Title: Presentation to Honourable Central Electricity Regulatory Commission on Views/Suggestions on CERCs
1Presentation toHonourable Central Electricity
Regulatory CommissiononViews/Suggestions
onCERCs Discussion Paper on Terms and Condition
of Tariff
November 12, 2003
2Content
- Backdrop for Tariff Fixation
- Goals for Tariff Setting
- Part I Broader Issues of Tariff Setting
- Part II Views/Recommendations on Specific Issues
- Summary
3Backdrop for Tariff Setting
4Capacity Addition Required and past performance
- Huge capacity Addition Required to realize the
vision of power for all by 2012 100,000 MW - Estimated investment in all sectors Rs. 900,000
Crs
- The Achievement in 9th Plan is lowest for all
plans - The need based targets for 8th and 9th Plan were
44,000 MW and 57,735 MW respectively. The
Planning Commission reduced the target
considering feasibility/resources constraints
etc. - The Xth Plan target for utilities is fixed at
41,110 MW. - Considering the status of various projects
identified for commissioning in this period, it
is unlikely that this target would be achieved,
even to a reasonable extent - Accordingly, the shortages are likely to increase
substantially
5Changing Structure
Structure Before Electricity Act- 03 (Post
Reforms)
DISTRI- BUTION
CONSUMER
GENERA- TION
TRANSCOs (eg. Delhi Transco) (Intra-State
Transmission, Bulk Power Purchase for Licensees)
Discom 1(Licensee 1)
LicenceArea 1
GENCOs
CPSU
Discom 2(Licensee 2)
LicenceArea 2
IPPs
Pvt. Licensees
Discom n(Licensee n)
LicenceArea n
Excess Captive
?
Regulators Role
No Choice to Generating Co./Consumer, Limited
Competition
6Changing Structure Emerging Structure Post EA
03
Generating Companies
Captive Generation Facilities
Own Generation
Transmission Network (Immediate Open Access)
Distribution Licensee 1
Distribution Licensee 2
Distribution Network (Gradual Open Access)
Own Distribution System
Licence Area
Power Traders would also be involved in some of
the transactions
Competitive, Flexible Structure enabling Choice
to Consumer
7Goals for Tariff Setting
8Goals of Tariff Setting
- Huge investment required (Rs. 900,000 Crs) to
realize the vision of Power for All by 2012 - Investment in Power Sector to compete for
investment in other sectors in terms of - Returns offered
- Climate for investment Stable policies,
regulatory and fiscal framework - The policy of allowing an attractive return
profile may be adopted for say the next 9-12
years and when the critical mass of investments
which can meet the 2012 vision is achieved, Govt.
may review it - This has happened in this country as well as
abroad whenever Govts want to attract investments
in certain sector. - Thus tariff-setting principles need to
distinguish between two stages - Stage I is the
immediate period for the next 9 12 years when
large investments would be required to meet the
capacity requirements of the sector and Stage II
would be the period thereafter.
Contd
9Goals of Tariff Setting (contd.)
- The need for attracting investments in Stage I
is more acute compared to Stage II and at the
same time more difficult - State of the sector today, from investment point
of view, is less favourable due to the various
ills affecting the sector. - Conditions likely to improve in the next 9 12
years as reforms are accomplished and critical
mass is achieved - Case for more favourable returns in Stage I to
attract investments. - Normalized returns in Stage II
- Even in Stage I, a staggered approach to returns
should be followed i.e., keeping in view the
immediate need of funds, a higher return should
be allowed for the next say 5 year period. The
returns may then decrease in subsequent 5 year
period and further decrease thereafter.
Contd
10Goals of Tariff Setting (contd.)
- Stable tariff policy framework in various stages
and in inter-stages intervals, keeping in account
large gestation period of power projects - Clearances have a long lead time (for ex. MoEF
clearance itself requires anywhere from 18 24
months). - Apart from ensuring the basic function of
adequate cost recovery, it should ensure that
there is enough revenue generation in the sector
itself to partly meet the funds requirement. - Ultimately, tariff setting should aim at helping
the sector in its journey of reforms
restructuring and should facilitate the emergence
of a financially strong, vibrant, competitive and
investor consumer friendly sector.
