Title: Installing PreChlorinated Water Mains with Static Pull Pipe Bursting Systems in Fort Pierce, Florida
1Installing Pre-Chlorinated Water Mains with
Static Pull Pipe Bursting Systems in Fort Pierce,
Florida
2The State of Water Distribution Systems
- Encrusted
- Corroded
- Water loss up to 40
- Under capacity
- Poor water quality
3Business Opportunity
- EPA estimates 750 billion dollars over next 20
years - AWWA estimates 1 trillion dollars over next 20
years
4Open Trench Water Main Replacement Projects?
Open trench method of replacement is becoming
more costly and less socially accepted.
5Pipe Bursting Pressure Pipe
- History
- Method was developed By British Gas and patented
in 1980s for gas distribution rehabilitation. - Success led to potable water crossover
- Pipe bursting without protection sleeve accepted
along with pre-chlorination method in early
1990s in the UK - Widely accepted in Europe with more than
60,000,000 feet installed in the past 16 years - Great News!
- Pre-Chlorinated method of pipe bursting is
accepted by Florida DEP in conjunction with the
Florida AWWA in November of 2000
6United Kingdom - Pipe Bursting
7Pipe Bursting with Pre-chlorination Method
- A preferred method of water line rehabilitation
- Follows path of the existing utility (reduces
potential for 3rd party utility damage) - Easement issues and line separation limitations
are reduced - the existing utility path is used - Reduce excavation costs by up to 85
- Able to increase the pipe diameter
- Production Install up to 400 of pipe in under
2 hours - Pre-chlorination save cost and disruption of
installing temporary services - FL- No permitting required for bursting
Classed as a line repair
8Pre-chlorinated Pipe
New service lines bored with piercing tools
Hydraulic unit pulls rod, expander and pipe
through existing line
Pin Joint Tooling
9Pipe Bursting Setup Push out rod
10Pipe Bursting Setup Attach tooling and pipe
11Pipe Bursting Setup Pull back
12Project Considerations
- Preferred pipe material
- HDPE MDPE
- Fusible PVC in review process
- Improved flow rates
- IPS and DIPS size pipes
- Zero leaks
- Electro-fusion couplers for mains and service
connections - Butt fusion for connecting segments of HDPE above
ground prior to burst - Computer model of systems can be constructed
13Connections Fuse-on Pullers
14Butt Fusion and De-Beading
15ConnectionsElectro-Fusion Couplers
16Squeeze-off Tool
17Equipment Selection
- Static equipment is most common for water
projects - No-contamination of the new HDPE pipe
- Ability to pull ductile iron slitters and
overcome repair sections - Fast and simple equipment to operate
18Equipment Selection
- High tonnage static pull back force
- 38 ton (2 6 pipe)
- 58 ton (4 8 pipe)
- 80 ton (4 12 pipe)
- 125 ton (6 20 pipe)
- Impactor assist for larger pipes
- Hydraulic power supply
19Project Considerations - Upsizing
- Replace existing pipe with pipe providing
suitable flow characteristics - Reduce project risks of surface heave by limiting
water projects to size for size or 1 upsize
replacement.
20Flow Comparisons
21Project Considerations Pre-chlorination
- Proven methods saving time and expense
- Pipe is pressure tested and disinfected above
ground prior to use
22Project Considerations Pre-chlorination
- Services are installed and ready to be
reconnected the same day of construction - No temporary services are required due to the
pre-chlorination and testing of the pipe prior to
installation
23Method OnePipe Bursting Water Mains
- Acceptable method by experienced city and
contractor - Pre - chlorination and testing conducted above
ground, left to stand a minimum of 24 hours - Flushed, and pulling head welded to pipe to keep
ends sealed hygienically - Pipe burst into place
- Super chlorinated swab is passed through the line
24Method OnePipe Bursting Water Mains
- After removal of swab, line is flushed and
commissioned - Pipe connected and flushed
- After flushing and commissioning, services are
connected - First of two samples taken
- 24 hours later, second samples taken
25Method TwoPipe Bursting Water Mains
- Acceptable method by experienced city and
contractor - Pre - chlorination and testing conducted above
ground, left to stand a minimum of 24 hours - Main line is flushed and sample one is taken
- 24 hours later, sample two is taken
26Method TwoPipe Bursting Water Mains
- When both samples have returned passed, a 14 day
log will be posted to that pipe. (THIS PIPE IS
NOW GOOD FOR 14 DAYS) - If the pipe is not installed within the 14 days,
the process is repeated. - Pipe is burst into place
- Super chlorinated swab is passed through the line
- After removal of swab, line is flushed and
commissioned - Service connections are made to the main line
27Fort Pierce, FloridaCase Study
28Water Main Problems
- Received complaints regarding potable water
clarity and low pressure concerns - Cast iron water mains more than 65 years old
- New service line installations required
- Limited working space, easement issues, high end
homes in neighborhood, heavy traffic making open
cut not a feasible option - David Mellert of FPUA contacted Murphy Pipeline
Contractors re pipe bursting
29Fort Pierce, Florida Case Study
- 12,000 feet of new mains
- Crew of 8 completed project in 2 months
- Existing 6 cast iron pipe replaced with 6 HDPE
pipe - An average of 400 feet per day was replaced
- Estimated cost savings vs. open cut 30
30Pre-Chlorination
- Lines capped and disinfected with a hypochlorite
solution
31Entry and Exit Pits
- Pits dug on entry and exit end of the pipe
- Rods passed from entry to exit pit in
approximately 45 minutes
32Bursting Head and Expander
- Bursting Rig is attached to the bursting blade
and expander - Pre-chlorinated and sealed HDPE pipe are attached
to the expander
33Hydraulic Static Pull
- Bursting blade is drawn through the existing
Host pipe causing it to fracture - Bursting expander then pushes broken pipe into
the surrounding soil
34Rods Recovered at Exit Pit
- Rods are removed from the exit pit as pipe is
pulled into place - Mainline connections are made and services tied
in - For the next burst the exit pit becomes new entry
pit
35Service Re-connection
- Small service excavations 4 x 4
- New services installed with piercing tools
- HDPE services are electro-fused to the main
providing a 100 sealed connection
36Conclusions
- Pipe bursting potable water mains utilizing the
pre-chlorination method is an effective method to
open cut pipe replacement - Allowed upsizing in place
- Minimized disturbance to the surrounding area
37Conclusions
- 12,000 feet of pipe replaced in 2 months with
crew of 8 - Previous FL project performed by Murphy Pipelines
received runner up project of the year - Fort Pierce project received nomination for
project of the year.
38Thank You