600 140
6(June) 1605 1920 315
7(July) 1715 2240 525
8(Aug) 1940 2560 620
23 However
This solution may not be realistic for several reasons
It may not be possible to achieve the production level of 320 unit/mo with an integer number of workers
Since all months do not have the same number of workdays a constant production level may not translate to the same number of workers each month
Some thoughts
Final inventory is 620 units not 100 units
Cost of carrying inventory in each period
24 Production Strategies
Constant production rate with Zero inventory
stockouts
carrying inventory
Constant production rate with no stockouts
carrying inventory
extra inventory at the period T
Mixed strategy
few changes in the workforce allowed
more flexibility
lower costs
25 Example 2 (based on example 1)
The plant has 38 workers who produced 630 units in a period of 40 days
K 630/(3840) 0.414 average number of units produced by one worker in one day
Assume we are given the following working days per month
jan 22 apr 20 jul 18
feb 16 may 21 aug 10
mar 23 jun 17
26 Constant Work Force Production Plan 38 workers K .414
(100 units at the end of the august in included in 687 units inventory)
Hence Inventory Cost 20958.517809.37
Payroll cost
(75/worker/day)(38 workers )(167days) 475950
Cost of plan
475950 17809.37 4800 498559.37
29 Cost Reduction in Constant Work Force Plan
In the original cum net demand curve consider making reductions in the work force one or more times over the planning horizon to decrease inventory investment.
30 Cost Evaluation of Modified Plan with One Workforce Adjustment
The modified plan calls for
hiring 6 workers in Jan (to 38)
reducing the workforce to 23 (from 38) at start of April
cost of hiring is 4800.00 4800.00
cost of layoffs is 18750.00 0.00
payroll cost is 356700.00 475950.00
holding costs are 2528.93 17809.37
shortage costs are 7770.40 0.00
The total cost of the modified plan is 390548.33
Original plan had cost of 498559.37
31 Cost Evaluation of Modified Plan with Two Workforce Adjustment
The modified plan calls for
hiring 6 workers in January
firing 8 workers at start of April
firing 12 workers at start of June
Two One None
cost of hiring is 4800.00 4800.00 4800.00
cost of layoffs is 25000.00 18750.00 0.00
payroll cost is 353850.00 356700.00 475950.00
holding costs are 3452.87 2528.93 17809.37
shortage costs are 0.00 7770.40 0.00
The total cost 387102.87 390548.33 498559.37
32 Constant Work Force Production Plan 38 workers K .414
Month wk Prod. Cum Cum Nt End Inv
days Dem Level Prod Dem
Jan 22 220 346 346 220 126
Feb 16 280 252 598 500 98
Mar 23 460 362 960 960 0
Apr 20 190 315 1275 1150 125
May 21 310 330 1605 1460 145
Jun 22 145 346 1951 1605 346
Jul 21 110 330 2281 1715 566
Aug 22 125 346 2627 1940 687
100
33 Cost Reduction in Constant Work Force Plan 34 Zero Inventory Plan (Chase Strategy)
Idea
change the workforce each month in order to match the workforce with monthly demand as closely as possible
This is accomplished by computing the units produced by one worker each month (by multiplying K by days per month)
Then take net demand each month and dividing by this quantity. The resulting ratio is rounded up and possibly adjusted downward.
35
At the end of December there are 32 workers
Period hired fired
1 7 Cost of this
2 17 plan
3 6 461732.08
4 25
5 13
6 20
7 4
8 13
36 Hybrid Strategies
Use a combination of options
Build-up inventory ahead of rising demand use backorders to level extreme peaks
Finished goods inventories Anticipate demand
Back orders lost sales Delay delivery or allow demand to go unfilled
Shift demand to off-peak times Proactive marketing
Overtime Short-term option
Pay workers a premium to work longer hours
37 Hybrid Strategies
Undertime Short-term option
Slow the production rate or send workers home early (lowers labor productivity but doesnt tie up capital in finished good inventories)
Reassign workers to preventive maintenance during lulls
Subcontracting Medium-term option
Subcontract production or hire temporary workers to cover short-term peaks
Hire fire workers Long-term option
Change the size of the workforce
Layoff or furlough workers during lulls
38 Another APP Example Quarter Sales Forecast (lb) Spring 80000 Summer 50000 Fall 120000 Winter 150000
_________________________
Hiring cost 100 per worker
Firing cost 500 per worker
Inventory carrying cost 0.50 per pound per quarter
Production per employee 1000 pounds per quarter
Beginning work force 100 workers
39 Level Production Strategy
Sales Production
Quarter Forecast Plan Inventory
Spring 80000 100000 20000
Summer 50000 100000 70000
Fall 120000 100000 50000
Winter 150000 100000 0
400000 140000
Cost 140000 pounds x 0.50 per pound 70000
40 Chase Demand Strategy (Zero Inventory) Hiring cost 100 per worker Firing cost 500 per worker Inventory carrying cost 0.50 per pound per quarter Production per employee 1000 pounds per quarter Beginning work force 100 workers
Sales Production Workers Workers Workers
Quarter Forecast Plan Needed Hired Fired
Spring 80000 80000 80 - 20
Summer 50000 50000 50 - 30
Fall 120000 120000 120 70 -
Winter 150000 150000 150 30 -
100 50
Cost (100 workers hired x 100) (50 workers fired x 500)
10000 25000 35000
41 APP By Linear Programming
Min Z 100 (H1 H2 H3 H4) 500 (F1 F2 F3 F4) 0.50 (I1 I2 I3 I4)
