Installing PreChlorinated Water Mains with Static Pull Pipe Bursting Systems in Fort Pierce, Florida - PowerPoint PPT Presentation

1 / 38
About This Presentation
Title:

Installing PreChlorinated Water Mains with Static Pull Pipe Bursting Systems in Fort Pierce, Florida

Description:

Installing PreChlorinated Water Mains with Static Pull Pipe Bursting Systems in Fort Pierce, Florida – PowerPoint PPT presentation

Number of Views:520
Avg rating:3.0/5.0
Slides: 39
Provided by: jason69
Category:

less

Transcript and Presenter's Notes

Title: Installing PreChlorinated Water Mains with Static Pull Pipe Bursting Systems in Fort Pierce, Florida


1
Installing Pre-Chlorinated Water Mains with
Static Pull Pipe Bursting Systems in Fort Pierce,
Florida
2
The State of Water Distribution Systems
  • Encrusted
  • Corroded
  • Water loss up to 40
  • Under capacity
  • Poor water quality

3
Business Opportunity
  • EPA estimates 750 billion dollars over next 20
    years
  • AWWA estimates 1 trillion dollars over next 20
    years

4
Open Trench Water Main Replacement Projects?
Open trench method of replacement is becoming
more costly and less socially accepted.
5
Pipe Bursting Pressure Pipe
  • History
  • Method was developed By British Gas and patented
    in 1980s for gas distribution rehabilitation.
  • Success led to potable water crossover
  • Pipe bursting without protection sleeve accepted
    along with pre-chlorination method in early
    1990s in the UK
  • Widely accepted in Europe with more than
    60,000,000 feet installed in the past 16 years
  • Great News!
  • Pre-Chlorinated method of pipe bursting is
    accepted by Florida DEP in conjunction with the
    Florida AWWA in November of 2000

6
United Kingdom - Pipe Bursting
7
Pipe Bursting with Pre-chlorination Method
  • A preferred method of water line rehabilitation
  • Follows path of the existing utility (reduces
    potential for 3rd party utility damage)
  • Easement issues and line separation limitations
    are reduced - the existing utility path is used
  • Reduce excavation costs by up to 85
  • Able to increase the pipe diameter
  • Production Install up to 400 of pipe in under
    2 hours
  • Pre-chlorination save cost and disruption of
    installing temporary services
  • FL- No permitting required for bursting
    Classed as a line repair

8
Pre-chlorinated Pipe
New service lines bored with piercing tools
Hydraulic unit pulls rod, expander and pipe
through existing line
Pin Joint Tooling
9
Pipe Bursting Setup Push out rod
10
Pipe Bursting Setup Attach tooling and pipe
11
Pipe Bursting Setup Pull back
12
Project Considerations
  • Preferred pipe material
  • HDPE MDPE
  • Fusible PVC in review process
  • Improved flow rates
  • IPS and DIPS size pipes
  • Zero leaks
  • Electro-fusion couplers for mains and service
    connections
  • Butt fusion for connecting segments of HDPE above
    ground prior to burst
  • Computer model of systems can be constructed

13
Connections Fuse-on Pullers
14
Butt Fusion and De-Beading
15
ConnectionsElectro-Fusion Couplers
16
Squeeze-off Tool
17
Equipment Selection
  • Static equipment is most common for water
    projects
  • No-contamination of the new HDPE pipe
  • Ability to pull ductile iron slitters and
    overcome repair sections
  • Fast and simple equipment to operate

18
Equipment Selection
  • High tonnage static pull back force
  • 38 ton (2 6 pipe)
  • 58 ton (4 8 pipe)
  • 80 ton (4 12 pipe)
  • 125 ton (6 20 pipe)
  • Impactor assist for larger pipes
  • Hydraulic power supply

19
Project Considerations - Upsizing
  • Replace existing pipe with pipe providing
    suitable flow characteristics
  • Reduce project risks of surface heave by limiting
    water projects to size for size or 1 upsize
    replacement.

