Title: Explain some of the major changes in the revision to ICR 56
1Introduction
- Explain some of the major changes in the revision
to ICR 56 -
- Correlate revisions to federal regulations (EPA
OSHA) - Christopher Alonge, PE
- NYS DOL DOSH ESU
- Senior Safety and Health Engineer
2Why were revisions necessary?
- To comply with OSHA (29 CFR 1926.1101) EPA
regulations (40 CFR 763, 40 CFR 61) - To clarify many portions of ICR56 and include
existing AVs within the code rule
3ICR 56 Major Revisions
- Many preliminary comments were submitted by
stakeholders regarding the January 20, 2004 draft
of the revised code rule. - The comments were reviewed by the Department and
appropriate revisions incorporated into the
revised code rule. - The previous January 20, 2004 draft together with
the revisions represent the final document
released to the public on July 20, 2005.
4General Rulemaking Process
- Governors Office of Regulatory Reform (GORR)
Approval - Publication of Major Changes to Proposed Rule in
State Register - Proposed Rule available through DOL
- Official Public Comment Period (60 days)
- Comment Responses Generated
- Final Revisions due to comments
- Adoption of Rule Announced in January 11, 2006
State Register
5Current Rulemaking Status
- Rule Adopted, Transition Period Until September
5, 2006 Effective Date - Comment Responses Spreadsheet generated by DOSH
Engineering Located on Website - Amended Code Rule 56 Located on Website
- Transition Period information Located on Website
- Guidance document to be released by Amended Code
Rule effective date September 5, 2006
6Transition Period
- Old or New Code Rule may be used for Asbestos
Projects through September 4, 2006 - Only New Code Rule for Asbestos Projects starting
September 5, 2006 - If site-specific variance used for Asbestos
Project, use Code Rule that variance is based
upon for that Asbestos Project. - Effective September 5, 2006 all variance
submissions must be prepared and submitted by a
currently certified Project Designer.
7Supplemental Documents
- Guidance
- The revised Code Rule can not address every
situation. DOL is developing a guidance document
to supplement the regulation and to assist
stakeholders in implementing the regulation - The guidance document will be based upon current
interpretations/clarifications and responses to
pertinent comments received
8Supplemental Documents (cont.)
- Site-Specific Variances
- All site-specific variances valid until
termination date of variance decision. - New Site-specific variances will be valid for one
year starting September 5, 2006. - All new site-specific variance decisions are
based upon new amended code rule. - Submissions not based upon new code rule must be
revised accordingly, before decision is granted
by ESU.
9Supplemental Documents (cont.)
- Other Variances
- All existing AVs, BVs, and Systemwide-Statewide
Variances will terminate on September 4, 2006 - Petitioners will be contacted prior to
termination date, to allow for necessary
submissions based upon the new code rule - AV-107 for controlled demolition asbestos
projects at municipally owned vacant residential
buildings/structures is being re-evaluated, and a
new AV may be issued by September 5, 2006
10Typical Expected SSVs
- Contaminated Area/Space Cleanup
- Crawlspaces with Soil Floors
- Large Tent Enclosures with Friable ACM Gross
Removal - Incidental Disturbance Cleanup - greater than
minor size - Dry Removal
- Intact Component Removal
- Floor Covering/mastic removal without hardwall
barriers - Negative Air exhaust greater than 25 ft.
- Decontamination Unit Size Reduction due to
Logistics - Exterior Friable ACM or Non-friable ACM rendered
friable abatement - Controlled Demolition Asbestos Project for
structures not unsound - No Plasticizing on cleanable surfaces
- Elevated Abandoned piping/conduit Wrap
Cut/Glovebag Removals
11Multi-employer Worksites
- Asbestos Abatement Contractor responsible to
inform all employers at worksite about nature of
their work, as well as PACM, ACM and asbestos
material (known and assumed) at the work site. - Asbestos Abatement Contractor responsible to
inform all non-asbestos contractors regarding
prohibition of disturbance to PACM, ACM, and
asbestos material at worksite. - Asbestos Abatement Contractor responsible for
notification to owner, all employers and
occupants, located in areas adjacent to Asbestos
Project work areas, for each occurrence of
elevated air sample results, resulting work
stoppage and barrier inspection/repairs completed
due to elevated air sample results.
12Multi-employer Worksites (cont.)
- All non-asbestos contractors responsible for
notification to owner or their auth.
representative upon discovery of PACM or suspect
miscellaneous ACM that has not previously been
identified within required inspections/surveys. - Building/structure owner or their auth.
representative responsible to inform all
employers expected to be at worksite during the
project, about the presence, location and
quantity of PACM, ACM or asbestos material,
within the portion of the building/structure
impacted by the entire project. - All contractors performing a supervisory role on
demolition, renovation, remodeling or repair
projects, shall prohibit disturbance of PACM, ACM
or asbestos material by non-asbestos contractors
under their direct supervision and control, and
shall require all asbestos contractors to be in
compliance with the code rule.
