AMERICAN SPORTS BUILDERS ASSOCIATION CRITICAL PATH METHOD SCHEDULING FOR SUCCESS - PowerPoint PPT Presentation

1 / 37
About This Presentation
Title:

AMERICAN SPORTS BUILDERS ASSOCIATION CRITICAL PATH METHOD SCHEDULING FOR SUCCESS

Description:

The Critical Path Method (CPM) was designed for and is useful on projects where ... it identifies the (critical) activities that control the overall length of ... – PowerPoint PPT presentation

Number of Views:77
Avg rating:3.0/5.0
Slides: 38
Provided by: natali76
Category:

less

Transcript and Presenter's Notes

Title: AMERICAN SPORTS BUILDERS ASSOCIATION CRITICAL PATH METHOD SCHEDULING FOR SUCCESS


1
AMERICAN SPORTS BUILDERS ASSOCIATIONCRITICAL
PATH METHODSCHEDULING FOR SUCCESS
  • December 6-8, 2008
  • New Orleans, Louisiana
  • Presented By Bill Pronevitch

2
SCHEDULING- Is It Necessary?
  • Effective Project Management involves
    coordinating activities such as
  • Planning
  • Organizing
  • Controlling Time (scheduling)
  • Cost
  • The Scheduling process forces people to
  • Quantify their effort in discrete terms
  • Place tasks in proper relationships

3
SCHEDULING- Methodologies
  • Two of the most common methodologies
  • Bar Charts
  • Critical Path
  • ADM Arrow Diagramming Method
  • PDM Precedence Diagramming Method
  • Both scheduling methods are widely used for
  • Controlling
  • Making optimal use of project time

4
SCHEDULING- Bar Charts
  • Bar Charts (also called Gantt Charts) are
    primarily for controlling Time elements
  • Analyze/ specify the basic approach to be used
  • Segment the work into a reasonable number of
    activities that can be scheduled
  • Estimate the time required to perform each
    activity (i.e.- activity duration)
  • Place activities in time-order (logic)
  • Adjust the chart until the specified completion
    date, if one exists, is satisfied.

5
SCHEDULING- Bar Chart
A B C D E F
  • Gantt Chart (Bar Chart) shows
  • All Activities and Status on a Single Chart

Activities
0 1 2 3 4 5 6 7 8 9
10 11 12
Time in Weeks
6
SCHEDULING- Bar Charts
  • Benefits
  • Plan, Schedule, and Progress on a single chart
  • A simple, understandable way to schedule small
    projects or undertakings
  • Disadvantages
  • Activity-limited, cant handle complex projects
  • Doesnt show logic ties (activity relationships)
  • Insufficient detail to enable timely detection of
    schedule slippages on long duration activities

7
SCHEDULING Critical Path
  • The Critical Path Method (CPM) was designed for
    and is useful on projects where the duration of
    each activity can be with
    reasonable certainty
  • - it predicts project overall completion
  • - it identifies the (critical) activities that
    control the overall length of the project
  • CPM is widely used in process industries
    construction and plant outages/ shutdowns.

estimated
8
SCHEDULING Critical Path
  • Benefits
  • Determines shortest project completion time
  • Identifies critical activities that can not
    be slipped or delayed (i.e.- TOTAL FLOAT)
  • Shows allowable slippage for non-critical
    activities (i.e.- FREE FLOAT)
  • Disadvantages
  • Large number of activities required
  • Difficult to read, understand, and maintain.

9
SCHEDULING CPM/ADM
  • ADM (Arrow Diagramming Method)
  • Arrow (line) represents an Activity
  • Tail (of arrow) shows an Activitys start
  • Head (of arrow) shows an Activitys finish
  • Node (or event) shown at each end
  • The Activity Number consists of Head and Tail
    numbers, commonly referred to as I-J nodes (i.e.-
    I-J Method of CPM)

10
SCHEDULING CPM/ADM
  • ADM Arrow Diagramming Method

Process Work Order
Requisition Material
Install Pump
1
4
5
2
Assign Crew
(Dummy Activity shows relationship, zero
duration)
3
11
SCHEDULING CPM/ADM
  • Benefits
  • Allows use of Dummy Activities which
  • Have a ZERO time duration
  • Can be used to show additional relationships
  • Disadvantages
  • An Activitys Predecessor must be complete
    before the Activity can start!
  • Neither the Activitys arrow length or arrow
    direction have any meaning

12
SCHEDULING CPM/PDM
  • PDM (Precedence Diagramming Method)
  • Box/ Node represents an Activity
  • Line/ Arrow represents a Precedence with time
    and direction properties
  • Precedence consist of two parts
  • Relationship a Predecessor or Successor
  • Lag the (positive or negative) number of work
    periods by which a specified Activity will be
    delayed (assumed to be 0 if not specified)

13
SCHEDULING CPM/PDM
  • PDM Precedence Diagramming Method

Process Work Order
Requisition Material
Install Pump
A
C
B
Assign Crew
D
Pump Installation Completed
E
14
SCHEDULING CPM/PDM
  • Types of Relationships, Lags (aa,n)
  • FS, 0 Finish-to-Start, With 0 units of delay
  • FF, 7 Finish-to-Finish, with 7 units of delay
  • SS, 5 Start-to-Start, with 5 units of delay
  • SF, 0 Start-to-Finish, with 0 units of delay

