The Effects of Uncertainty on Quantified Risk Assessment for LNG Facilities - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

The Effects of Uncertainty on Quantified Risk Assessment for LNG Facilities

Description:

Heat transfer from the sea to a spreading LNG pool for one size of ship spill ... Size of Release. Maximum consequence distances change significantly ... – PowerPoint PPT presentation

Number of Views:109
Avg rating:3.0/5.0
Slides: 30
Provided by: clea8
Category:

less

Transcript and Presenter's Notes

Title: The Effects of Uncertainty on Quantified Risk Assessment for LNG Facilities


1
The Effects of Uncertainty on Quantified Risk
Assessment for LNG Facilities
  • CCPS Meeting
  • 24-26 April, 2006

2
Contents
  • Introduction
  • Worked example
  • Sensitivity studies
  • Concluding comments

3
Introduction
  • Canvey LNG Terminal public inquiry (1982)
  • SRD assessment
  • British Gas assessment
  • Used same approach
  • Agreed on list of scenarios
  • Estimate frequency and consequences of each
    scenario

4
Introduction
  • Conclusions
  • Differences of factor of 2 arise through use of
    different consequence models
  • Potentially bigger differences in failure
    frequencies
  • Large spills dominate risk to society
  • Note Much subsequent work has assessed
    consequences not frequencies

5
Introduction
  • So what would happen if we repeated the exercise
    now?
  • What really matters in deciding individual and
    societal risk
  • On-site?
  • Off-site?

6
Worked Example
7
Worked Example
  • Select scenarios for import terminal
  • LNG jetty area
  • LNG import pipe work
  • LNG storage area
  • LNG export pipe work
  • Process area
  • Natural Gas export area

8
Worked Example
  • Add a realistic nearby population
  • Loughborough, England

LNG Terminal
9
Worked Example
  • Use generic failure frequencies
  • Use lengths of large diameter pipe work on site
  • Assume size of LNG tanks and transfer lines, size
    of ships
  • Implies frequency of ship visits
  • Use ACDS/BP model for ship failure frequency
  • Use proprietary data to infer jetty release
    frequency

10
Worked Example
  • Evaluate Consequences of Release
  • Assume wind rose
  • Perform calculations typically for 5 wind speeds,
    12 wind directions
  • Use different inventory in tanks
  • Assume different release directions
  • Differentiate between times when ships are
    present and not present
  • Differentiate between indoor/outdoor and
    day/night (population distribution)

11
Worked Example
  • Combine frequency of event and consequences to
    determine
  • Individual Risk
  • Societal Risk

12
Worked Example
  • Contours of location specific risk (LSR) from all
    scenarios and realizations
  • People are present 100 of the time and are
    located outside.

13
Worked Example
  • Societal Risks
  • F-N curves for each scenario
  • Sum over all scenarios

14
Sensitivity Studies
  • Examine uncertainty arising from LNG behaviour
  • Dense gas behaviour
  • Boil-off rate
  • Burning rate
  • Explosions
  • Examine sensitivity to event behaviour
  • Size of hole created by initiating event
  • Immediate vs. delayed ignition
  • Duration of release and mitigation
  • Escalation from smaller releases

15
Sensitivity - Dense Gas
  • LNG dispersion - dense in near field
  • What about further out
  • Heat transfer from surface
  • Humidity

16
Sensitivity Dense Gas
  • Failure of LNG export pipeline
  • 5 m/sec and D atmospheric conditions
  • Sensitivity to
  • Heat transfer modelling
  • Humidity

Dispersion
Case
Distance Relative
to Base Case
Base Case
1.00
No heat transfer
1.26
No heat transfer, low
1.38
absolute humidity
17
Sensitivity Boil-off Rate
  • Heat transfer from the sea to a spreading LNG
    pool for one size of ship spill
  • 50 kW/m2 used for analysis
  • 25 and 100 kW/m2 cases examined

18
Sensitivity Boil-off Rate
Figure 6 from paper
  • Not too sensitive
  • Bigger cloud for shorter time vs. smaller cloud
    for longer
  • Middle case is marginally worse

19
Sensitivity Pool Fires
  • Mass burning rate for pools
  • Back radiation from flame
  • Heat from underlying surface
  • On land
  • Up to 0.14 kg/m2/s has been measured
  • On sea
  • Heat flux from surface could enhance land value
  • Could be approximately double

20
Sensitivity Pool Fires
  • Single LNG storage tank release case
  • Bigger fire for less time vs. smaller fire for
    longer time
  • Low mass burning rate gave slightly higher
    societal risks

LSR Contours
21
Sensitivity - Explosions
  • Studies suggest LNG vapour clouds dont detonate
  • Produce less risk than equivalent sized LPG cloud
  • Less congestion present at LNG import terminal
    compared to an LNG export terminal
  • Warning at liquefaction facilities
  • Refrigerant Storage
  • Large inventories of volatile materials in
    process
  • Release in the congested process area can lead to
    potentially significant consequences

22
Sensitivity LNG Behavior
  • Conclude
  • Effect on risk for a large spill may be
    counter-intuitive
  • Cant prejudge outcome by guessing what is worst
    case for risk
  • Location specific risk may be very sensitive to
    assumptions
  • Societal risk less so

23
Sensitivity Event Behaviour
  • Issues
  • Size of hole created by initiating event
  • Immediate vs. delayed ignition
  • Duration of release and mitigation
  • Escalation from smaller releases
  • These are the parts of the event tree that are
    uncertain

24
Size of Release
  • Large ship spill
  • Sensitivity of risk to assumed size of release
  • One tank 1m2 hole
  • One tank 6m2 hole
  • All tanks 6m2 hole

25
Size of Release
  • Maximum consequence distances change
    significantly
  • Reflected in vulnerability of people to event -
    if it happens

26
Size of Release
  • . but ACDS suggests 9091 ratio of failure
    sizes
  • And catastrophic releases more likely to ignite
    immediately (?)
  • So effect on catastrophic risk is less than might
    be thought
  • Depends on weighting of N, contribution to PLL
    changes to 49, 36 and 15 respectively, when N2
    is applied

27
Duration of Release
  • Spill at Jetty, with 5 sec (small) and 90 sec
    (medium) releases for one loading arm and total
    transfer rate (large) release
  • Assume similar 9091 split of smallmediumlarge
  • In this case, small releases contribute most to
    expected loss of life

Figure 1 from paper
28
Sensitivity Event Behaviour
  • Conclude different ways the event behaves can
    make a big difference
  • Need to consider whole of event tree before
    deciding on what is dominant contributor

29
Concluding Comments
  • Have we moved forward in 20 years?
  • Yes, but
  • Important to concentrate on
  • Events that cause biggest risk
  • Factors that can change this risk
  • Not always obvious what impact changes have
    event frequency has linear impact on risk whereas
    modeling parameters may produce less than linear
    changes
  • Need to consider causes and effects in holistic
    way
  • E.g. Release cause and ignition probability
Write a Comment
User Comments (0)
About PowerShow.com