Title: Using Earned Value Project Management at the Washington State Department of Transportation
1Using Earned Value Project Management at the
Washington State Department of Transportation
Rick Smith Project Control and Reporting Urban
Corridors Office
Douglas B. MacDonald Secretary of Transportation
Paula Hammond Chief of Staff
John Conrad Assistant Secretary
AASHTO Standing Committee on Quality May 24,
2007
2WSDOTs Highway Construction Program2005 2015
(Millions)
3WSDOT Expenditure Plan
2003 State Nickel Gas Tax Increase 2005
Transportation Partnership Act 9.5 cents Nov
2005 Initiative-912 Voters retained TPA tax
4Line Item Appropriations
- For every one of these projects, WSDOT is
required to deliver - Scope as originally submitted
- Budget as appropriated
- Schedule as required by legislature
- Each phase itemized in legislative budget
- Significant changes need Governors Office or
Legislative approval
5Project Delivery Trends
6Project Delivery Trends
7Project Delivery Trends
8(No Transcript)
9(No Transcript)
10(No Transcript)
11(No Transcript)
12Urgent Need - Project Management Skills and Tools
- Massive amounts of funding
- Tight (impossible?) requirements
- Difficulties in recruitment and retention
- Sharply increasing construction costs
13How are you being measured?
- Did you spend the money as expected?
- or
- Did you get the results you wanted?
- or
- Did you get it done on time?
14Earned Value Concept in a Nutshell
- Answers the question
- Did we get what we planned, for the amount of
money we planned to spend, and did we get it when
we needed it?
But even more important How will our
performance be at the finish line?
15Earned Value Compares
- The amount of work that was planned
- with
- What was actually accomplished
- with
- What was actually spent
- To determine if the project is performing as
planned
16History of Earned Value Management (EVM)
- Originated in 1967 for Public Sector
- DoD implemented for new projects C/SCSC
- Modern day earned value came from industrial
engineering - 1995 C/SCSC redeveloped to be more user friendly
- 1998 ANSI 748 Guide Issued
17Results of Using Earned Value Management
- Early warning of project issues
- Ability to resolve issues proactively
- Visibility of changes and their potential impacts
- A tool that provides a three dimensional view of
the project
18Example - Mowing My Lawn
- Contract to mow lawn for 10
- Scheduled to take one hour
- Pay by the minute
- (10/60minutes 16.7 cents per minute)
- 45 minutes, half complete, stops
- Planned value is 7.50 (should be 75)
- Actual is only 50 complete (5.00)
- Earned value 5.00
19Ahead of or Behind Schedule?
- Planned Value 7.50
- Earned Value 5.00
- Schedule Performance Index (SPI) EV/PV
5.00/7.50 0.67 - Less than 1 behind schedule
- More than 1 ahead of schedule
20Over Budget?
- Actual Cost 7.50
- Earned Value 5.00
- Cost Performance Index (CPI) EV/Actual
5.00/7.50 0.67 - Less than 1 over budget
- More than 1 under budget
21Added Costs
- Actual Cost 7.50
- Buy a tourniquet - 2.50, total 10.00
- Earned Value 5.00
- Cost Performance Index (CPI) EV/Actual
5.00/10.00 0.5 - Less than 1 over budget
- More than 1 under budget
22In Order to Utilize Earned Value
YOU MUST HAVE A PLAN
23Work Breakdown Structure
- Defines the team mission
- A deliverable - oriented grouping of project
elements that organize and define the total scope
of the project - How far do you break down a task?
- To a level that makes sense for the project
- Generally to a single point of responsibility for
delivery
24Task Planning
- Scope of work for each task
- Resources required
- Time (start with the optimal or desired duration
for each task) - Task Lead determined
25Task Sequencing
- Conduct team strategic planning session
- Analyze best sequence for project tasks
- Establish task dependencies
- Powerful use of Post It technique
- Once all tasks are laid out, they can be placed
into scheduling software of choice
26Estimating Task Costs
- When estimating task duration resources needed
and resource availability should be considered - If specific resources are unknown, use generic
resources, e.g. job classification. - Dont forget indirect costs such as
administrative costs - Goal is to develop optimal budget at the
deliverable level - Determines Budget at Completion (BAC) bottom up
verification
27Bust and Adjust
- Once the duration, task sequences and costs have
been entered into the scheduling software.and
the end result is calculated. - This confirms the budget and schedule established
by the legislature - If the bottom up plan varies, then modify
durations, logic or cost estimates - This provides early indication of potential
problem areas
28Earned Value
Now that you have a plan . . .
29Tracking Progress
How does the projects actual performance
compare to the plan?
