Title: Hazardous Installations Directorate Offshore Division KEY PROGRAMME 3
1Hazardous Installations DirectorateOffshore
DivisionKEY PROGRAMME 3
- INSTALLATION INTEGRITY
- Roger Fronks
- Principal Inspector/Project Manager
Step Change OIM Network - 20 May 2004
2KP3 Installation Integrity
- Topic and key programmes 2004/2005
- 3 Topic Programmes
- Musculo-skeletal disorders and improving
occupational health risks - Reduction in FPSO collision risks
- Incorporating health and safety in design
- 3 Key Programmes
- KP1 managing offshore process integrity
- KP2 risk management in the workplace and
- KP3 .. Installation Integrity.
3KP3 Installation Integrity
- A pilot programme of offshore inspections focused
on maintenance management and backlogs to inform
the main programme. This was undertaken between
October last year and March this year and is
complete. - A 3 year inspection programme focussed on key
integrity issues to commence second quarter 2004. - Joint supporting projects with external
stakeholders such as UKOOA - The sharing of our programme findings with all
stakeholders as promptly as possible
-
4Stan Cutts Specialist InspectorProcess
Integrity
- What are HSE Offshore Divisions current concerns
about offshore major hazards and what are we
doing about them ?
5KP3 Installation Integrity
- Working to common template
- Examination of records
- Check suitability of performance stds
- Interrogate backlog/overdue list
- Includes reactive work
- Standards of DH and contractors
- Includes physical testing of SCEs
6What do we mean by Integrity ?
- Integrity refers to the risk of failure
- of structure, plant, equipment or systems,
- which could either cause or contribute to
- a major accident and/or cause fatalities.
- It also includes structure, plant, equipment
- or systems that prevent or mitigate the
- effect of a major accident and/or fatalities.
7Integrity
Another way of putting it. Does it do
what it says on the tin ?
8Why Now ?
- Ageing Installations
- Industrys Commercially-Driven Changes
- Reduced Manning
- Reduced Maintenance/Inspection
- Deficiencies identified in KP1
- Specific Incidents e.g. Brent B
9KP3 Priority Areas
- Integrity of piping repairs
- Risk assessments and Hazops
- Awareness of personnel
- Valve failures
- Hydrocarbon containment
- ESDV issues
- Maintenance quality and backlog
- Lack of resources
- Competence
- Mitigation systems
- Corrosion
- (Ship collision)
10How ?
- Maintenance Policy/Strategy
- Enactment
- Predictive Analysis
- Number/Frequency of Breakdowns
- Performance Standards
- Backlog Justification
- Deferrals Process
- Traceability of SCE definition
-
- ICP Interface
- Verification System
- Replacement Parts
- Repair Techniques
- Role of TAs
- Supervision
- Competence
- Capacity for Human Error
- System Testing
11Weaknesses Observed on some installations
- Backlog
- Corrosion
- Maintenance Management System
- Beach Support
- Planning
- Supervision
- Performance Standards
- Physical Evidence
- SCE Performance
12Conclusions from KP3 Pilot
- Based on 11 inspections, sufficient evidence has
been gathered to justify the following
challenges - Is the maintenance function adequately resourced
? - Is the planning of SC maintenance efficient ?
- Is the quality of maintenance acceptable ?
- Is the performance of SCEs reliable ?
- Are inspection and audit standards optimal ?
- Is supervisory and engineering support solid ?
- HSE influence can help to remedy deficiencies in
these important areas
13KP3 Inspection Programme
- A number of fully developed KP3 inspections will
be undertaken between now and 31 March 2005. - Each inspection will be undertaken using a
template developed from the KP3/2 pilot and the
Belfry Workshop. - A multi-disciplinary team comprised of at least
one IMT inspector and two topic specialists will
carry out each inspection. - Each inspection will take at least two weeks, to
include an offshore inspection of at least 3 days
duration plus pre and post onshore components and
report preparation.
14Installation Integrity Relevant Law
- HSWA S2 general duty
- DCR R8 maintenance of integrity
- PUWER R4 suitability of work equipment
- R5 maintenance
- SCR R2 definition of SCE/verification
- PFEER R5 assessment
- R9 prevention fire/explosion
- R19 - suitability and condition of
plant - COSHH R9 maintenance, examination of control
- measures
- LOLER R9 thorough examination of lifting plant
15We consider it very important.
- That we explain to you what we are doing and why
- That KP3 is a joint and co-operative venture with
the duty holders - That the workforce are fully on board, and fully
informed