Presentation to Honourable Central Electricity Regulatory Commission on Views/Suggestions on CERCs - PowerPoint PPT Presentation

About This Presentation
Title:

Presentation to Honourable Central Electricity Regulatory Commission on Views/Suggestions on CERCs

Description:

Issues as regards Open Access in Electricity Transmission & Distribution. Author: hema Created Date: 11/1/2003 5:51:35 AM Document presentation format: – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 48
Provided by: hema97
Category:

less

Transcript and Presenter's Notes

Title: Presentation to Honourable Central Electricity Regulatory Commission on Views/Suggestions on CERCs


1
Presentation toHonourable Central Electricity
Regulatory CommissiononViews/Suggestions
onCERCs Discussion Paper on Terms and Condition
of Tariff
November 12, 2003
2
Content
  • Backdrop for Tariff Fixation
  • Goals for Tariff Setting
  • Part I Broader Issues of Tariff Setting
  • Part II Views/Recommendations on Specific Issues
  • Summary

3
Backdrop for Tariff Setting
4
Capacity Addition Required and past performance
  • Huge capacity Addition Required to realize the
    vision of power for all by 2012 100,000 MW
  • Estimated investment in all sectors Rs. 900,000
    Crs
  • The Achievement in 9th Plan is lowest for all
    plans
  • The need based targets for 8th and 9th Plan were
    44,000 MW and 57,735 MW respectively. The
    Planning Commission reduced the target
    considering feasibility/resources constraints
    etc.
  • The Xth Plan target for utilities is fixed at
    41,110 MW.
  • Considering the status of various projects
    identified for commissioning in this period, it
    is unlikely that this target would be achieved,
    even to a reasonable extent
  • Accordingly, the shortages are likely to increase
    substantially

5
Changing Structure
Structure Before Electricity Act- 03 (Post
Reforms)
DISTRI- BUTION
CONSUMER
GENERA- TION
TRANSCOs (eg. Delhi Transco) (Intra-State
Transmission, Bulk Power Purchase for Licensees)
Discom 1(Licensee 1)
LicenceArea 1
GENCOs
CPSU
Discom 2(Licensee 2)
LicenceArea 2
IPPs
Pvt. Licensees
Discom n(Licensee n)
LicenceArea n
Excess Captive
?
Regulators Role
No Choice to Generating Co./Consumer, Limited
Competition
6
Changing Structure Emerging Structure Post EA
03
Generating Companies
Captive Generation Facilities
Own Generation
Transmission Network (Immediate Open Access)
Distribution Licensee 1
Distribution Licensee 2
Distribution Network (Gradual Open Access)
Own Distribution System
Licence Area
Power Traders would also be involved in some of
the transactions
Competitive, Flexible Structure enabling Choice
to Consumer
7
Goals for Tariff Setting
8
Goals of Tariff Setting
  • Huge investment required (Rs. 900,000 Crs) to
    realize the vision of Power for All by 2012
  • Investment in Power Sector to compete for
    investment in other sectors in terms of
  • Returns offered
  • Climate for investment Stable policies,
    regulatory and fiscal framework
  • The policy of allowing an attractive return
    profile may be adopted for say the next 9-12
    years and when the critical mass of investments
    which can meet the 2012 vision is achieved, Govt.
    may review it
  • This has happened in this country as well as
    abroad whenever Govts want to attract investments
    in certain sector.
  • Thus tariff-setting principles need to
    distinguish between two stages - Stage I is the
    immediate period for the next 9 12 years when
    large investments would be required to meet the
    capacity requirements of the sector and Stage II
    would be the period thereafter.

Contd
9
Goals of Tariff Setting (contd.)
  • The need for attracting investments in Stage I
    is more acute compared to Stage II and at the
    same time more difficult
  • State of the sector today, from investment point
    of view, is less favourable due to the various
    ills affecting the sector.
  • Conditions likely to improve in the next 9 12
    years as reforms are accomplished and critical
    mass is achieved
  • Case for more favourable returns in Stage I to
    attract investments.
  • Normalized returns in Stage II
  • Even in Stage I, a staggered approach to returns
    should be followed i.e., keeping in view the
    immediate need of funds, a higher return should
    be allowed for the next say 5 year period. The
    returns may then decrease in subsequent 5 year
    period and further decrease thereafter.

