Application and Implementation of State Estimator at Idaho Power Company - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

Application and Implementation of State Estimator at Idaho Power Company

Description:

The Project addresses the NERC and WECC requirements for EMS ... Tie Line to JBRIG. ZBR. to MPSN. Capacitors. REACTOR. L342. 303D. 302Z. 305A. 306A. SCADA model ... – PowerPoint PPT presentation

Number of Views:95
Avg rating:3.0/5.0
Slides: 23
Provided by: mmp8
Category:

less

Transcript and Presenter's Notes

Title: Application and Implementation of State Estimator at Idaho Power Company


1
Application and Implementation of State Estimator
at Idaho Power Company
  • S. Kincic and M. Papic

2
Outline
  • Background
  • Overview of IPCO and its EMS System
  • IPC Experience with State Estimator
  • Modeling Issues
  • SE in Planning
  • Conclusions

3
1. Background
  • The EMS project has been initialized by Grid
    Operations and Planning following the
    recommendations of the US/Canada outage task
    force on the August 2003 blackout.
  • The Project addresses the NERC and WECC
    requirements for EMS functionality identified
    from the August 14th Blackout as well as improved
    coordination with additional Off-Line Planning
    Functions.

4
Background
NE Blackout TF Recommendations
  • Recommendation 22 Evaluate and adopt better
    real-time tools for operators and reliability
    coordinators
  • Recommendation 24 - Improve quality of system
    modeling data and data exchange practices
  • NERC should work with the regional reliability
    councils to establish regional power system
    models that enable the sharing of consistent and
    validated data among entities in the region.
    Power flow and transient stability simulations
    should be periodically benchmarked with actual
    system events to validate model data.

5
1. Background
  • Installation and complete modeling of the new EMS
    has been completed entirely by IPCO EMS team
  • Project completed in two phases
  • Phase I Implementation of SE and advanced
    applications (May 2005)
  • Phase II Cutover to the new SCADA (May 2007)
  • SE tuning has been accomplished throughout 2007

6
2. System Overview
Company
  • Covers 24.000 sq. miles
  • Peak 3300MW
  • Net importer of energy
  • 17 plants
  • Shared ownership of three coal fire plants
  • 4,600 miles of transmission lines
  • 18,000 miles of distribution lines

7
(No Transcript)
8
2. IPC System Model
  • Planning Model (bus-branch representation)
  • EMS/Dispatching Model (node-breaker
    representation)
  • Models Accuracy and Validation
  • Inter-Utility Data Exchange
  • The system representation at any given time
    includes the static data (network topology) and
    the system conditions (loads, interchanges,
    flows)
  • Wide System Model (WSM)

9
EMS System Configuration
  • Windows Based
  • One pair of servers for SCADA and Generation
    Application
  • One pair of servers for SE and Advanced
    Application
  • One pair of servers for ICCP data
  • One server for DTS
  • Two modeling Servers

10
EMS System IPC Data Exchange
IPC
PNSC
PAC
BPA
SPPC
EHVDP
CMRC
NWE
RDRC
PGE
PGE
11
3. State Estimator
  • Operates on PNSC model (North West WECC)
  • Model Includes
  • 8000 buses (1400 measured)
  • 5000 lines
  • 4000 substations
  • Receives about 15000 analogs and statuses

12
3. State Estimator
  • SE runs every 300 sec.
  • RTNET includes SE and RTCA
  • STNET includes PWRFLOW and CA
  • After every State Estimate , the base case is
    monitored for violations
  • Real Time CA runs every 300 sec.
  • Base Case used for STNET (outage schedule)

13
4. Modeling Issues
  • Planning model is used as a source of line and
  • transformers parameters- occasionally
  • conversion of p.u. in percentage omitted
  • SE uses breaker oriented model-terminals of every
  • device are attached to two or three nodes.
  • Assignment of device to incorrect node
    topology
  • error
  • Series capacitors composed of modules that can be
  • Inserted and bypassed separately (often non-seen
    on company one line). If represented as a single
    device- Significant power flow error

14
4. Modeling Issues
  • Breaker oriented model- over 30.000 breakers.
    Status of breakers required or topology error if
    breaker is in wrong position. Maintenance is
    required
  • Field changes have to be modeled- difficulty in
    obtaining new data
  • Mapping of the measurements into the model if the
    name change- composite key broken

15
  • Bus configurations
  • need attention

SCADA model
NETWORK model
16
  • Wrong direction of
  • measurements

breaker
100 MW
100 MW
56
57
100 MW
transformer
100 MW
100 MW
LV
HV
17
  • Load model

Load model-time dependant schedule for operating
area
Individual loads follow the same pattern
No load diversity
18
Detailed load model
19
5. Application of
SE in Planning
20
Translation of dispatching (breaker to breaker)
model into the planning model
21
6. Conclusion
  • Vendors provide operational structure
  • Utilities have to address modeling issues
  • The flow of measurement data among
  • utilities has to be established
  • Idaho Power Company has successfully
  • accomplished these tasks

22
What Next?
  • Continue working and improving IPCO model.
  • Developing a process of updating IPCO model with
    external transmission facilities.
  • Participating in the development of the WSM
  • Further Validating of SE, STNET and CA results
  • Implementing of Metrics for SE Evaluation ()
  • Integrating of PMU data into IPCO SE.
  • Start using POM to evaluate critical
    contingencies and develop a mitigation plan when
    the contingency occurs. ()
Write a Comment
User Comments (0)
About PowerShow.com