First DRAFT Report on Management - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

First DRAFT Report on Management

Description:

... such as system engineering, telescope/optical systems, pointing control systems, ... with industry to achieve major advances in x-ray telescope fabrication. ... – PowerPoint PPT presentation

Number of Views:64
Avg rating:3.0/5.0
Slides: 18
Provided by: yale5
Category:

less

Transcript and Presenter's Notes

Title: First DRAFT Report on Management


1
First DRAFT Report on Management
  • Mission Management
  • The SDT has expended a considerable effort on
    addressing various management issues relevant to
    the JDEM mission. The organization chart
    suggested in the White Paper of September 24,
    2003 has been modified and this modified version
    is shown in Figure 1.
  • Note to SDT
  • In the Interim Report of NASA Roadmap 8 a class
    of missions is discussed, namely the Universe
    Probes, which address focused science questions
    through moderate sized (300M-600M) missions
    that are fully competed and scientist led. JDEM
    is mentioned as a first priority item in this
    category if it fits within the cost cap. Is this
    for real, and if so, does it change our
    recommendation here about a Project Manager-led
    mission?

2
(No Transcript)
3
(No Transcript)
4
(No Transcript)
5
  • 7.1 The first issue that was extensively
    discussed was whether JDEM should be a PI
    (Principal Investigator)-led mission or a PM
    (Project Manager)-mission led by a NASA Project
    Manager. In the former case, the PI is
    responsible to DOE and NASA for both the
    development of the mission and the scientific
    investigation, whereas in the latter the PM is
    responsible to both NASA and DOE for the mission
    development, but the PI is still responsible to
    NASA and DOE for the scientific investigation.
    Some of the considerations are the following
  • The scientific motivation for the JDEM is a
    highly focused, targeted investigation into the
    nature of dark energy. As a cost-capped competed
    mission the proposing team will need to
    incorporate sound scientific, technical, and
    management solutions as part of a successful
    proposal. As such, its cultural and
    implementation aspects resemble those of a PI-led
    mission in many significant ways. The SDT
    recognizes that the scope of the mission and its
    probable cost may present organizational and
    management challenges that may exceed those that
    can be reasonably expected from vesting line
    authority in a single PI. A successful approach
    will need to address this concern by employing to
    the greatest extent possible professional space
    project management.

6
  • A balance will need to be struck that ensures
    the successful scientific return while providing
    both to the PI and the agencies an effectively
    managed construction project. The challenge is
    to do deliver a program on cost and schedule
    while not undermining the future of an equally
    challenging scientific mission. So, while the
    size and scope of JDEM may exceed the resources
    of a typical PI institution, the proposed
    solution must ensure the close marriage of
    project and scientific management and ensure the
    success of both the project manager and the PI.
  • The organization of the project into a PM-led
    mission mode solves the management problem by
    applying professional space project development
    expertise. This management mode is normally
    applied when construction and operation of a
    multi-purpose space facility needs to balance
    project resources among several simultaneous
    scientific goals (e.g., missions involving
    multiple instruments and investigations, or those
    supporting major general observer phases).
    Although this approach ensures the mission
    development will be led by a person with
    extensive space-project experience, the
    separation of responsibilities between the
    Project Manager and Principal Investigator
    creates the new risk that the PI team will be not
    as effective in optimizing the mission for the
    focused JDEM scientific goals. Given the
    scientific challenge of the mission the
    traditional PM-led structure is likely not
    adequate to ensure overall mission success.

7
  • 7.2 As an example of neither traditional PI nor
    PM led missions, the proposed organization chart
    for line authority in Figure 1 addresses the
    management and scientific concerns at the highest
    levels by making the PI and Project Scientist
    co-chairs of the Scientific Coordination Group.
    We expect that competed missions will propose
    variations on this potential solution in
    accordance with their capabilities and may
    propose variants on either PI or PM led
    investigations in order to accomplish the goals
    of a cost-capped scientific mission. This
    example organization emphasizes that the
    scientific goals of the Dark Energy Investigation
    and the project are one and the same.
  • This culture needs to be instilled into all
    elements of the project, a task that is not
    reasonably nor effectively accomplished through a
    single Project Scientist or PI. To help ensure
    that the scientific requirements of the mission
    are understood and correctly implemented at all
    levels, the Dark Energy Investigation team shall
    provide discipline scientists who will be
    integrated with the various technical disciplines
    within the project. This would include
    mission-level disciplines such as system
    engineering, telescope/optical systems, pointing
    control systems, contamination control,
    electrical systems, software systems, integration
    and test planning and execution, scientific
    performance verification, and ground systems.
    These responsibilities shall be in addition to
    those that are normally involved in developing
    the core JDEM scientific instrument, the
    primary responsibility of the Dark Energy
    Investigation PI-led team. It would be highly
    desirable for such staff to be co-located with
    the Project, at least during critical development
    phases involving the discipline. While such
    staff would be provided by an ultimately report
    to the PI of the Dark Energy Investigation, close
    coordination with the Project Scientist and the
    Project Scientist Office will be necessary,
    especially during co-located activities. The
    proposing Dark Energy Investigation teams shall
    be evaluated on the quality and organization of
    staff available to perform these functions.

