Maytag Business Integration Integrating Two World Class Supply Chains - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

Maytag Business Integration Integrating Two World Class Supply Chains

Description:

Every home...Everywhere Every home...Everywhere Every home... Detroit Tigers. New Agenda Tonight ... Overall Project Management and Scope Trish Vigansky ... – PowerPoint PPT presentation

Number of Views:336
Avg rating:3.0/5.0
Slides: 37
Provided by: whirl9
Category:

less

Transcript and Presenter's Notes

Title: Maytag Business Integration Integrating Two World Class Supply Chains


1
Maytag Business IntegrationIntegrating Two
World Class Supply Chains
  • Supply Chain Management
  • Steve Whalen
  • Chris Richards
  • Trish Vigansky
  • Ellie Lundberg
  • Kevin OMeara

2
Detroit Tigers New Agenda Tonight
3
Agenda
  • Introductions and Structure Kevin OMeara
  • Overall Project Management and Scope Trish
    Vigansky
  • International Integration Activities Ellie
    Lundberg
  • Physical Network Integration Steve Whalen
  • Systems Integration Chris Richards
  • Questions and Answers All

4
The Presenters.
  • Trish Vigansky
  • Responsible for our inventory deployment /
    management
  • Overall Supply Chain Project lead reporting to
    Brian Hancock, VP Supply Chain and the Corporate
    PMO

5
NAR Supply Chain Leadership Staff
6
Agenda
  • Introductions and Structure Kevin OMeara
  • Overall Project Management and Scope Trish
    Vigansky
  • International Integration Activities Ellie
    Lundberg
  • Physical Network Integration Steve Whalen
  • Systems Integration Chris Richards
  • Questions and Answers All

7
Supply Chain Management Integration Scope
  • Integration Objectives
  • Deliver business case efficiencies
  • Integrate systems processes
  • 1 order 1 delivery 1 invoice

8
Maytag Integration Project Structure Supply
Chain
Formalized project management structure utilized
to manage integration
9
Maytag Integration Project Structure
34 projects underway to deliver integration
commitments
10
Maytag Business Case
Logistics Roadmaps
Total Whirlpool Business Case Efficiencies
400 Million Driven primarily by efficiencies in
Manufacturing, Procurement Logistics
  • Elimination of Private Fleet
  • LDC Integration and Consolidation
  • Logistics Procurement
  • RDC Integration and Consolidation
  • SOP Process -Production Planning
  • SOP Process - Demand Forecasting
  • Home Depot Delivery
  • FDC Consolidation
  • Inbound Transportation
  • International Logistics
  • Logistics Staff Consolidation
  • Call Center Consolidation

Savings formally tracked in Roadmapping tool by
milestone. . . with detailed back-up required to
document attainment of efficiencies
11
Maytag Integration Order-to-Cash Map . . . after
systems consolidation
On October 30th . . .
Two delivery documents, one at each warehouse
Invoice
Order
Delivery Documents
Integrated routing enables multiple shipments on
one truck for 40 of deliveries
WHR MYG brands can be combined on one order in
SAP - requires one sold-to number for TP -
consolidated payment terms - capability to
leverage
Invoice
Two Invoices, One Payer Account
Two warehouse inventory locations
1 order . . . 2 deliveries . . . 2 invoices
12
Future State Order-to-Cash Map
In 2nd quarter 2008 . . .
Delivery Document
Shipment
Order
Trade Partner
Brands can be combined on one order in SAP
Invoice
Consolidated RDC Warehouse - one inventory
location for MYG WHR brands
One consolidated warehouse enables one invoice
1 order . . . 1 delivery . . . 1 invoice enabled
by Network Consolidation
13
Change Management Scorecard
Testing and Program Level Updates to Track
Overall Project Status also included
14
Agenda
  • Introductions and Structure Kevin OMeara
  • Overall Project Management and Scope Trish
    Vigansky
  • International Integration Activities Ellie
    Lundberg
  • Physical Network Integration Steve Whalen
  • Systems Integration Chris Richards
  • Questions and Answers All