15
SCHEDULING PDM/ LOGIC
  • Relationships (Logic Ties, Lags

Finish -to- Finish
Finish to- Start
(FF,5)
A
A
B
B
(FS,0)
Start to- Finish
Start to- Start
A
B
B
A
(SS,4)
(SF,0)
16
SCHEDULING CPM/PDM
  • 6 Major Types of Constraints
  • Start On a mandatory date
  • Start No Earlier Than can start later
  • Start No Later Than can start earlier
  • Finish On a mandatory date
  • Finish No Earlier Than can finish later
  • Finish No Later Than can finish earlier
  • NOTE Schedule logic drives earlier and
    later start and finish dates

17
SCHEDULING- PDM/ OTHER
  • Hammock Activity
  • Spans many activities to show an overall
    performance period (i.e.- a summary activity)
  • Logic Loop
  • One of the most common scheduling errors
  • Occurs when a set of activities precede each
    other in a circular fashion, (a group of
    activities can never begin nor end)
  • Must be eliminated prior to calculating the
    schedule (i.e.- running a time analysis)

18
SCHEDULING- Hammock
  • PDM Hammock (Summary) Activity

A
B
C
D
E
19
SCHEDULING PMD/LOOP
  • LOOP No beginning or end
  • (a circular path)

A
B
C
D
LOOP
E
F
20
SCHEDULING PDM/ CALCS
  • Once a network has been created and the durations
    estimated for each activity, both the Total
    Time to reach project completion and each
    activitys individual start and finish times,
    can be calculated
  • Manual computation is easy and logical (but
    tedious time-consuming on large projects)
  • Forward Pass calculates early start/finish,
    (ES/EF)
  • Backward Pass calculates late start/finish,
    (LS/LF)

21
SCHEDULING CALCS
  • FORWARD PASS
  • Calculates Earliest Start and Earliest Finish
    times, observing the following rules
  • Assign an ES time to the first activity
  • Other activities start as soon as their
    predecessor relationships have been satisfied
  • Equations
  • ES EF (Pred.) 1
  • EF ES Duration - 1

22
SCHEDULING CALCS
  • BACKWARD PASS
  • Calculates Latest Start and Latest Finish
    times, observing the following rules
  • Assign an EF time to the last activity.
  • All activities finish as soon as their
    Successor relationships have been satisfied.
  • Equations
  • LF LS (Succ.) 1
  • LS LF Duration 1

23
SCHEDULING CALCS
  • PDM ACTIVITY NOTATION
  • Activity Number unique number to an activity
  • Duration number of work periods assigned
  • ES EF calculated in Forward Pass
  • LS LF calculated in Backward Pass
  • ACTIVITY NUMBER
  • ES EF
  • LS LF
  • DURATION

24
FORWARD BACKWARD PASS
START
FINISH
25
FORWARD BACKWARD PASS
1
5
6
19
6
9
10
13
20
24
START
5
9
24
Early Dates ESs EFp 1 EFs ESs Ds - 1
FINISH
26
FORWARD BACKWARD PASS
5
1
6
19
12
15
16
19
20
24
START
24
11
15
Late Dates LFp LSs -1 LSp LFp D 1
FINISH
27
FORWARD BACKWARD PASS
5
1
6
19
12
15
16
19
20
24
START
24
24
11
15
Late Dates LFp LSs -1 LSp LFp D 1
FINISH
28
(No Transcript)
29
(No Transcript)
30
What is the Scheduling Process?
Report/ Status
Scheduling
Planning
31
IDENTIFY MILESTONES
  • Project Start
  • Project Phase Start and Finishes
  • Equipment and/ or Long Lead Item Delivery
  • Project Finish

32
DEVELOP ACTIVITY LIST(EXAMPLE HOUSE
CONSTURCTION)
  • Select Lot
  • Clear and Grub Lot
  • Install Utilities
  • Construct House
  • Select Contractors
  • Arrange Financing
  • Close Financing
  • Landscape
  • Purchase Appliance and Lighting Fixtures
  • Install Flooring
  • Paint

33
ASSIGN DURATION TO ACTIVITES(EXAMPLE HOUSE
CONSTRUCTION)
  • Select Lot 3 days
  • Clear and Grub Lot 10 days
  • Install Utilities 3 days
  • Construct House 60 days
  • Select Contractors 5 days
  • Arrange Financing 5 days
  • Close Financing 1 day
  • Landscape 5 days
  • Purchase Appliance/Lighting Fixtures 1 day
  • Install Flooring 5 days
  • Paint 5 days

34
SEQUENCE ACTIVITIES
  • ASK THREE QUESTIONS!
  • What activity must come before this one?
  • What activity must come after this one?
  • What activities can I perform at the same time?

35
REVIEW AND FINALIZE
  • Review Relationships
  • Review and Finalize Durations
  • Review Resource Usage
  • Review and Finalize Project End Date
  • Does this achieve the desired date?
  • If it does not. What is the plan NOW?!?

36
(No Transcript)
37
SCHEDULING- CONCLUSION
  • Planning and scheduling functions are usually
    performed iteratively in order to provide for
    accomplishing all required tasks within the
    specified time frames
  • Both Critical Path Methods (ADM PDM) create
    networks showing activity durations and total
    time for project completion
  • Failing to Plan is Planning to Fail, hence
    Plan the Work, Work the Plan
Write a Comment
User Comments (0)
About PowerShow.com