Summary of MINERnAs Impact on Fermilab - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

Summary of MINERnAs Impact on Fermilab

Description:

Report on the Mini-Review of the. Impact of MINERnA on Fermilab. Monday, March 29, 2004. A Fermilab internal mini-review was conducted on Monday March 29, 2004 to ... – PowerPoint PPT presentation

Number of Views:50
Avg rating:3.0/5.0
Slides: 11
Provided by: tri562
Learn more at: https://home.fnal.gov
Category:

less

Transcript and Presenter's Notes

Title: Summary of MINERnAs Impact on Fermilab


1
Summary of MINERnAs Impact on Fermilab
  • Jorge G. Morfín
  • Fermilab
  • Fermilab Directors Review
  • 10 January 2005

2
Report on the Mini-Review of theImpact of
MINERnA on Fermilab.Monday, March 29, 2004
A Fermilab internal mini-review was conducted on
Monday March 29, 2004 to assess the issues and
impact of approval of the MINERvA experiment on
Fermilab and on the MINOS experiment. The
committee Mike Crisler (chair), Kurt Krempetz,
Qizhong Li, Bill Louis, Doug Moehs, Rich Stanek
PAC Observers Jim Alexander, Jim Brau, Heidi
Schellman Presentations Summary of Physics
Goals - Jorge Morfin Detailed Description of
Detector - Kevin McFarland Impact on the MINOS
experiment - Stan Wojcicki The MINOS near
detector hall - what is there, what does MINOS
need - Dave Pushka What does MINERvA need?
Impact on Fermilab - Peter Shanahan
3
Summary from Impact Review Committee
  • 1 The committee did not identify any unusual
    safety issues.
  • 2. The sense of the committee is that the Minerva
    collaboration has provided a fairly complete
    analysis of the resources they will require from
    Fermilab, but some omissions were noted. We would
    estimate that when the analysis is more fully
    refined, that the base cost to Fermilab will
    likely increase by of order 40, and that a
    contingency of 40 would be appropriate. The
    proposed schedule is somewhat tight, which may
    lead to less than 4 years of running.
  • 3. The sense of the committee is that the MINOS
    experiment will likely benefit from the
    information provided by Minerva, and that we do
    not anticipate any significant negative impact
    from either the installation or running of
    Minerva on the operation of MINOS. Minerva
    intends to run parasitically to MINOS and make no
    independent beam requests. It is likely that
    interactions in the Minerva apparatus will
    contribute a few percent additional deadtime to
    the MINOS near detector.

4
Summary from Impact Review Committee - continued
4. There is an issue with the availability of
cooling in the MINOS cavern. The preliminary
Minerva estimates assumed the nominal estimated
rates of water flow into the cavern. Recent
measurements have shown that the actual flow rate
is 240 gpm instead of the expected 300 gpm. This
new information was not available to Minerva
during their preparations for this review. The
sense of the committee is this is not a major
issue, but it will necessitate the additional
cost of larger heat exchangers.
5
Summary of Current RequestsDesign Tasks
6
Fabrication Tasks
7
Installation Tasks and Sum Request
2278
911
3189
8
New Fermilab Impact Items
9
Have we double-counted?
Summary Point 2. The sense of the committee is
that the Minerva collaboration has provided a
fairly complete analysis of the resources they
will require from Fermilab, but some omissions
were noted. We would estimate that when the
analysis is more fully refined, that the base
cost to Fermilab will likely increase by of order
40, and that a contingency of 40 would be
appropriate. The proposed schedule is somewhat
tight, which may lead to less than 4 years of
running. By adding 40 to our original
(MINOS-cost based estimates) to cover omissions
and then adding new impact items on top of that,
are we double counting? If we take our original
estimates (before applying the factor of 1.4) and
adding the new requests we have Sum total
before contingency 1857 K
contingency 742 K Sum total 2599
K compared to 3189 K
10
Total MINERnA Impact on Fermilab
Task MS SWF Cont. Total Design
0K 746 298 1044 Fabrication 252 743 39
8 1394 Installation 21 516 215
751 TOTAL 273 2005 911 3189 Total w/o
factor 1.4 265 1592 742 2599
Write a Comment
User Comments (0)
About PowerShow.com