11Part ITariff Setting Broader Issue
12Tariff Setting Broader Issues
- Existing Practice Cost plus System
- Discourages efficiencies
- Financials
- Technological
- Operating
- Micro Management
- Detailed scrutiny of technology
- Technology/Equipment selection vetting
- Many time even capacities of sub-systems are
analyzed - Highly time consuming, taking lot of Commission's
time and resources - Not tuned to changing/dynamic structure
- Enhanced participation of private sector players
- Faster approvals (tariff etc.)
Pressing Need to move away from Cost plus System
13Tariff Setting Across the Chain Transition
- Existing Structure Takes Time, lacks drivers to
improve efficiencies - Desired Structure would take time to evolve
Need for interim Structure to cut down the time
and promote efficiencies
14Tariff Setting Interim Structure (Generation)
Interim
Existing
Regulated on Cost Plus basis
Regulated on Normative Basis
- Steps Involved
- (in each case)
- Cost Scrutiny/approval
- Financing Plan scrutiny/approval
- Scrutiny of interest rates
- Steps Involved (one time activity)
- Determination of Normative Cost
- Arriving at Normative Financing Plan
- Fixing Normative OM Cost
- Arriving at Normative Operating parameters
Faster approval process, uniform tariff for
similar projects Promotes efficiencies
Take time and Leads to separate tariff for
similar type of projects
Interim Structure to realize the Vision and
promote efficiency
15Part IIViews/Recommendations on Specific Issues
161. Rate of Return Approach
- Views
- Tariff setting needs to move from a cost-plus
approach to a normative performance based
approach. - Cost-Plus approach requires detailed analysis of
the different loans, their repayment schedules
and other terms conditions. - It does not provide incentive to utility to lower
cost of borrowings as even higher rates are
passed through in tariff. - Adoption of a Return on Capital Employed (ROCE)
approach would incentivise utilities to adopt
more efficient means of financing so as to reduce
its cost. - The ROCE may be calculated each year with
normative cost of equity, debt and the
debt-equity ratio. - Recommendation
ROCE Approach to be Adopted
172. Rate of Return ROCE- Cost of Debt
- Views
- The interest rate may be taken as lending rates
for A rated borrower (minimum investment grade
rating below which Banks/FIs generally do not
lend). - This may work out to a spread of 3 to 3.5 over
the base PLR, which for simplicity, may be taken
as SBIs Long Term PLR for Infrastructure
Projects. - A provision also need to be made for factoring in
other costs of raising debt-finance viz. upfront
fees, etc. - Generally, lenders stipulate a call option in the
loans which entitles them to review the rates of
interest at regular period of time after
disbursement of the loan (say every 5 years). No
corresponding put option to the borrower. - If interest rates in the economy go up, lenders
may require enhancement of the interest rate
applicable to the loan also. - It would pose significant interest rate risk for
the borrower which no borrower is in a position
to take. - Accordingly, there should be a provision for a
mid-term review of tariff should the interest
rates in the economy rise by say more than 3. - Recommendation
SBI PLR 3.5 (on pre-tax basis), with provision
for Mid-Term Review to be Adopted
183. Rate of Return ROCE- Cost of Equity
- Views
- Pressing need to attract investments in the
sector and generate internal resources for huge
capacity additions - Returns, adjusted for Risk profile, to be
attractive vis-à-vis competitive sectors for
investments of the desired amount to flow in. - The returns available to the investors should
therefore be the opportunity cost of funds to the
investor and not linked to interest rates in the
economy. - Against competing investment avenues, a cost of
equity lesser than 16 would be definitely
unattractive. - In developed economies where there is no acute
investment program, returns are linked to
interest rates. - Taking 16 as the base minimum ROE required, CAPM
model may be used to see if a higher equity
return is justifiable. - The higher of ROE derived through the CAPM model
and 16 should be used as the cost of equity. - Recommendation
ROE of 16 (post-tax) to be continued at least
for Xth and XIth Plan Period
194. ROCE- Debt Equity Ratio
- Views
- The generally followed a debt-equity norm of
7030 in the past needs to be relooked in view of
changing structure. - From long-term assured off-take arrangements and
elaborate payment security structures to
liberalized competitive market place - Less possibility of payment security structures
and even if it is, experience of IPPs under
operation shows how ineffective they are in
actual practice. - This would have the effect of slightly raising
the risk profile of the investments.