Contd
10
Goals of Tariff Setting (contd.)
  • Stable tariff policy framework in various stages
    and in inter-stages intervals, keeping in account
    large gestation period of power projects
  • Clearances have a long lead time (for ex. MoEF
    clearance itself requires anywhere from 18 24
    months).
  • Apart from ensuring the basic function of
    adequate cost recovery, it should ensure that
    there is enough revenue generation in the sector
    itself to partly meet the funds requirement.
  • Ultimately, tariff setting should aim at helping
    the sector in its journey of reforms
    restructuring and should facilitate the emergence
    of a financially strong, vibrant, competitive and
    investor consumer friendly sector.

11
Part ITariff Setting Broader Issue
12
Tariff Setting Broader Issues
  • Existing Practice Cost plus System
  • Discourages efficiencies
  • Financials
  • Technological
  • Operating
  • Micro Management
  • Detailed scrutiny of technology
  • Technology/Equipment selection vetting
  • Many time even capacities of sub-systems are
    analyzed
  • Highly time consuming, taking lot of Commission's
    time and resources
  • Not tuned to changing/dynamic structure
  • Enhanced participation of private sector players
  • Faster approvals (tariff etc.)

Pressing Need to move away from Cost plus System
13
Tariff Setting Across the Chain Transition
  1. Existing Structure Takes Time, lacks drivers to
    improve efficiencies
  2. Desired Structure would take time to evolve

Need for interim Structure to cut down the time
and promote efficiencies
14
Tariff Setting Interim Structure (Generation)
Interim
Existing
Regulated on Cost Plus basis
Regulated on Normative Basis
  • Steps Involved
  • (in each case)
  • Cost Scrutiny/approval
  • Financing Plan scrutiny/approval
  • Scrutiny of interest rates
  • Steps Involved (one time activity)
  • Determination of Normative Cost
  • Arriving at Normative Financing Plan
  • Fixing Normative OM Cost
  • Arriving at Normative Operating parameters

Faster approval process, uniform tariff for
similar projects Promotes efficiencies
Take time and Leads to separate tariff for
similar type of projects
Interim Structure to realize the Vision and
promote efficiency
15
Part IIViews/Recommendations on Specific Issues
16
1. Rate of Return Approach
  • Views
  • Tariff setting needs to move from a cost-plus
    approach to a normative performance based
    approach.
  • Cost-Plus approach requires detailed analysis of
    the different loans, their repayment schedules
    and other terms conditions.
  • It does not provide incentive to utility to lower
    cost of borrowings as even higher rates are
    passed through in tariff.
  • Adoption of a Return on Capital Employed (ROCE)
    approach would incentivise utilities to adopt
    more efficient means of financing so as to reduce
    its cost.
  • The ROCE may be calculated each year with
    normative cost of equity, debt and the
    debt-equity ratio.
  • Recommendation

ROCE Approach to be Adopted
17
2. Rate of Return ROCE- Cost of Debt
  • Views
  • The interest rate may be taken as lending rates
    for A rated borrower (minimum investment grade
    rating below which Banks/FIs generally do not
    lend).
  • This may work out to a spread of 3 to 3.5 over
    the base PLR, which for simplicity, may be taken
    as SBIs Long Term PLR for Infrastructure
    Projects.
  • A provision also need to be made for factoring in
    other costs of raising debt-finance viz. upfront
    fees, etc.
  • Generally, lenders stipulate a call option in the
    loans which entitles them to review the rates of
    interest at regular period of time after
    disbursement of the loan (say every 5 years). No
    corresponding put option to the borrower.
  • If interest rates in the economy go up, lenders
    may require enhancement of the interest rate
    applicable to the loan also.
  • It would pose significant interest rate risk for
    the borrower which no borrower is in a position
    to take.
  • Accordingly, there should be a provision for a
    mid-term review of tariff should the interest
    rates in the economy rise by say more than 3.
  • Recommendation

