Title: OverPressure Events at the Idaho National Engineering and Environmental Laboratory
1 Over-Pressure Events at the Idaho National
Engineering and Environmental Laboratory
- James Wolski
- Department of Energy - Idaho Operations Office
May 13, 2003
2Idaho National Engineering and Environmental
Laboratory Site
Glass flask rupture due to failed
pressure regulator gauge Airline
rupture during dosimetry badge check
Rupture of laboratory gas drying units
Personnel injury resulting from failed
high-pressure fitting
3GLASS FLASK RUPTURES DUE TO FAILED PRESSURE
REGULATOR GAUGE
4GLASS FLASK RUPTURES DUE TO FAILED PRESSURE
REGULATOR GAUGE
- Background
- Event occurred at the Idaho Nuclear Technology
and Engineering Center (INTEC) - The activity in progress was to conduct a bubble
leak test on a portable sample station - The function of the sample station was to sample
and purge underground spent nuclear fuel storage
vaults - The glass flask shattered sending shards over
roughly a ten foot radius
5GLASS FLASK RUPTURES DUE TO FAILED PRESSURE
REGULATOR GAUGE
- The sample station structural capability pressure
had never been determined - Bubble leak test was to be performed at 12 psi
- Rubber stopper on top of the glass flask came out
during the test. Zip ties were used to hold the
rubber stopper, but did not hold. A hose clamp
was used to hold the rubber stopper - An unusual whistling sound was noted coming out
of the HEPA filter, but the test continued - The glass flask shattered very shortly after
passing the bubble leak test
6GLASS FLASK RUPTURES DUE TO FAILED PRESSURE
REGULATOR GAUGE
- After the flask shattered, the system was
modified to install a calibrated pressure
indicator. -
- The regulator was used to pressurize the system.
The regulator pressure gauge read 12 psi the
calibrated gauge read 28 psi. -
- The pressure regulator pressure gauge was tested.
The gauge read 10 psi with the test system
pressure reading up to 100 psi. -
- Use of the glass flask in a pressurized system
was not recommended by the flask manufacture.
7GLASS FLASK RUPTURES DUE TO FAILED PRESSURE
REGULATOR GAUGE
- No pressure relief protection was
provided. -
- No calibrated pressure indicator gauge was
installed during the bubble leak testing. -
- No maintenance inspection criteria or
pre-operational check was provided for compressed
gas regulators -
- Company polices and procedures did not
adequately implement appropriate compressed gas
standards -
8GLASS FLASK RUPTURES DUE TO FAILED PRESSURE
REGULATOR GAUGE
- Problems that contributed to the glass flask
rupture - Personnel directing and performing work
did not follow approved work control process - Workers failed to stop work when
activities went beyond scope of work request - Workers continued to troubleshoot the
cause and did not preserve the scene - The nitrogen regulator was tested and
found to be defective causing over pressurization
of the sample station - Calibrated gauge was not used to ensure
correct system pressure was achieved
9- AIR LINE RUPTURE DURING
-
- DOSIMETRY BADGE CHECK
10AIR LINE RUPTURE DURING DOSIMETRY BADGE CHECK
- Background
-
- Radiological and Environmental Laboratory
at Central Facilities Area -
- Air Operated Thermoluminescent Dosimeter
Badge opening device -
- System is operated with nitrogen pressure
at 85 psig -
- The pressurized tubing expanded and broke
at normal operating pressure. One employee was
treated for noise exposure
11AIR LINE RUPTURE DURING DOSIMETRY BADGE CHECK
- Badge opening station was relocated
- Modifications were needed to the existing
airline system - An under rated piece of ¼-inch tygon
tubing was used, the tygon tubing was rated for
60 pounds per square inch - The piece of tubing was selected based on
the available length, rather than evaluating the
pressure specifications of the tubing - A formal stop work was put in place
pending a review of the incident
12AIR LINE RUPTURE DURING DOSIMETRY BADGE CHECK
- Problems that contributed to the air line rupture
- There was no configuration management
system in place for this system - The employee did not use known pressure
specifications to select the tubing used for the
badge opening station - The piece of tubing was selected based on
available length, rather than evaluating the
pressure specifications of the tubing
13- RUPTURE OF LABORATORY GAS
-
- DRYING UNITS
14RUPTURE OF LABORATORY GAS DRYING UNITS
- The INEEL Research Center (IRC) is an R
D Laboratory Facility for the Idaho National
Engineering and Environmental Laboratory -
- A researcher was switching an experiment
in the laboratory from nitrogen to compressed air -
- A system was established that used a new
gas cylinder, a new pressure regulator and
existing laboratory gas drying units -
- After pressure was applied to the system,
the drying units ruptured -
- Fragments, contents and parts from the
drying units scattered throughout the laboratory.