8
  • 7.3 There should be a Joint NASA-DOE Review Team
    that reports to the NASA-DOE Joint Oversight
    Group (box in top left of Organization Chart)
    rather than having two separate review processes,
    one reporting to NASA and the other to DOE. A
    single review process is much more efficient,
    less wear and tear on the collaboration, and
    ensures better coordination and feeling of shared
    overall responsibility by the agencies. An
    argument was advanced that a joint review team
    did not work well for GLAST. We believe that we
    should not take this as a guide. GLAST was
    primarily a NASA project with a 10-ish DOE
    contribution. The coordination was not fully
    shared by the two agencies. We hope that JDEM,
    as the name implies, will be more realistically a
    JOINT mission with shared oversight
    responsibility. In this case a Joint Review Team
    reporting to the Joint Oversight Group is not
    only appropriate but might be instrumental in the
    joint management responsibility becoming a
    reality. The Joint Oversight Group can then
    report to the individual agencies as appropriate.

9
  • 7.4 The Spacecraft, Launch, Mission Operations,
    Engineering, Administrative Support (budget), QA,
    and System Integration belong naturally under the
    Mission Project Manager. Eventually more boxes
    may appear, or they might be arranged
    differently. We believe that this is a detail at
    this time and in cost-capped competed missions
    different organizational solutions may be used to
    control cost.
  • 7.5 The NASA/DOE White Paper of September 25,
    2003 initiating the JDEM mission has suggested
    that the Dark Energy Investigation that is the
    focus of this mission be a PI-led investigation.
    The SDT believes that this is appropriate given
    the focused scientific goals of this mission. We
    recommend that the Dark Energy Investigation PI
    have line responsibility over the Science
    Collaboration, the Science Instrument Payload,
    the Telescope, and the Science Operations.

10
  • The development of the science instrument for an
    astronomical space mission is usually the
    responsibility of the PI-team, in order to foster
    optimization of the instrument for the proposed
    scientific investigation. In the case of JDEM,
    particularly if as expected there is only one
    instrument, the OTA can be treated as an
    extension of the instrument. This is extremely
    important for JDEM, because very detailed
    properties of the telescope such as
    point-spread-function, scattered light and
    thermal stability will interplay with the
    properties of the science instrument. Often
    trades will have to be made during the design
    phase, and unfortunately, sometimes even in the
    fabrication and integration phases. NASA
    missions have taken several approaches to the
    procurement of the OTA and integration of the
    science instrument. For large facility-class
    missions, the mission integrator or a large NASA
    laboratory has taken responsibility for designing
    and procuring the OTA and provided the facilities
    for integrating the scientific instrument and
    OTA. Often, the science team associated with the
    mission provided scientific and technical
    oversight during the design and fabrication
    process. Chandra is an example of a successful
    collaboration, in which both government
    scientists and scientists from the science team
    worked with industry to achieve major advances in
    x-ray telescope fabrication. In the case of the
    Hubble Space Telescope, the telescope scientists
    from the science team had inadequate access, and
    the process failed. Another approach would be to
    have the PI take direct line responsibility for
    the design and procurement of the telescope.
    This is usually the approach for PI-led missions,
    where there is a single instrument. In this
    approach, NASA Centers could provide both
    extensive technical advice, oversight and, if
    needed, integration facilities. Note, that in
    this approach, it is likely that the PI-team
    would have to discuss the OTA design and
    organization of the fabrication as part of the
    proposal process. Whether one of these management
    approaches are used for the OTA or some
    combination of the two-, in order to achieve a
    successful mission, DOE and NASA must ensure that
    the PI-team plays the lead role in specifying the
    telescope and has the authority to obtain a
    thorough understanding of the actual properties
    of the telescope as the OTA is fabricated and
    tested.

11
  • 7.6 Mission Control and Science Support Center
    and the Dark Energy Investigation Science
    Operations Center
  • The Mission Control and Science Support Center
    belong under the line authority of the Project
    Manager. There also needs to be a Science
    Operations Center under the Dark energy
    Investigation PI. Both of these Centers are
    necessary, and it is clear that they have to
    interact intimately and constructively for the
    mission to be successful. The issue is to
    delineate the responsibilities of each,
    minimizing duplication of effort and minimizing
    cracks into which important functions may fall.
    One possible model for these Centers is shown in
    Figure 2.