30EVM Requires 3 Values
- Planned Value (PV)
- Actual Costs (AC )
- Earned Value (EV)
31Planned Value
- The budgeted costs of the work scheduled
- The projects time-phased budget
- Can only change when baseline is changed
32Planned Value
Planned Value
Time Phased Budget Based on Schedule
33Actual Costs
- The actual costs of the work completed during the
month or reporting period - Actual costs by work code
- Requires accurate charging of staff time to
appropriate control account
34Earned Value
- The projects physical progress
- Progress reported in baseline or planned dollars
- Represents sum of completion for each task or
deliverable
35Cost Variance (CV)
- Difference between the earned value (EV)
achieved (physical progress) and the actual cost
(AC) incurred for performing the Work - EV - AC
- Good News Positive Number means youre under
spending for the work accomplished - Bad News Negative Number means youre over
spending for the work accomplished - REQUIRES PM ATTENTION
36Schedule Variance (SV)
- Difference between the earned value (EV)
achieved (physical progress) and the planned
value (PV) work scheduled for the reporting
period - EV - PV
- Good News Positive Number means youre ahead of
schedule - Bad News Negative Number means youre behind
schedule - REQUIRES PM ATTENTION
37Cost Performance Index (CPI)
The cost efficiency factor representing the
relationship between actual costs expended and
the value of the physical work performed CPI
EV / AC Good News A number greater than 1 means
that your spending is less than planned for the
work accomplished Bad News A number less than 1
means that your spending is more than planned for
the work accomplished REQUIRES PM ATTENTION
38Schedule Performance Index (SPI)
The schedule efficiency factor representing
the relationship between the value of the
baseline schedule and the value of the physical
work performed SPI EV / PV Good News A
number greater than 1 means that your work
accomplished (performance) is ahead of
schedule Bad News A number less than 1 means
that your work accomplished (performance) is
behind the schedule REQUIRES PM ATTENTION
39Compare Actual Performance with the Baseline Plan
Legend Planned Value Earned Value Actual Costs
Wk 1 Negative Cost Variance (EV-AC) Wk 1
Negative Schedule Variance (EV-PV)
40Compare Actual Performance with the Baseline Plan
Wk 2 Management Attention Corrective Action
Legend Planned Value Earned Value Actual Costs
41Compare Actual Performance with the Baseline Plan
Wk 5 Positive Cost Variance (EV-AC) Wk 5
Positive Schedule Variance (EV-PV)
Legend Planned Value Earned Value Actual Costs
EARLY MANAGEMENT ATTENTION
42EVM Early Attention to Issues Avoids this
Problem
BIG VARIANCE AT COMPLETION
43Tracking the CPI SPI
Early Management Attention can result in
improvement
10/06 11/06 12/06 01/07 02/07 03/07
44Predictive Measures
- Statistically Determine Estimate At Completion
(EAC) - Determine Threshold Values to Trigger Corrective
Action - Evaluate Risk Management Process Effectiveness
45Estimate at Completion (EAC)
- Three Methods Utilized for Calculating
- Method 1 AC ETC
- Method 2 AC BAC EV
- Method 3 AC (BAC-EV)/cum CPI
46EAC Method 1
- AC ETC
- Actual Costs Estimate to Complete
- Used when the original estimate assumptions were
fundamentally flawed or no longer relevant due
to a change in conditions - Requires PM to perform bottom up evaluation of
Estimate to Complete
47EAC Method 2
- AC BAC EV
- Actual Costs Budget at Completion Earned
Value - Used when current variances are seen as
atypical and the expectation is that similar
variances will not occur in the future
48EAC Method 3
- AC (BAC EV)/ cum CPI
- Actual Costs (Budget at Completion Earned
Value)/ cumulative Cost Performance Index - Used when current variances are seen as typical
of future variances - Most respected, since cumulative variances are
indicative of future variances
49What does the cumulative Cost Performance Index
(CPI) tell you?
- If your project is more than 20 complete, the
CPI stabilizes. In other words, if you are
overrunning at 20, you will be overrunning at
completion.
- Furthermore, the overrun at completion will be
greater than the overrun to date! - Source research on 700 DOD contracts
50Establish Earnings Rules
- To Standardize Performance Measures
- To Minimize Subjectivity
51Earning Rules Construction Example
Units Produced Method A ratio of units produced
to the total specified at completion. Units must
be nearly identical.
Examples Drilling 10 holes, 4 complete 40
complete
Paving 5 miles, completed 4 miles 80 complete
52Earning Rules Design Example
Interim Earnings Gates Method Establish the
percent of the total that is to be represented by
each deliverable. Analogous to yard markers can
not achieve a first down until deliverable is
completed.
30 - - - 60 - - - 90 - 100
everything completed
preliminary products
first review complete
draft final
53Earning Rules Permitting Example
Environmental Permits Example Environmental
Specialty Office can claim progress for work to
obtain permit up to 75 complete. Gate at
75. 100 complete can be claimed when permit is
delivered to PEO.
0 - - - - 75 - - - - 100
permit docs completed submitted
started work
permit received and forwarded to PEO
54EVM Lessons Learned
- Education and buy-in are crucial
- Executives
- Project Managers
- Staff
- Find the right owner
- Project Manager
- Program Manager
- Business Manager
55EVM Lessons Learned
- Plan the work carefully and accurately
- All parties buy in to the WBS
- WBS composed of measurable, deliverable pieces
- Honest earnings plan is critical
- Assess variances early
- ..Highest Potential for Cost / Schedule
Recovery..
56EVM Lessons Learned
- Make sure the bad news is heard
- Take corrective action
- Staff changes?
- Mid-term evaluation of work
- Re-plan as necessary
- Budget increase?
- Scope change?
- Schedule change?
57EVM Limitations
- EVM requires thorough and accurate planning of
cost and schedule to be effective. - Future performance is being forecast based on
past performance (so if your data are bad, so is
your forecast) -
- EVM is designed to ensure that the future
predicted by EVM does not materialize as it
encourages corrective action
58References
- Earned Value Project Management, Quentin W.
Fleming and Joel M. Koppelman, 3rd Edition, 2005 - Practice Standard for Earned Value Management,
Project Management Institute (PMI), 2005 - Project Management Toolbox, Dragan Z. Milosevic,
2003 - Fundamentals of Project Performance Measurement,
Robert R. Kemp, 2000 - Project Management Using Earned Value, Humphreys
and Associates Inc., 2002 - Earned Value Management, APM Guideline for the
UK, Association for Project Management, 2002 - E.V.A. for the UK, 6 th Edition, ( Earned Value
Analysis, A Real Guide to Cost and schedule
Control), Steve Wake, 2003 - Practical Project Management, Harvey A. Levine,
20002