Three workers were injured
15RUPTURE OF LABORATORY GAS DRYING UNITS
- The system manual required a two-stage
medium duty regulator, with a designed delivery
range of 4-80 psig - The laboratory gas dryer units had a
maximum working pressure of 90 psig -
- The researcher selected a regulator that
he believed was appropriate for the application
from a regulator storage drawer -
- He thought he had a two-stage regulator
with a 0-300 psig delivery pressure gauge
16RUPTURE OF LABORATORY GAS DRYING UNITS
- He actually had a 0-300 bar or 0-4000 psi single
stage regulator with a designed delivery range of
50-2500 psig, at high flow rates - The cylinder valve was opened and there was no
supply pressure gauge indication -
- The regulator T-handle was loosened and removed,
later reinserted until some resistance was felt -
- The cylinder valve was opened, the system
pressurized and the drying units ruptured
17RUPTURE OF LABORATORY GAS DRYING UNITS
- Problems that resulted in the rupture of the
drying units -
- Improper regulator with defective supply
pressure gauge was selected for the work to be
performed -
- Inappropriate adjustment of the regulator
left at an unknown preset delivery pressure -
- Compressed gas training courses did not
contain sufficient information on hazards,
lessons learned, relief valves, selection of
regulators, maximum operating pressure and burst
pressure -
- The researcher was not familiar with the
vendor manual or the appropriate procedure
18PERSONNEL INJURY RESULTING FROM FAILED HIGH
PRESSURE FITTING
19Personnel Injury Resulting From Failed High
Pressure Fitting
- An In Situ Grouting Treatability study was in
progress at the Cold Test Pit South of the
Radioactive Waste Management Complex (RWMC). The
work was in a pit with buried simulated waste
material. - Activities taking place involved drilling and
grouting of a series of holes in the Cold Test
Pit. - A Worker was struck in the right temple area by
metal from a ruptured high-pressure fitting.
There was a Type B accident investigation
20Personnel Injury Resulting From Failed High
Pressure Fitting
- The high pressure pumping station consists of a
positive displacement pump that was powered by a
diesel engine through a gearbox and clutch. -
- The pumping station experienced problems with
plugging. -
- A manual pressure relief on the pump was used to
relieve pressure after the pump was secured. -
- The pump included an automatic pressure safety
shutdown. The recommended setpoint was 290-435
psi above operating pressure. The safety
shutdown was set at 8700 psi. -
- No overpressure prevention device was provided
downstream of the pump.
21Personnel Injury Resulting From Failed High
Pressure Fitting
- The 45o swivel elbow that was replaced in the
high-pressure grout line was designed in
accordance with the SAE-J514 standard with a
working pressure rating of 2500 psi -
- Normal system pressure was about 6000 psi
-
- While using the grouting system, pressure
was raised to establish flow. A fitting
connecting the high pressure pump to a
pressure/flow sensor failed, striking a
subcontractor worker -
- The subcontractor did not communicate similar
high-pressure failure of this system to MO
contractor.
22Personnel Injury Resulting From Failed High
Pressure Fitting
- Subcontractor process for the high-pressure
grout system was inadequate. Parts were
purchased and installed that did not meet system
design. -
- MO contractor oversight of operations,
maintenance and configuration management was
inadequate. -
- Subcontractor did not follow and MO
contractor did not adequately enforce the
subcontract requirements. -
- DOE oversight of the project was inadequate
23- Path forward
- INEEL Pressure Systems Task Team was established
- Developed a checklist for compressed gas
assemblies to identify safety vulnerabilities - Evaluated applicable systems, identified
deficiencies, corrected deficiencies or took
systems out of service - Reviewed regulatory requirements, performed gap
analysis - Reviewed human performance contributing causes
and error precursors - Team proposed corrective actions, plan for
site-wide implementation of immediate corrective
actions until corrective actions are implemented