SBI PLR 3.5 (on pre-tax basis), with provision
for Mid-Term Review to be Adopted
18
3. Rate of Return ROCE- Cost of Equity
  • Views
  • Pressing need to attract investments in the
    sector and generate internal resources for huge
    capacity additions
  • Returns, adjusted for Risk profile, to be
    attractive vis-à-vis competitive sectors for
    investments of the desired amount to flow in.
  • The returns available to the investors should
    therefore be the opportunity cost of funds to the
    investor and not linked to interest rates in the
    economy.
  • Against competing investment avenues, a cost of
    equity lesser than 16 would be definitely
    unattractive.
  • In developed economies where there is no acute
    investment program, returns are linked to
    interest rates.
  • Taking 16 as the base minimum ROE required, CAPM
    model may be used to see if a higher equity
    return is justifiable.
  • The higher of ROE derived through the CAPM model
    and 16 should be used as the cost of equity.
  • Recommendation

ROE of 16 (post-tax) to be continued at least
for Xth and XIth Plan Period
19
4. ROCE- Debt Equity Ratio
  • Views
  • The generally followed a debt-equity norm of
    7030 in the past needs to be relooked in view of
    changing structure.
  • From long-term assured off-take arrangements and
    elaborate payment security structures to
    liberalized competitive market place
  • Less possibility of payment security structures
    and even if it is, experience of IPPs under
    operation shows how ineffective they are in
    actual practice.
  • This would have the effect of slightly raising
    the risk profile of the investments.
    Additionally, the amount of investments required
    in the sector in the next 8-9 years also has to
    be seen.
  • Considering the above, lenders may not be willing
    to lend at the same 7030 debt-equity ratio and
    may insist on a better debt-equity ratio.
  • Moreover, credit profile of the borrower would
    also determine the debt-equity ratio being
    offered to him. For a majority of SEBs with poor
    financial health and a track-record of defaults
    on debt obligations, lenders may definitely like
    to insist on better equity cushion.
  • Having determined these norms and approved tariff
    based on these norms, Commission should not look
    into what is the actual debt-equity ratio or the
    cost of borrowings for the company and the same
    should be left to the investors.
  • Recommendation

For Calculation of ROCE, DebtEquity Ratio of
5050 to be adopted
20
5. ROCE to be fixed or dynamic and fixed every
year?
  • Views
  • The investment decision is taken based on
    principles of ROCE allowed at the approval stage
  • Changing principles of ROCE every year would lead
    to regulatory etc. uncertainties, which needs to
    be avoided
  • If principles of ROCE norms is required to be
    changed, the revised norm should not be made
    applicable for fully developed/under construction
    or operation projects.
  • In competitively bid project, the tariff offered
    by the bidder remains the same through the
    project life irrespective of change in tariff
    norms thereafter
  • Recommendation

It principles should be fixed for project life
21
6. Tax ROE to be Pre or Post Tax or increase ROE
by 0.5 to avoid pass through of Income Tax?
  • Views
  • In order to attract investment in the sector etc.
    16 ROE to be on Post Tax Basis.
  • However, to avoid regular/yearly scrutiny, ROE
    can be specified on pre tax basis by suitably
    grossing it by effective tax rate over the
    project life
  • Effective Tax rate to be computed by considering
    Section 80 IA benefit and MAT rate and initial
    depreciation shield.
  • At current tax laws, the effective tax rate for a
    coal based power plant with a life of 25 years is
    21.13 and that for a gas based station is
    16.41.
  • The ROCE would thus need to be enhanced by the
    above effective tax rates to make it on a
    pre-tax basis.
  • To be adjusted for change in law/rate rates
  • Recommendation

ROE to be Post Tax or to make it pre-tax,
suitably grossed up to effective tax rate
22
7. Whether Additional Capitalization to be
allowed?
  • Views
  • Capital costs for stations various type of power
    plants should be based on laid down norms i.e, a
    fixed amount for various type of projects and
    considering the size of plant, economies of
    scale, etc. Thus for a gas based project, a
    normative cost of Rs. 3 crores/MW may be approved
    whereas for a coal based station, Rs. 4 crores
    per MW may be stipulated as the norm for capital
    cost.
  • Once these norms are set, all cost components in
    tariff should be calculated w.r.t. these norms
    and there should be no linkage with the actual
    capital cost of the plant.
  • All cost over-runs/savings w.r.t. this normative
    cost should be to the account of the developer
  • Recommendation