20
Flow Comparisons
21
Project Considerations Pre-chlorination
  • Proven methods saving time and expense
  • Pipe is pressure tested and disinfected above
    ground prior to use

22
Project Considerations Pre-chlorination
  • Services are installed and ready to be
    reconnected the same day of construction
  • No temporary services are required due to the
    pre-chlorination and testing of the pipe prior to
    installation

23
Method OnePipe Bursting Water Mains
  • Acceptable method by experienced city and
    contractor
  • Pre - chlorination and testing conducted above
    ground, left to stand a minimum of 24 hours
  • Flushed, and pulling head welded to pipe to keep
    ends sealed hygienically
  • Pipe burst into place
  • Super chlorinated swab is passed through the line

24
Method OnePipe Bursting Water Mains
  • After removal of swab, line is flushed and
    commissioned
  • Pipe connected and flushed
  • After flushing and commissioning, services are
    connected
  • First of two samples taken
  • 24 hours later, second samples taken

25
Method TwoPipe Bursting Water Mains
  • Acceptable method by experienced city and
    contractor
  • Pre - chlorination and testing conducted above
    ground, left to stand a minimum of 24 hours
  • Main line is flushed and sample one is taken
  • 24 hours later, sample two is taken

26
Method TwoPipe Bursting Water Mains
  • When both samples have returned passed, a 14 day
    log will be posted to that pipe. (THIS PIPE IS
    NOW GOOD FOR 14 DAYS)
  • If the pipe is not installed within the 14 days,
    the process is repeated.
  • Pipe is burst into place
  • Super chlorinated swab is passed through the line
  • After removal of swab, line is flushed and
    commissioned
  • Service connections are made to the main line

27
Fort Pierce, FloridaCase Study
28
Water Main Problems
  • Received complaints regarding potable water
    clarity and low pressure concerns
  • Cast iron water mains more than 65 years old
  • New service line installations required
  • Limited working space, easement issues, high end
    homes in neighborhood, heavy traffic making open
    cut not a feasible option
  • David Mellert of FPUA contacted Murphy Pipeline
    Contractors re pipe bursting

29
Fort Pierce, Florida Case Study
  • 12,000 feet of new mains
  • Crew of 8 completed project in 2 months
  • Existing 6 cast iron pipe replaced with 6 HDPE
    pipe
  • An average of 400 feet per day was replaced
  • Estimated cost savings vs. open cut 30

30
Pre-Chlorination
  • Lines capped and disinfected with a hypochlorite
    solution
  • Pressure testing

31
Entry and Exit Pits
  • Pits dug on entry and exit end of the pipe
  • Rods passed from entry to exit pit in
    approximately 45 minutes

32
Bursting Head and Expander
  • Bursting Rig is attached to the bursting blade
    and expander
  • Pre-chlorinated and sealed HDPE pipe are attached
    to the expander

33
Hydraulic Static Pull
  • Bursting blade is drawn through the existing
    Host pipe causing it to fracture
  • Bursting expander then pushes broken pipe into
    the surrounding soil

34
Rods Recovered at Exit Pit
  • Rods are removed from the exit pit as pipe is
    pulled into place
  • Mainline connections are made and services tied
    in
  • For the next burst the exit pit becomes new entry
    pit

35
Service Re-connection
  • Small service excavations 4 x 4
  • New services installed with piercing tools
  • HDPE services are electro-fused to the main
    providing a 100 sealed connection

36
Conclusions
  • Pipe bursting potable water mains utilizing the
    pre-chlorination method is an effective method to
    open cut pipe replacement
  • Allowed upsizing in place
  • Minimized disturbance to the surrounding area

37
Conclusions
  • 12,000 feet of pipe replaced in 2 months with
    crew of 8
  • Previous FL project performed by Murphy Pipelines
    received runner up project of the year
  • Fort Pierce project received nomination for
    project of the year.

38
Thank You