15
International Integration Activities
  • CURRENT STATE
  • Scope Integrate Three Business Units
  • Whirlpool International Business
  • One entity per region / one system per region /
    one global process
  • Maytag International Business
  • Two entities / two systems / two processes
  • FUTURE STATE
  • Transition Two States
  • Interim State
  • Operate two systems in the US
  • July - October
  • Final State
  • Operate one system in the US

16
Process Change
As-Is Centralized Order Management
International Customers send their orders into
Schaumburg
Schaumburg receives the order and manages until
fulfillment
Warehouse picks and loads the order per
Schaumburgs instructions
Order is shipped per the Customer Instructions
To-Be Regional Order Management
Regional contacts enter order into appropriate
system and send to Hilltop
Warehouse picks and loads the order per
Hilltops instructions
International Customers send their orders into
appropriate Region
Hilltop receives the order and manages until
fulfillment
Order is shipped per the Regional and Hilltops
Instructions
17
Areas Of Impact Scope - Method
  • Process Freight Forwarder, terms
  • Inventory On Hand or Build to Order Shared
    Inventory
  • Shipments Mixed Loads, Spare Parts
  • Documentation Flow FDC RDC
  • Shipment Flow - Port Distribution ASN
  • Customs Compliance

18
Agenda
  • Introductions and Structure Kevin OMeara
  • Overall Project Management and Scope Trish
    Vigansky
  • International Integration Activities Ellie
    Lundberg
  • Physical Network Integration Steve Whalen
  • Systems Integration Chris Richards
  • Questions and Answers All

19
2006 Combined Whirlpool Maytag U.S. Appliance
Distribution Network
Trade Partner
Trade Partner
Supplier
Supplier
42 M
117 M
180 M
62 M
100 M
161 M
48 M
Factory
Factory Distribution Center (FDC)
Regional Distribution Center (FDC)
Local Distribution Center (FDC)
119 M
Trade Partner
Home
830 M Combined Spend (Duplicate Network)
20
Distribution Network Engineering and Consolidation
Legacy Whirlpool Distribution Network
Legacy Maytag Distribution Network
21
Results - Whirlpool 2008 Distribution Network
We must build, re-locate, bid, and/or shut down
over 75 facilities (approximately 1 facility/week)
22
Inbound Logistics Consolidation
Integrate MYG Inbound Logistics into Whirlpool
Centrally Controlled Inbound Network
MYG/WHR Future State Centrally Routed
Transportation (WHR process)
MYG Current State Factory Routed Transportation
Key Challenges 1) Engineering 2) Loss of
Control by Factories 3) Determination of
Savings (supplier changes)
23
FDC Consolidation
Eliminate FDCs at Closed Factories
WHR/MYG Current State
WHR/MYG Future State
Key Challenges 1) Post Closing Announcement
Productivity 2) Property Disposition
24
RDC Consolidation
Consolidate Duplicate RDCs
WHR/MYG Current State
WHR/MYG Future State
Key Challenges 1) Funding (Zenith - 500 M
) 2) Operational Efficiency (Size) 3) WM
Functionality
25
LDC Consolidation
Consolidate Duplicate LDCs
WHR/MYG Current State
WHR/MYG Future State
Key Challenges 1) Engineering 2)
Procurement (specialized providers) 3) Service
Disruption
26
Agenda
  • Introductions and Structure Kevin OMeara
  • Overall Project Management and Scope Trish
    Vigansky
  • Physical Network Integration Steve Whalen
  • Systems Integration Chris Richards
  • Questions and Answers All

27
Purpose (Planning)
  • Integrate Maytag Existing locations and products
    into the Whirlpool Planning Environment
  • Support of activities required to build Maytag
    product inside Whirlpool facilities and
    distribute that product back into the Maytag
    network
  • Support taking an order in SAP for Maytag Product
    in the October time frame

28
Current Planning Landscape
WISE Data W/H
Adexa
Shipments
  • Historical orders
  • Fcst
  • Inventory levels
  • Production Sch

Orders
  • Fcst (Appliances)

Fcst
COMPASS
  • Returns
  • Inventory levels
  • Deployment
  • Planning

Historical Shipments Inventory Levels Production
Schedule
  • Order Entry
  • Load Consolidation
  • Shipment Builder