Provision for mid-term review, if during
construction stage, there is significant
variation in tax laws impacting project cost
23
8. Rate Base to be from assets side or liability
side?
  • Views
  • The calculation of rate base should ensure that
    the tariff allows a return component which covers
    both ROE as well as interest cost of debt.
  • There are various options for calculating the
    rate base from the asset side liability side.
  • The most prudent option would be one which allows
    flexibility to the developer, adequately covers
    his returns interest cost of debt and at the
    same time does not lead to a sharp increase in
    retail tariffs.
  • As suggested earlier, Normative Approach should
    be adopted in this case also.
  • The rate base, should take into account its
    reduction due to repayment of loan etc.
  • Recommendation
  1. Initial Rate Base Should be Normative Capital
    Cost
  2. This may be decreased by 5 p.a., up to 50 of
    original, in view of debt-equity ratio of 5050

24
9. Basis of Capital Cost Normative or Actual
  • Views
  • Taking actual cost as on COD would lead to
    different tariffs for similar projects
  • Further, it would increase the steps required to
    fix the tariffs
  • Recommendations
  1. It should be on normative basis (due
    consideration to type of project, technology,
    economies of scale etc.)
  2. There should be provision for mid-term review to
    account for any change in law/tax rates

25
10. Treatment of Initial Spares in Project Cost
  • Views
  • In the existing tariff-setting methodology,
    initial spares are included as a part of the
    project cost.
  • Further, there is a linkage between initial
    spares and calculation of maintenance spares for
    working capital purposes)
  • Recommendations
  1. Existing practice of including cost of initial
    spares in project cost to be continued. Normative
    project cost to be suitably adjusted for initial
    spares
  2. There should not be any linkage between initial
    spares and calculation of maintenance spares

26
11. Foreign Exchange Variation
  • Views
  • In a normative based tariff setting methodology,
    actual mode and mix of financing would not be of
    any issue
  • Developer to optimize the financing package
  • Recommendation

In view of suggestion for normative parameters
for tariff fixation and return on ROCE, this
issue does not arise
27
12. Working Capital Issues
  • Views
  • Existing norms are based on prudent principles
    and well accepted
  • Giving Interest on Working Capital along with
    ROCE would lead to its under recovery due to
    reduction in capital base over the period
  • Interest rate needs to be uniform (charged to
    A rated borrower)
  • Recommendations
  1. Existing Norms to be retained
  2. Interest on Work. Cap to be separate component of
    tariff
  3. Interest Rate to be SBI PLR 3

28
13. OM Expenses (Normative/Actual? escalation)
  • Views
  • OM cost should be on a normative basis as a
    given percentage of the normative project cost.
  • Linking OM expenses to actual project
    cost/expenses leads to wide variation for similar
    type of projects.
  • The actual OM expenses (including Insurance) are
    found be more than allowed in existing norms,
    particularly for gas based projects.
  • As regards year-on-year escalation factor, a
    suitable weighted average of WPI and CPI may be
    used (say 60 WPI and 40 CPI).
  • Recommendation

OM expenses (first year) allowed should be 4.25
for Gas Stations and 3 for Coal Stations of
Normative Project Cost
29
14. Depreciation Rate
  • Views
  • Depreciation does not serve the purpose of loan
    repayment only. It also serves to generate
    additional resources which can be used for future
    creation of capacity.
  • Realizing this, Govt. of India had also increased
    rates of depreciation in March, 1994.
  • However, in a normative ROCE model, linking of
    depreciation rates to loan repayment exactly may
    not also be possible as there is no concept of
    actual equity or debt separation in the capital
    base.
  • Recommendation

Retain Depreciation Rates as notified by MOP in
1994 (7.84 for coal 8.24 for gas stations, at
least for Xth and XIth Plan period
30
15. Depreciation Other Issues
  • Views
  • The calculation of depreciation amount every year
    should be done on the basis of historic normative
    project cost (Not on economic/replacement cost).
  •  Further, sector needs huge investment for
    capacity addition.
  • Internal resource is key source of investment
    financing
  • Recommendation