12
  • In this model Mission Operations performs the
    usual functions of command and control of the
    space vehicle and the instrument, and telemetry
    and control of receiving data from the
    instrument. The unscrambled data is then passed
    on to the Dark Energy Investigation (DEI) Science
    Operations Center. In this Center the Image
    Processing Pipeline is run, as well as the
    Supernova detection and trigger software. This
    Center then schedules the spectroscopic follow-up
    observations and passes these requests back to
    Mission Control. The Supernova Data Base and the
    local depository of the Proprietary Data are also
    the responsibility of the DEI Science Operations
    Center. Data for public release is passed on to
    the NASA Science Support Center where the Public
    Data Archive is kept. It should also be the
    responsibility of the Science Support Center to
    provide User Support should there be a Guest
    Observing phase of the Mission. During the Dark
    Energy Investigation phase the DEI Science
    Operations Center will be the interface to the
    DEI Science Collaboration, while during the Guest
    Observing phase the NASA Science Support Center
    will be the interface to the Guest Observer
    Community.

13
Alternate Section 7.6
  • 7.6 Mission Operations Center and the Dark Energy
    Investigation
  • The Mission Operations Center, which sends
    commands to the spacecraft and receives the raw
    data, belongs under the line authority of the
    Project Manager. The Dark Energy Investigation PI
    Team will be responsible for scientific planning,
    calibration and analysis of the data. It is clear
    that the Mission Operations Center and the PI
    Team have to interact intimately and
    constructively for the mission to be successful.
    The issue is to delineate the responsibilities of
    each, minimizing duplication of effort and
    minimizing cracks into which important functions
    may fall.

14
  • In the model we propose, the PI team would create
    the top level observing commands, including RA
    dec pointings, exposure times, observing cadence,
    instrument configurations, etc. The Mission
    Operations Center would translate these
    observational parameters into a detailed and
    executable schedule, send commands to the space
    vehicle and the instrument, and receive the
    returned data from the observatory. The Mission
    Operations Center would perform zero-level data
    processing (descrambling and file construction)
    and pass the data on to the PI Team. The PI Team
    would then calibrate the data and produce
    higher-level data products (images, catalogs,
    etc.) If needed by the science, the PI Team would
    create observing commands for follow-up
    observations. Either immediately, or at the end
    of a proprietary period, the higher-level data
    products for public release would be returned to
    a public archive for release to the community.
  • Both NASA and the astronomical community consider
    a Guest Investigator (GI) program to be positive
    outcome of the JDEM mission, provided it does not
    drive the costs of the mission too much. However,
    in order for the dark energy investigation to be
    successful, and in order to avoid duplication of
    effort, a substantial amount of the
    infrastructure required to support the GIs must
    be under the control of the PI. In particular,
    the data calibration pipeline must be produced
    and controlled by the PI, and this pipeline must
    then also be available to the GIs. Therefore, we
    recommend that the AO solicit support for a GI
    program as part of the dark energy proposal. The
    manner in which a proposal provides support for a
    GI program without driving mission cost would be
    a selection criterion.

15
  • 7.7 A very important Management issues that does
    not appear explicitly on the Organization Chart
    (and maybe it should) is the flow of funding from
    two different agencies and the control of
    contingency funds.
  • a. One possible scheme that might lead to the
    best overall management of the mission is for
    the agencies to agree on their share of the
    overall project cost and then put the funds in a
    common pot, to be used by the Mission Project
    Manager in a way to ensure an efficient and
    timely project completion. In a similar way
    each agency could put their agreed upon share of
    contingency funds into a common contingency pot,
    to be assigned by the Mission Project Manager in
    a way most advantageous to the overall project.
    However, given the somewhat different customs,
    cultures, and chains of responsibility of the
    two agencies, we are not optimistic that such a
    simple scheme will be accepted by the two
    agencies.

16
  • b. A more realistic arrangement might be for the
    two agencies to agree before construction start
    on which specific subsystems to be the funding
    responsibility of each agency. As a for
    instance, NASA could agree to be responsible for
    the funding of the Spacecraft, Launch, Mission
    Operations and Support Center, the Mission
    Project Managers Office and Engineering, etc.,
    support boxes, while DOE could agree to fund the
    Science Payload/Instruments, Telescope, Science
    Operations, and the Dark Energy Investigations
    coordinating office (with possible non U.S.
    commitments like France funding the
    spectrometer), or some other variation of this.
    In this case funds would flow from NASA to the
    Mission Project Managers office, and DOE funds
    would flow directly to the Dark Energy
    Investigation office. In a similar fashion each
    agency would set the standard for the level of
    contingency to include in the base budgets,
    supply the contingency for their subsystems, and
    presumably assume the responsibility for
    covering unavailable overruns beyond the
    contingency budgeted for their subsystems.
  • If the former of the above, (a), is adopted, an
    organization chart like the one we have been
    discussing seems sufficient. If the latter, (b),
    is closer to the actual funding model, the
    organization chart might have to reflect this
    more complicated scheme.

17
JDEM Example Mission Operations,
Science Operations, and Science Support Centers
Write a Comment
User Comments (0)
About PowerShow.com