13Cleanup of Uncontrolled ACM Disturbance
- Who is responsible?
- Upon discovery of uncontrolled disturbance, the
Owner must contract with licensed asbestos
contractor for immediate isolation and cleanup of
disturbed ACM - The Owner shall vacate and generally isolate
(cordon off and turn off impacted HVAC systems)
the room/area/space from remainder of
building/structure, until Asbestos Contractor
arrives on site for completion of isolation
procedures and immediate clean up of disturbance.
14Asbestos Project Phases of Work
15Definitions
- Asbestos Project Phasing chart
- See chart within asbestos project
definition(Phase IA-IB IIA-IID) - Other major definitions added
- Daily Project Log
- PACM Suspect Misc. ACM
- OSHA work classes
- Adequately wet
- Building/Structure Owners Authorized
Representative - Multi-employer work sites
- NESHAP RACM
- NESHAP non-friable categories
- NOB ACM
- AHERA-Bulk Sampling Categories - TSI, Surfacing
Suspect Miscellaneous - Asbestos Contractor
- Asbestos Abatement Contractor
- Asbestos Survey
- Regulated Abatement Work Area
16Recordkeeping/Notifications
- Recordkeeping requirements clarified for
non-abatement asbestos contractors - Project Record to be available on-site with
owners representative during the active portion
(phase II) of an asbestos project. - i.e. full-time project monitor or asbestos
abatement contractor would be typical owner
representatives covered in guidance - Building owner responsible to maintain entire
project record upon conclusion of asbestos
project. - Copies of all project records for past asbestos
projects to be turned over to new
building/structure owner upon transfer of
ownership - Notification requirements clarified for
non-continuous asbestos projects
17Project Air Sampling
- Asbestos Abatement Contractor independent of air
monitoring firm (must be contracted separately by
owner) - Quantity of ACM in work area determines air
sampling requirements for work area - Air sampling Technician on-site for duration of
sample collection - Allow TEMs instead of PCMs for clearance
- TEM clearance AHERA protocols for clearance,
unless TEM analysis of failed PCM air samples.
If AHERA protocol not used for TEM clearance, ICR
56 clearance sampling and clearance criteria
applies
18Project Air Sampling
- Table 2 Asbestos Project Air Sampling
Requirements - Major changes
- Define requirements criteria for background air
samples - Preabatement air samples replaced with work
area preparation samples for large project
friable ACM - Negative air exhaust banking allowed
- Clearance for Minor required for incidental
disturbance if part of small or large project
19Notes (1) For sample location and total
number required, see Subparts 56-6 through
56-9. (2) 1 sample outside the
building/structure if entire building/structure
is regulated abatement work area. (3) Required
on glove bag failure or loss of integrity, or
tent failure or loss of integrity. (4)
Required for an Incidental Disturbance Project or
if minor size regulated abatement work area is
part of small or large asbestos project. (5)
Required for all OSHA Class I and Class II
Friable ACM asbestos projects. (6) During IIC
final cleaning stage, air sampling as per Phase
IIB is required. (7) One additional inside
sample shall be required for every 5,000 sq. ft.
above 25,000 sq. ft. of floor space within the
regulated abatement work area.
20Asbestos Survey/Inspection
- When is a survey required and by who?
- Prior to Building/structure demolition,
remodeling, renovation or repair for
non-agricultural buildings/structures with
construction commencement before 1974 unless
condemned and structurally unsound - Portion of Building/structure impacted by project
shall be inspected/surveyed for ACM by an
asbestos contractor w/appropriately certified
personnel
21Asbestos Survey/Inspection(cont.)
- Survey Exemptions and what they mean
- Not required for agricultural building
- Not required for structurally unsound structure
- However, controlled demolition shall be an
asbestos project (as per ICR 56-11.5) - Not required for owner of one or two-family
dwelling, when the owner contracts for but does
not control the demolition, renovation,
remodeling or repair work - NOTE survey required by owners agent
- However, all contractors hired by the owner must
still comply with OSHA EPA, so all PACM and
suspect misc. ACM is treated and handled as ACM
and is assumed to be ACM until proven otherwise
by appropriate laboratory analyses
22Work Area Preparation
- Asbestos Abatement Contractor Daily Project Log
summary of required entries - Decontamination Units
- Eliminate airlock at work area
- Define Clean room min. size
- Include personal decon remote as well as when and
how they may be used (some special projects,
non-friables tent with glovebag) - Remote waste decon eliminated
- Small Project personal decon reduced to 3
chambers - Electric shutdown/isolation
- shutdown exemption procedures included
23Work Area Preparation(cont.)
