Title: Proposed Chromium and Cadmium Remediation Plan: Plate This, Inc' Chesterfield, Missouri
1Proposed Chromium and Cadmium Remediation
PlanPlate This, Inc.Chesterfield, Missouri
Plate This, Inc.
Ganesh Environmental Engineering Incorporated
Ganesh Environmental Engineering Inc.U.S.
Environmental Protection AgencyMissouri
Department of Natural Resources
2Site Background
- Plate This, Incorporated
- World Leader in Metal Plating
- 1000 acre facility
- HQ in Chesterfield, Missouri (manufacturing,
transport, and offices) - 1993, Single Truck Accident Hauling Chromium and
Cadmium Wastes - Temporary treatment to prevent movement of metals
using passive walls - Great Flood of 1993
- 8 year litigation
- Plate This required to pay all clean up costs
3Site Characteristics
- Only a small 47 acre plot in the northeastern
section of company property contaminated - Missouri River to the East and South
- Industrial zoned area neighbored by a
transportation hub and barrel maker - Transport, Waste Treatment, and Maintenance Area
- Various sources of surface water
- Typical River Bottom Geology
- Contamination
- Shallow Wells 4
- Deep Wells19
4Scope and Role of Operable Unit or Response Action
- 50 Years of Industrial Practices at Site with No
Plans of Changing - Not Specified as a Brownsfield Site
- Contaminant Removal to
- Chromium1000 ug/l
- Cadmium110 ug/l
- Remediation Phases
- Phase I Discontinue pumping companys wells
- Phase II Containment of Site
- Phase III Contaminant Removal
5Summary of Site Risks
- Facility not near residential zones, yet if not
treated, metals can end up in downstream water
treatment plant intakes - Health Problems
- Chromium--Hematological, Hepatic, Renal,
Neurological, Testicular diseases in human beings - Cadmium--Renal (proteinuria), Cardiovascular,
Hematological, Hepatic, Neurological, Testicular
cancers - MCLs
- Chromium1000 ug/l
- Cadmium110 ug/l
6Remedial Action Objectives
- Site divided into 30 sectors
- 4 sectors remediated by EKRT and Soil Washing
- 4 sectors remediated by EKRT alone
- Remaining sectors remediated by Phytoremediation
- Maximum contaminant levels
- 1000 ug/L Chromium
- 110 ug/L Cadmium
7Summary of Remedial Action Alternatives
- Electro Kinetic Remediation Technology (EKRT)
- Soil Washing
- Treatment Walls
- In Situ Vitrification (ISV)
- Phytoremediation
8Remedial Action Alternatives to be Achieved and
Estimated Quantities of Material to be Addressed
- Implementation Requirements
- Reasonable Future land use
- Expected Outcome using various Remediation
Alternatives - Estimated Cost
9Evaluation of Alternatives
- Overall Protection of Human Health and the
Environment - Long Term Effectiveness and Permeance
- Reduction of Toxicity, Mobility, Volume through
Treatment - Short Term Effectiveness
- Implementability
- Cost
- State/Support Agency Acceptance
10Preferred Alternative
- Soil Washing, EKRT, Phytoremediation
- Cost of Soil Washing 9,239,640
- Cost of EKRT 27,841,391
- Cost of Phytoremediation 12,849,873
- Total Cost of Remediation 49,930,000
11Community Participation
- All design decisions will go to the public for a
final decision. - Public Comment Period June 1-July 31, 2003
- Public Hall Meeting June 10, 2003
- Chesterfield City Hall690 Chesterfield Pkwy W,
Chesterfield, MO 63017 Phone (636) 537-4000 - Location of Administrative Records
- St. Louis County Library16400
- Burkhardt Place
- Chesterfield, Missouri 63017
- Phone (636) 728-0001Call for Hours
12Conclusions and Wrap-Up
- Chromium concentration down to 1000 ug/l
- Cadmium concentration down to 110 ug/L
- Three technologies used are EKRT, Soil Washing,
Phytoremediation - Cost of the project 49,930,000
- Takes three years to remediate the highly
concentrated portions
13Questions or Comments?