IRP in Vermont - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

IRP in Vermont

Description:

How do Distribution Utilities use VELCO ... Financial viability ... Viable financing plans are critical: Vt may add alternatives without regional cost support ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 14
Provided by: bruceb52
Category:
Tags: irp | vermont | viability

less

Transcript and Presenter's Notes

Title: IRP in Vermont


1
IRP in Vermont
  • Docket 7081
  • Workshop Sept. 13, 2005

2
IRP in VT
  • What are IRPs and How are they developed?
  • DUP How does it impact VELCOs Transmission
    Planning
  • How do Distribution Utilities use VELCO
    Transmission Planning?
  • Alternatives to Transmission Analysis and
    Selection

3
What are IRPs and How are they developed?
  • A plan for meeting electric energy needs over
    twenty years at lowest cost by combining
  • Power supply (central distributed)
  • Transmission and distribution
  • End-use efficiency
  • IRPs are developed separately by each utility
  • Power supply is company-wide
  • Transmission distribution is location specific
  • End-use efficiency affecting each utility

4
Legal Basis for IRP
  • Under 30 V.S.A. 218c. an IRP is a plan for
    meeting the publics need for energy services,
    after safety concerns are addressed, at the
    lowest present value life cycle cost, including
    environmental and economic costs, through a
    strategy combining investments and expenditures
    on energy supply, transmission and distribution
    capacity, transmission and distribution
    efficiency, and comprehensive energy efficiency
    programs.

5
Principal Criteria of Solution
  • Societal cost
  • Fuel
  • Capital (construction financing)
  • Environmental (Externalities)
  • Stability
  • Solution must be flexible
  • Robust across scenarios
  • Avoid rate shocks
  • Financial viability
  • Rates must maintain utilitys investment grade
    credit rating and access to capital markets

6
Scenario Development
7
Portfolio Development
8
Analysis of End-use Efficiency Potential
9
Ranking Portfolio Performance
10
TD Reliability Efficiency
  • Comprehensive multi-year study of TD system
    efficiencies
  • Prioritize all right-of-way clearing on areas
    with greatest need
  • Monitor delivery system reliability indices
  • Use line patrols and infrared scans to find and
    correct problems before they cause outages
  • Address capacity constraints consistent with DUP
    planning guidelines
  • Consider all feasible alternatives including
    joint facilities with neighboring utilities,
    on-site generation and DSM
  • Consider environmental impacts, societal costs
    and other public concerns
  • Work with VELCO in support of the Northwest
    Reliability Project

11
DUP How does it impact VELCOs Transmission
Planning
  • Southern Loop as an example
  • Local reliability issue post contingency with
    existing loads (CV DUP Docket 6805)
  • Regional reliability problems S. Vt/SW NH
  • RTEP S. Loop Monadnockpost-NRP
  • Potential local capacity needs (CV DUP Docket
    6805)
  • Future regional/state capacity needs (RTEP)
  • All will be examined in CVPS DUP Docket 6805

12
How do Distribution Utilities use VELCO
Transmission Planning?
  • DU Utility Planners work with VELCO continuously
    ( VUPG)
  • VELCO considers DU power supply plans
  • e.g.. 1987 VELCO Plan revised in 1992 after Phase
    I/II multi-terminal and NW VT cogen plans
    changed
  • Transmission projects and Power Supply interact
    for least-cost solution, e.g., Northern Loop/ VJO
    delivery

13
Alternatives to Transmission Analysis and
Selection
  • DUP analysis looks at least-cost societal NPV to
    compare solutions does not differentiate
    between public and private benefits/costs
  • Risk of complex implementation plans and
    reliability of long-run performance are factors
  • ISO-NE adopted transparent planning to allow
    entry by merchant G/T/DR providers
  • Viable financing plans are critical Vt may add
    alternatives without regional cost support