Subject to
P1 - I1 80000 (1) Demand
I1 P2 - I2 50000 (2) constraints
I2 P3 - I3 120000 (3)
I3 P4 - I4 150000 (4)
P1 - 1000 W1 0 (5) Production
P2 - 1000 W2 0 (6) constraints
P3 - 1000 W3 0 (7)
P4 - 1000 W4 0 (8)
W1 - H1 F1 100 (9) Work force
W2 - W1 - H2 F2 0 (10) constraints
W3 - W2 - H3 F3 0 (11)
W4 - W3 - H4 F4 0 (12)
where Ht hired for period t Ft fired for period t It inventory at end of period t Wt workforce at period t Pt units produced at period t 42 Optimal Solutions to Aggregate Planning Problems Via Linear Programming
Dt the forecasts of demand for aggregate units for period t t 1 T
nt number of units that can be made by one worker in period t
CtP cost to produce one unit in period t
CtW cost of one worker in period t
CtH cost to hire one worker in period t
CtL cost to layoff one worker in period t
CtI cost to hold one unit in inventory in period t
CtB cost to backorder one unit in period t
Wt number of workers available in period t
Pt number of units produced in period t
It number of units held in the inventory at the end of period t
Ht number of workers hired in period t
Ft number of workers fired in period t
43 Optimal Solutions to Aggregate Planning Problems Via Linear Programming
LP
s.t constraints
All variables are continuously divisible is it a problem
Solution Produce 214.5 of aggregated units
Hire 56.38 workers
IP
s.t constraints
Some variables are continuously divisible some are real number only problem
44 Linear Programming Objective Function and Constraints
Number of constraints is 3T number of unknown is 5T
Multiple products processed on various workstation
i an index of product i 1 m
j an index of workstation j 1 n
t an index of period t 1 T
Dit the maximum demand for product i for period t
dit the minimum sales allows of product i for period t
aij time required on workstation j to produce one unit of product i
cjt capacity of workstation j in period t in the same units as aij
ri net profit from one unit of product i
hi cost to hold one unit of product i for one period in the inventory
Xit amount of product i produced in period t
Sit amount of product i sold in period t
Iit number of units of product i held in the inventory at the end of period t
46 Linear Programming Product Mixed Planning Objective Function and Constraints This model can be used to obtain information on demand feasibility bottleneck location product mix 47 Product Mix Planning
Demand feasibility
Determine if the set of demands is capacity-feasible
If SitDit then demand is feasible otherwise demand is infeasible
If could not find a feasible solution then lower bound dit is too high for a given capacity
Bottleneck locations
Constraints restrict production on each workstation in each period
Observe binding constraints to determine which workstations limit capacity
Consistently binding workstation is a bottleneck
Require close management attention
Product mix
If capacity is an issue then model will try to maximize revenue by utilizing products with high net profit
48 Homework Assignment
Read chapter 3 sections 1 4
Problems
3.5
3.9 3.11
3.14 3.16
49 References
Presentations by McGraw-Hill/Irwin and WilsonG.R.
Production Operations Analysis by S.Nahmias
Factory Physics by W.J.Hopp M.L.Spearman
Inventory Management and Production Planning and Scheduling by E.A. Silver D.F. Pyke R. Peterson
Production Planning Control and Integration by D. Sipper and R.L. Bulfin Jr.
About PowerShow.com
PowerShow.com is a leading presentation/slideshow sharing website. Whether your application is business, how-to, education, medicine, school, church, sales, marketing, online training or just for fun, PowerShow.com is a great resource. And, best of all, most of its cool features are free and easy to use.
You can use PowerShow.com to find and download example online PowerPoint ppt presentations on just about any topic you can imagine so you can learn how to improve your own slides and presentations for free. Or use it to find and download high-quality how-to PowerPoint ppt presentations with illustrated or animated slides that will teach you how to do something new, also for free. Or use it to upload your own PowerPoint slides so you can share them with your teachers, class, students, bosses, employees, customers, potential investors or the world. Or use it to create really cool photo slideshows - with 2D and 3D transitions, animation, and your choice of music - that you can share with your Facebook friends or Google+ circles. That's all free as well!
For a small fee you can get the industry's best online privacy or publicly promote your presentations and slide shows with top rankings. But aside from that it's free. We'll even convert your presentations and slide shows into the universal Flash format with all their original multimedia glory, including animation, 2D and 3D transition effects, embedded music or other audio, or even video embedded in slides. All for free. Most of the presentations and slideshows on PowerShow.com are free to view, many are even free to download. (You can choose whether to allow people to download your original PowerPoint presentations and photo slideshows for a fee or free or not at all.) Check out PowerShow.com today - for FREE. There is truly something for everyone!