Additionally, the amount of investments required
in the sector in the next 8-9 years also has to
be seen. - Considering the above, lenders may not be willing
to lend at the same 7030 debt-equity ratio and
may insist on a better debt-equity ratio. - Moreover, credit profile of the borrower would
also determine the debt-equity ratio being
offered to him. For a majority of SEBs with poor
financial health and a track-record of defaults
on debt obligations, lenders may definitely like
to insist on better equity cushion. - Having determined these norms and approved tariff
based on these norms, Commission should not look
into what is the actual debt-equity ratio or the
cost of borrowings for the company and the same
should be left to the investors. - Recommendation
For Calculation of ROCE, DebtEquity Ratio of
5050 to be adopted
205. ROCE to be fixed or dynamic and fixed every
year?
- Views
- The investment decision is taken based on
principles of ROCE allowed at the approval stage - Changing principles of ROCE every year would lead
to regulatory etc. uncertainties, which needs to
be avoided - If principles of ROCE norms is required to be
changed, the revised norm should not be made
applicable for fully developed/under construction
or operation projects. - In competitively bid project, the tariff offered
by the bidder remains the same through the
project life irrespective of change in tariff
norms thereafter - Recommendation
It principles should be fixed for project life
216. Tax ROE to be Pre or Post Tax or increase ROE
by 0.5 to avoid pass through of Income Tax?
- Views
- In order to attract investment in the sector etc.
16 ROE to be on Post Tax Basis. - However, to avoid regular/yearly scrutiny, ROE
can be specified on pre tax basis by suitably
grossing it by effective tax rate over the
project life - Effective Tax rate to be computed by considering
Section 80 IA benefit and MAT rate and initial
depreciation shield. - At current tax laws, the effective tax rate for a
coal based power plant with a life of 25 years is
21.13 and that for a gas based station is
16.41. - The ROCE would thus need to be enhanced by the
above effective tax rates to make it on a
pre-tax basis. - To be adjusted for change in law/rate rates
- Recommendation
ROE to be Post Tax or to make it pre-tax,
suitably grossed up to effective tax rate
227. Whether Additional Capitalization to be
allowed?
- Views
- Capital costs for stations various type of power
plants should be based on laid down norms i.e, a
fixed amount for various type of projects and
considering the size of plant, economies of
scale, etc. Thus for a gas based project, a
normative cost of Rs. 3 crores/MW may be approved
whereas for a coal based station, Rs. 4 crores
per MW may be stipulated as the norm for capital
cost. - Once these norms are set, all cost components in
tariff should be calculated w.r.t. these norms
and there should be no linkage with the actual
capital cost of the plant. - All cost over-runs/savings w.r.t. this normative
cost should be to the account of the developer - Recommendation
Provision for mid-term review, if during
construction stage, there is significant
variation in tax laws impacting project cost
238. Rate Base to be from assets side or liability
side?