Depreciation to be calculated on normative cost
and should generate some surplus (over loan
repayment) for further investment
31
16. Operational Norms for Thermal Stations
  • Views
  • The fixation of operational norms (station heat
    rate, secondary fuel consumption and auxiliary
    consumption) should take into account the
    relative performance of a wide cross-section of
    utilities in the country from both central
    state sector as well as the private sector so
    that the norms are achievable by all utilities
    which put in reasonably efficient efforts.
  • The norms so fixed should also act as reasonable
    benchmarks for utilities to improve whose
    performance is below the norms.
  • The existing practice of comparing norms against
    actuals and allowing the lower of the two
    discourages efficiency improvement measures.
  • During stabilization period, norms should be
    relaxed.
  • Recommendation

Norms to be based on performance of wide-section
of utilities and tariff to be based on normative
parameters only
32
17. Norms for Target Availability
  • Views
  • The norms should take into account the relative
    performance of a wide cross-section of utilities.
  • The average operating PLF/availability for all
    generating stations put together in the country
    stands at about 72, against stipulated norm of
    80.
  • Wide-gap between the norms and the actual ground
    level performance
  • The norms for target availability should thus be
    fixed at the national average plus say 2-3.
  • Alternatively, if the threshold availability
    level is being raised to 80, then the ROE should
    also be enhanced from 16 suitably to reflect the
    higher risk carried by the project company.
  • Recommendation

Target Availability should be 75 for recovery of
fixed charges including ROE _at_ 16
33
18. Incentive (Linked to availability or PLF? )
  • Views
  • PLF depends on despatch of the plant, which is
    dictated by customer beneficiaries and not the
    developer
  • Maintaining high availability is important for
    grid stability and should be rewarded
  • Further, linking of incentives to PLF has a
    number of other shortcomings.
  • Non-merit operation of grid
  • Recommendation

Incentive should be linked to Availability
34
19. Development Surcharge
  • Views
  • Development Surcharge was allowed in tariff to
    central sector utilities as a means of gathering
    surplus funds for future capacity additions.
  • In a competitive market place, there is no reason
    why Govt. owned utilities should derive an
    advantage of securing cashflows for future
    investments by way of statutory levies/surcharge.
  • If the Govt. so desires, the funds required for
    setting up new capacity should be given by way of
    planned budgetary allocations rather than collect
    the same by way of a surcharge.
  • The surplus funds for future capacity addition
    can be generated through a higher rate of
    depreciation etc. which would then be uniformly
    available to all utilities and not to central
    sector utilities only.
  • Recommendation

Development Surcharge should not be specific to
fund investment program of Central Generating
Stations
35
Transition Period Support Need for
Cess/Surcharge
  • Distribution Sector Transition Phase Need for
    Support
  • Low retail tariff elasticity
  • Need to keep retail tariffs affordable for all
    consumer categories
  • This may be ensured by
  • Reducing losses
  • Tariff rationalization
  • Operational/organizational efficiency improvement
  • However, these measures would take time
  • During this period sustainability of the utility
    to be ensured
  • Therefore support required to bridge the gap
    Actual tariff minus regulated tariff
  • Most State Govts do not have resources to bridge
    this gap major constraint to distribution
    privatization reforms
  • CERC requested to recommend to Central Govt. to
    levy a cess on all power sold in the country to
    meet transitional period support
  • Surcharge Collection to be administered by the
    Excise Machinery.

36
Transition Phase Need for Support (contd.)
Revenue Gap Govt. Support
?
Without reforms perpetual drain on Govt.
resources
With reforms
Transition Period
Reforms to release Govt. funds for priority
sectors
37
20. Tariff Norms Review Period
  • Views
  • Tariff policy framework should be stable enough
    for a reasonable period of time
  • keeping in view the development period of
    projects
  • However, periodic review is necessary
  • Changes in cost levels in economy, technology,
    equipment prices
  • Revised norms to be applicable for new projects
    only
  • For fully developed/set-up projects, tariff
    principles once set, should continue for the
    entire life of the plant.
  • The investment decision and financing is based on
    prevalent norms
  • The apprehension of customers that escalation
    component (viz. OM cost) may become very high
    compared to actuals can be taken care of better
    by suitably determining the escalation factor
    with weights linked to various indices of costs
    in the economy.
  • Recommendation

