Title: PRESENT STATUS OF GEOTHERMAL ENERGY AND ITS UTILIZATION IN TURKEY
1PRESENT STATUS OF GEOTHERMAL ENERGY AND ITS
UTILIZATION IN TURKEY
- Umran Serpen
- Dept. of Petroleum and Natural Gas Engineering of
Istanbul Technical University
2OUTLINE
- INTRODUCTION
- THE STATUS OF GEOTHERMAL ENERGY IN TURKEY
- ECONOMICS OF GEOTHERMAL UTILIZATION IN TURKEY
- GEOTHERMAL LEGISLATION IN TURKEY
- RESULTS
3INTRODUCTION
- Geothermal energy exploration started in early
1960 in Turkey. - At first, exploration efforts focused on high
enthalpy fields for potential power production,
and Kizildere and Germencik fields were
discovered. - Later exploration efforts resulted in discoveries
of some middle enthalpy fields, such as
Seferihisar, Simav, Salavatli-Sultanhisar, Tuzla,
Dikili, Caferbeyli, etc however, those
geothermal resources have not yet been thoroughly
explored. - With proper exploration methods and investment,
some of them might end up with higher enthalpy
fluids. There are geochemical evidences to
support such situations in some of those fields.
Recently, another high enthalpy field with 215oC
temperature, namely, Kavaklidere geothermal field
was discovered.
4GEOTHERMAL ENERGY IN TURKEY(Indirect Use)
- A conventional steam cycle power plant with 17.4
MWe capacity was installed in Kizildere
geothermal field and has been generating an
average gross power of 10 MWe since 1984. - Technologically superior an air cooled binary
cycle power plant with gross capacity of 7.3 MWe
has recently been completed in Aydin-Salavatli-Sul
tanhisar and operating for more than 4 months. - A decision was made to install another power
plant with larger capacity in Aydin-Germencik for
which reservoir assessment studies are being
conducted, and 9-well drilling program will be
started soon to add existing 9 wells. This power
plant would be in line within 2-3 years.
5GEOTHERMAL ENERGY IN TURKEY(Indirect Use)
6GEOTHERMAL ENERGY IN TURKEY(Direct Use)
- Direct-use of geothermal energy in Turkey has
mostly developed through district heating
systems. First district system was installed in
1987, and 11 others were followed during the
period of 1991-2004. - Direct-use capacity of district heating systems
has reached to the total capacity of
approximately 250 MWt. It is estimated that the
district heating systems have served roughly
35000 households
7District Heating Systems of Turkey.
8Major Greenhouse Areas in Turkey.
9Balneology in Direct Use
- There is another major area, namely balneology
and swimming for the direct use. There are
several health-spa and swimming pools in Turkey.
Their power-use is difficult to quantify, control
and register. - Therefore, the thermal power requirements of well
known major balneological sites together with
some small ones were computed with available data
and for several small sites were estimated on the
basis of the known ones. - Finally, a power requirement for balneology and
swimming is estimated as 110 MWt.
10Total Direct Use in Turkey
- District Heating 253 MWt.
- Greenhouse Heating 142 MWt.
- Balneology Swimming 110 MWt.
- Total 505 MWt.
11Turkeys Geothermal Resource Base
Both estimates are very close except for the
category over 250oC. Since no resource has been
discovered over 250oC, second estimation fits
more to the real situation.
12GEOTHERMAL POTENTIAL OF TURKEY(Results of a
Stochastic Study)
Convertible Energy Categories of Turkey.
13TURKEYS GEOTHERMAL POTENTIAL(Results of a
Stochastic Study on B. Menderes Region)
- The expected accessible geothermal energy for B.
Menderes region is found 5x1019 J and this is
predicted from 18 known fields and occurrences. - The basin simulation runs revealed that, if only
half structures are productive, the predicted
accessible heat is 5x1019 J. - The expected available energy for electricity
production is 2x1018 J. Under current technology
only 3.19x1017 J. - The expected convertible energy for direct use is
3.5x1018 J whereas for electricity production is
3.2x1016 J.
14TURKEYS GEOTHERMAL POTENTIAL(Summary)
- A potential of a few thousands of MWe (1000 to
1500 ) at Menderes Massive - A few hundredths MWe at around Central Anatolia
and - Few tens MWe at Quaternary Volcanoes of Eastern
Anatolia regions.