MAYTAG
Deployment Targets
  • Target Setting
  • MRP
  • WIP Inventory
  • Raw Material Inv
  • G/L

Quantum Pull and Flex
Production Schedule
Production Recommendations
PRMS
  • Forecasting

I2-DP
  • Orders
  • Shipments
  • Inventory levels
  • Intransits

LOGICS
Forecast
Delivery information
WHIRLPOOL
  • Order Entry
  • Inventory Levels
  • Load building
  • Warehouse Mgmt
  • Deployment Planning
  • Master Planning
  • Inventory Planning

Inventory levels
Delivery information
  • Warehouse Mgmt
  • Deployment Plan
  • Production Plan

I2-SCP
SAP
SAP
  • Production Plan
  • (outside of firm)
  • Production Plan (firm)

WMCS
Production Crates
  • Detailed Sch
  • MRP

29
Phase I--Forecast Goes Early
WISE Data W/H
Adexa
Shipments
  • Historical orders
  • Fcst
  • Inventory levels
  • Production Sch

Orders
  • Fcst (Appliances)

Fcst
COMPASS
Historical Shipments Inventory Levels Production
Schedule
  • Returns
  • Inventory levels
  • Deployment
  • Planning
  • Order Entry
  • Load Consolidation
  • Shipment Builder

MAYTAG
Deployment Targets
  • Target Setting
  • MRP
  • WIP Inventory
  • Raw Material Inv
  • G/L

Quantum Pull and Flex
Production Schedule
Production Recommendations
PRMS
I2-DP
Maytag
Whirlpool
  • Orders
  • Shipments
  • Inventory levels
  • Intransits

LOGICS
Forecast
Delivery information
WHIRLPOOL
  • Order Entry
  • Inventory Levels
  • Load building
  • Warehouse Mgmt
  • Deployment Planning
  • Master Planning
  • Inventory Planning

Inventory levels
Delivery information
  • Deployment Plan
  • Production Plan
  • Warehouse Mgmt
  • Production Plan
  • (outside of firm)

I2-SCP
SAP
SAP
  • Production Plan
  • (firm)

WMCS
Production Crates
  • Detailed Sch
  • MRP

30
Phase II--Order taken in SAP
WISE Data W/H
Adexa
Shipments
  • Historical orders
  • Fcst
  • Inventory levels
  • Production Sch

Orders
  • Fcst (Appliances)

Fcst
COMPASS
Historical Shipments
  • Returns
  • Inventory levels
  • Deployment
  • Planning
  • Order Entry
  • Load Consolidation
  • Shipment Builder

MAYTAG
Deployment Targets
  • Target Setting
  • MRP
  • WIP Inventory
  • Raw Material Inv
  • G/L

Quantum Pull and Flex
Production Schedule
Production Recommendations
PRMS
SAP Shipments Inventory Levels Production Schedule
BW
I2-DP
Maytag
Whirlpool
  • Orders
  • Shipments
  • Inventory levels
  • Intransits

LOGICS
Forecast
Delivery information
WHIRLPOOL
  • Order Entry
  • Inventory Levels
  • Load building
  • Warehouse Mgmt
  • Deployment Planning
  • Master Planning
  • Inventory Planning

Inventory levels
Delivery information
  • Deployment Plan
  • Production Plan
  • Warehouse Mgmt
  • Production Plan
  • (outside of firm)

I2-SCP
SAP
SAP
  • Production Plan
  • (firm)

WMCS
Production Crates
  • Detailed Sch
  • MRP

31
Phase III--Move MP and DPL
WISE Data W/H
Adexa
Shipments
  • Historical orders
  • Fcst
  • Inventory levels
  • Production Sch

Orders
  • Fcst (Appliances)

Fcst
COMPASS
  • Returns
  • Inventory levels
  • Deployment
  • Planning
  • Order Entry
  • Load Consolidation
  • Shipment Builder

MAYTAG
  • Target Setting
  • MRP
  • WIP Inventory
  • Raw Material Inv
  • G/L

Quantum Pull and Flex
Production Schedule
PRMS
I2-DP
Maytag
Whirlpool
  • Orders
  • Shipments
  • Inventory levels
  • Intransits