Tariff norms may be reviewed once in 5 years, to
be applicable for new projects only. No change
for fully developed/operating projects
38
21. Regional Tariff (i.e. Pooled Tariff for CPSU)
  • Views
  • The need for pooled generation tariffs is not
    clear.
  • Generation tariffs should be on station-wise
    basis and not pooled basis.
  • Pooled tariff concept is generally applicable for
    distribution utilities when they procure bulk
    power and not for generation companies.
  • The pooled tariff concept for generating
    companies can work specifically in a
    short-term/spot sales scenario.
  • In case of long-term contracts, it would become
    very difficult to implement a provision whereby
    tariff gets upwardly revised every time a new
    incremental capacity is set up.
  • Recommendation

Tariffs should be stationwise
39
22. Peak/Off Peak Tariff in Bulk Generation
  • Views (whether should be introduced?)
  • The concept is in the right direction.
  • Compels distribution companies to manage load
    curves in a more efficient manner
  • Ensures higher availability of generating
    capacity during peak hours
  • reduce congestion on transmission lines to some
    extent
  • However for it to be really effective,
    differential tariffs based on time of day etc.
    should also be implemented at the downstream
    level i.e., transmission distribution business.
  • If this is not the case, the distribution
    licensee/supplier would end up getting squeezed
    by the higher peak bulk tariff rates which he
    would not be able to pass to the retail
    consumers.
  • There should be a clear road-map for appropriate
    TOD metering/retail tariff fixing, etc.
  • Recommendation

Differential Tariffs should be introduced
40
23. Declared Capacity Auxiliary Consumption
  • Views/Basis for Recommendation
  • Existing definitions are well accepted and
    understood in the Sector
  • Recommendation

No need to change the definitions
41
Goals for Tariff Setting Other Issues
42
Need for Intra State ABT
  • Currently applicable only to Central sector
    generators and beneficiaries who are directly
    connected to and are a player on the regional
    grids (Inter State only).
  • The advantages not being completely utilized by
    the entire power sector
  • On the intra-state level, a significant surplus
    capacity exists with various generating companies
    CPPs which at present is not being optimally
    utilized.
  • Moreover, a number of state generating stations
    still have single part tariff, which is not in
    line with merit order regime. Such generating
    stations would be asked to back down even though
    on a variable-cost based merit order system they
    would have been fully dispatched.
  • It is also necessary that the distribution
    utilities become more accountable in their load
    management processes by assessing consumer demand
    more accurately and planning their load shedding
    schedules judiciously.

43
Need for Intra State ABT
  • Unbundling of SEBs would increase no. of players
    managing the load in the system.
  • Unless a mechanism is put into place at the
    intra-state level to cover these distribution
    companies also under ABT, the loop would not be
    closed and the actual implementation of ABT would
    not be complete.
  • Thus, implementation of ABT at the intra-state
    level would free up idle generating capacity
    leading to meeting of more consumer demand,
    ensure better load management by the distribution
    companies, boost bilateral trading, etc.
  • ABT with a self contained discipline mechanism
    would enable better and reliable grid operations

44
Advantages of Intra State ABT
  • The experience of implementing ABT in the country
    till date has shows following major advantages
  • The UI charge in ABT results in better grid
    discipline and grid security by limiting grid
    frequency excursions within a manageable range.
  • Improvement in grid voltage levels leading to
    reduction in transmission losses and enhancement
    of transmission capacity.
  • Maximization of generation during peak-hours and
    backing down of generation during off-peak hours
    as per merit order. ABT facilitates Merit Order
    Dispatch as the fixed cost payable based on
    capacity allocated becomes a sunk cost and
    dispatch of plants is based on variable costs.
  • The two-part tariff concept of ABT presents an
    inherent platform for bilateral trading.
  • Improvement in performance of power plants by
    reducing trippings and long term damage.
  • Improvement in commercial dealings with reduction
    in year-end adhoc adjustments and consequent
    disputes.

45
Summary
46
Summary Tariff Setting Goals
  • Tariff setting to take into account changing
    structure of power sector
  • It should lead to faster approval process
  • Normative cost etc. approach
  • It should promote efficiencies

47
Thank you
Write a Comment
User Comments (0)
About PowerShow.com