15TRENDS IN THE UTILIZATION OF GEOTHERMAL ENERGY IN
TURKEY
- Unlike the world trend, utilization of heat pumps
and development of enhanced geothermal systems
have not gained any footage in Turkey. - Heat pump utilization is very limited due to its
high capital costs. Carbon credits exchange may
not be feasible given the high CO2 content of
most of Turkeys high enthalpy geothermal
resources. - Although Kizildere geothermal power plant has
long been in line for privatization, it has not
been materialized (Oct.15th 2006). - On the other hand, geothermal power plants and
greenhouse heating seem to be very popular for
the private sector.
16Economics of Power Generation in Turkey
- A stochastic study was conducted on economics of
geothermal resources in Turkey (Serpen, 2005). - As for electricity generation, this type of
utilization looks profitable with the electricity
selling prices of around 6 cents/kWh. - The payout time for this type of investments
reaches 7 to 8 years. - The profitability increases with the quality
(heat content) of resource and the magnitude
(physical extent) of resources.
17Economics of District Heating
- A stochastic study was also conducted for
district heating systems (several of them already
installed). They do not seem to be profitable
with actual low fixed rate heat tariffs. - Several of them are studied, and only a one of
them resulted in a marginally profitable
business. - Other studies, such as conceptual planning of the
extension of Balçova district heating system,
district heating project for Seferihisar-Cumali
and Gediz geothermal resources have always
resulted in negative NPV with actual tariffs and
deposit costs imposed on people.
18Economics of Greenhouse Heating
- Greenhouse heating looks very profitable.
- It costs 5 million dollars to build a 100 decare
greenhouse which pays out in two years. - A power plant, which consumes roughly the same
amount of heat costs 12 million dollars and pays
out in 8 years. - It may be more profitable to go into business of
greenhouse than power production.
19Health-Spa Tourism
- Health-Spa business is thriving in Turkey, and
our Spas were visited by 4 million domestic
visitors. But, the Spas are generally not in good
shape. - Turkey has a lot of natural balneological sites
each serving a different kind of illness. If
these sites were rebuilt and proper health
services provided, Turkey could attract a lot of
foreign patients and visitors who do not have
this sort of facilities in their countries, or at
least at affordable prices.
20Why Our Geothermal Resources Have Not Been
Properly Developed
- There are many problems hindering the development
of geothermal resources of Turkey. These can be
summarized in 3 categories - (1) technical,
- (2) economical, and
- (3) legislative.
21GEOTHERMAL LEGISLATION IN TURKEY
- There are several draft codes for geothermal
energy - One prepared by Ministry of Energy,
- Another by Ministry of Interior.
- Another by an opposition representative.
- Taking into account of legislations of major
producers, this author has prepared a
contemporary draft code for geothermal energy and
presented to Ministry of Energy. This draft was
based on Integrated Resource Management
Philosophy.
22Problems of District Heating Systems
- The resources have been completely ignored and
therefore, some resources could not supply
sufficient heat to the oversized district heating
systems (Salihli and Gönen towns). - The worst has recently happened, and local
government officials in Sandikli town connected a
coal-fired boiler to existing geothermal district
heating system. It is a real pity for the
national geothermal industry.
23Problems of District Heating Systems
- The most serious problem in this sector is that
some local government officials started to
reconsider geothermal district heating systems. - They seriously ponder on dismantling the existing
district heating facilities and connect the
natural gas to the houses for heating. - On the other hand, they consider allocating
geothermal resources to health tourism, which has
lately been very popular and economically
attractive.
24RESULTS
- In Turkey, economics of power generation looks
sound, and new projects are in line. - Economics of district heating systems with
existing financial model and tariffs in Turkey
are not in good shape, and they will not be able
to compete with natural gas in the short and mid
term. - Turkey has suitable geothermal resources for the
utilization of process heating, and this should
be emphasized and taken into account by
industrialists.
25RESULTS (cont.)
- The utilization of geothermal resources of Turkey
in greenhouse heating seems economically sound,
and industry has already sensed that trend. - Taking into account of Turkeys rich geothermal
resources she merits a contemporary geothermal
legislation, but the existing official drafts of
geothermal law are insufficient and far from to
meet actual requirements of Turkey in many
aspects.
26Acknowledgement
- The Author gratefully acknowledges the support
provided by Zorlu Energy and expresses his
gratitude to its manager.