- Engineering Controls
- Modify Negative air requirements
- Eliminate piggy-back and restrict exhaust duct
tubing to a maximum of 25 feet in length from
neg. air unit - Reduce 50 foot exhaust requirement to 15 foot, or
if exhaust directly to exterior, then seal
openings within 15 of exhaust location - Use of Manometer for OSHA class I Large Small
asbestos projects document twice per shift - Exhaust Termination Location protected/surrounded
by construction fencing
24Work Area Preparation(cont.)
- Barriers Exemptions
- Floor, Wall Clg. plastic sheeting eliminate
sheeting on removal surfaces - Neg. press. Tents
- Any quantity non-friables
- Any quantity friable TSI w/glovebag-only
abatement - Minor and small quantity gross removal of friable
ACM w/contiguous decon. on small projects - Fire-retardant Spray Plastic
- In lieu of 2 layers floor, wall clg. plastic
sheeting - Applied by trained personnel
- Special Projects See Subpart 11
- Removal of ceilings and components to access ACM
similar to former AV-86
25Handling
- Pre-abatement waiting period reduced to 4 hours
and eliminated for exterior work where negative
air is not required - Daily Inspection/repair required for barriers and
negative air systems - Sequential Abatement - Multiple Abatement within
a single regulated abatement work area - Top-down abatement and most friable to least
friable - For example, ceiling friables, TSI, wall plasters
and other friables, then class II non-friables
other than flooring, ending with class II
non-friable flooring - One complete cleaning at conclusion of each
abatement type, clearance at conclusion of all
abatement and cleanings - When is Dry Removal allowed never according to
the codeguidance issueobtain written EPA
approval first then submit for SSV with EPA
approval
26Final Cleaning Procedures
- Process and settling periods
- Still 3 cleans, but exemption from multiple
cleans when no sheet poly required or tent
enclosure is used - 2 Cleans required for pre-demo asbestos projects
with 1 layer of sheet poly - Reduction in some of the settling/drying periods
- Visual Inspections required following final
cleaning and settling/drying period - Small and Large size work area visual inspection
to be performed by project monitor hired by
building owner independent of asbestos abatement
contractor. Visual inspection as per ASTM E1368
to confirm that the scope of abatement is
complete and no visible debris, residue or pools
of liquid remain. - Supervisor responsible for completeness
inspection prior to project monitor inspection.
27Clearance Procedures
- Exemption for exterior asbestos projects without
negative pressure enclosures. - A satisfactory visual inspection shall serve as
the clearance for these asbestos projects
exception included for 1-2 family owner-occupied
residential building/structures supervisors
inspection allowed but must be acceptable to
owner - Once appropriate clearance has been obtained for
an asbestos project, remaining work area prep
shall be removed, concluding with the
decontamination system enclosures
28Waste Removal from site
- All waste to be removed from work site within ten
calendar days after successful completion of
Phase IIC clearance procedures for all work areas
(or turned over to owner for owners disposal) - All waste removed from site shall be documented,
accounted for and disposed of in compliance with
EPA NESHAP
29Special Projects
- In-Plant Operation changes and what they mean
- Same as before, but now allowed ACM materials
include any quantity non-friable organically
bound (NOB) ACM by outside asbestos contractors - Note Only current ELAP approved labs can make
the NOB ACM determination from bulk samples of
non-friable suspect ACM material - Emergency projects-must call for approval to
proceed with project. SSV may be necessary - Minor Projects
- decontamination room or area required
- includes minor size work area and isolated O M
event
30Special Projects(cont.)
- Pre-demo projects
- Non-porous salvage items may be removed prior to
abatement no disturbance to ACM - Porous walls and floors one layer of plastic
sheeting required instead of 2 layers. - Non-porous cleanable walls, floors and ceilings
dont require plastic sheeting. - Controlled Demolition w/ACM in place - similar to
AV-106
31Special Projects (cont.)
- Exterior Non-friable roofing, siding, caulking,
glazing compound, tars, sealers, coatings other
non-friable ACMs similar to AV-84, AV-89,
AV-119 typical exterior caulking/glazing SSV - Non-friable flooring Mastic similar to AV-120
- Critical barriers, isolation barriers Negative
air ventilation systems required at a minimum - Note Beadblaster or other abrasive abatement
methods require asbestos project abatement as per
full requirements of ICR 56 including attached
decon and 6 air changes per hour - Abandoned pipe/duct/conduit wrap cut similar
to AV-87, only with less limitations