LOGICS
Forecast
Forecast
Delivery information
WHIRLPOOL
  • Order Entry
  • Inventory Levels
  • Load building
  • Warehouse Mgmt
  • Deployment Planning
  • Master Planning
  • Inventory Planning

Inventory levels
Calendars, Capacity Engr Models, Components
Delivery information
  • Deployment Plan
  • Production Plan
  • Warehouse Mgmt
  • Production Plan
  • (outside of firm)

I2-SCP
SAP
SAP
  • Production Plan
  • (firm)

WMCS
Production Crates
  • Detailed Sch
  • MRP

32
Purpose (Warehousing)
  • Integrate Maytag Existing FDC/RDC Warehouse
    locations into Whirlpool such that they can
  • Process SAP deliveries/shipments by October
    deadlines
  • Maintain Accurate Inventories and mechanisms to
    verify and adjust these Inventories with SAP as
    the Master Inventory System
  • Interact appropriately to other Areas of the
    business such as Manufacturing, Finance, and
    Sales

33
Current Landscape
WISE Data W/H
Sales Data Orders Master Data
  • Historical orders
  • Fcst
  • Inventory levels
  • Production Sch

Orders Demand
COMPASS
Maytag International SAP
  • Returns
  • Inventory levels
  • Deployment
  • Planning
  • Order
  • Entry
  • Order Entry
  • Load Consolidation
  • Shipment Builder
  • ASN Delivery info
  • Inventory adjustments
  • Status

Shipments Reservation Inventory
MAYTAG
  • Order information
  • Load Consolidation
  • Item Info
  • Serial Info

IWCS/HWCS
  • MRP
  • WIP Inventory
  • Raw Material Inv
  • G/L

Schedule Production Count
  • WM
  • Inventory levels

PRMS
Production Counts
LOGICS
  • Deployment Plan
  • Production Plan(outside
  • firm period)

Delivery information
WHIRLPOOL
  • Order Entry
  • Inventory Levels
  • Load building
  • Warehouse Mgmt
  • Forecasting
  • Deployment Planning
  • Master Planning
  • Inventory Planning

Inventory levels
Delivery information
  • Warehouse Mgmt
  • Orders
  • Inventory levels
  • Intransits

i2
SAP
SAP
WMCS
Production Sch(firm period)
  • Detailed Sch
  • MRP

34
Selecting the Approach
  • Three potential approaches were examined
  • Interface Maytag IWCS system through Compass to
    SAP
  • Interface Maytag IWCS system directly to SAP
  • Implement Logics in all Maytag Sites

35
Selected Approach
WISE Data W/H
Sales Data Orders Master Data
  • Historical orders
  • Fcst
  • Inventory levels
  • Production Sch

Orders Demand
COMPASS
Maytag International SAP
  • Returns
  • Inventory levels
  • Deployment
  • Planning
  • Order
  • Entry
  • Order Entry
  • Load Consolidation
  • Shipment Builder
  • ASN Delivery info
  • Inventory adjustments
  • Status

Shipments Reservation Inventory
MAYTAG
  • Order information
  • Load Consolidation
  • Item Info
  • Serial Info

IWCS/HWCS
  • MRP
  • WIP Inventory
  • Raw Material Inv
  • G/L

Schedule Production Count
  • WM
  • Inventory levels

PRMS
Production Counts
  • Order information
  • Load Consolidation
  • Item Info
  • Serial Info
  • ASN Delivery info
  • Inventory adjustments
  • Status

Production Counts
LOGICS
  • Deployment Plan
  • Production Plan(outside
  • firm period)

Delivery information
WHIRLPOOL
  • Order Entry
  • Inventory Levels
  • Load building
  • Warehouse Mgmt
  • Forecasting
  • Deployment Planning
  • Master Planning
  • Inventory Planning

Inventory levels
Delivery information
  • Warehouse Mgmt
  • Orders
  • Inventory levels
  • Intransits

i2
SAP
SAP
WMCS
Production Sch(firm period)
  • Detailed Sch
  • MRP

36
Agenda
  • Introductions and Structure Kevin OMeara
  • Overall Project Management and Scope Trish
    Vigansky
  • Physical Network Integration Steve Whalen
  • Systems Integration Chris Richards
  • Questions and Answers All