- Views
- The calculation of rate base should ensure that
the tariff allows a return component which covers
both ROE as well as interest cost of debt. - There are various options for calculating the
rate base from the asset side liability side. - The most prudent option would be one which allows
flexibility to the developer, adequately covers
his returns interest cost of debt and at the
same time does not lead to a sharp increase in
retail tariffs. - As suggested earlier, Normative Approach should
be adopted in this case also. - The rate base, should take into account its
reduction due to repayment of loan etc. - Recommendation
- Initial Rate Base Should be Normative Capital
Cost - This may be decreased by 5 p.a., up to 50 of
original, in view of debt-equity ratio of 5050
249. Basis of Capital Cost Normative or Actual
- Views
- Taking actual cost as on COD would lead to
different tariffs for similar projects - Further, it would increase the steps required to
fix the tariffs - Recommendations
- It should be on normative basis (due
consideration to type of project, technology,
economies of scale etc.) - There should be provision for mid-term review to
account for any change in law/tax rates
2510. Treatment of Initial Spares in Project Cost
- Views
- In the existing tariff-setting methodology,
initial spares are included as a part of the
project cost. - Further, there is a linkage between initial
spares and calculation of maintenance spares for
working capital purposes) - Recommendations
- Existing practice of including cost of initial
spares in project cost to be continued. Normative
project cost to be suitably adjusted for initial
spares - There should not be any linkage between initial
spares and calculation of maintenance spares
2611. Foreign Exchange Variation
- Views
- In a normative based tariff setting methodology,
actual mode and mix of financing would not be of
any issue - Developer to optimize the financing package
- Recommendation
In view of suggestion for normative parameters
for tariff fixation and return on ROCE, this
issue does not arise
2712. Working Capital Issues
- Views
- Existing norms are based on prudent principles
and well accepted - Giving Interest on Working Capital along with
ROCE would lead to its under recovery due to
reduction in capital base over the period - Interest rate needs to be uniform (charged to
A rated borrower) - Recommendations
- Existing Norms to be retained
- Interest on Work. Cap to be separate component of
tariff - Interest Rate to be SBI PLR 3
2813. OM Expenses (Normative/Actual? escalation)
- Views
- OM cost should be on a normative basis as a
given percentage of the normative project cost. - Linking OM expenses to actual project
cost/expenses leads to wide variation for similar
type of projects. - The actual OM expenses (including Insurance) are
found be more than allowed in existing norms,
particularly for gas based projects. - As regards year-on-year escalation factor, a
suitable weighted average of WPI and CPI may be
used (say 60 WPI and 40 CPI). - Recommendation
OM expenses (first year) allowed should be 4.25
for Gas Stations and 3 for Coal Stations of
Normative Project Cost
2914. Depreciation Rate
- Views
- Depreciation does not serve the purpose of loan
repayment only. It also serves to generate
additional resources which can be used for future
creation of capacity. - Realizing this, Govt. of India had also increased
rates of depreciation in March, 1994. - However, in a normative ROCE model, linking of
depreciation rates to loan repayment exactly may
not also be possible as there is no concept of
actual equity or debt separation in the capital
base. - Recommendation
Retain Depreciation Rates as notified by MOP in
1994 (7.84 for coal 8.24 for gas stations, at
least for Xth and XIth Plan period
3015. Depreciation Other Issues
- Views
- The calculation of depreciation amount every year
should be done on the basis of historic normative
project cost (Not on economic/replacement cost). - Further, sector needs huge investment for
capacity addition. - Internal resource is key source of investment
financing - Recommendation
Depreciation to be calculated on normative cost
and should generate some surplus (over loan
repayment) for further investment
3116. Operational Norms for Thermal Stations
- Views
- The fixation of operational norms (station heat
rate, secondary fuel consumption and auxiliary
consumption) should take into account the
relative performance of a wide cross-section of
utilities in the country from both central
state sector as well as the private sector so
that the norms are achievable by all utilities
which put in reasonably efficient efforts. - The norms so fixed should also act as reasonable
benchmarks for utilities to improve whose
performance is below the norms. - The existing practice of comparing norms against
actuals and allowing the lower of the two
discourages efficiency improvement measures. - During stabilization period, norms should be
relaxed. - Recommendation
Norms to be based on performance of wide-section
of utilities and tariff to be based on normative
parameters only
3217. Norms for Target Availability
- Views
- The norms should take into account the relative
performance of a wide cross-section of utilities. - The average operating PLF/availability for all
generating stations put together in the country
stands at about 72, against stipulated norm of
80. - Wide-gap between the norms and the actual ground
level performance - The norms for target availability should thus be
fixed at the national average plus say 2-3. - Alternatively, if the threshold availability
level is being raised to 80, then the ROE should
also be enhanced from 16 suitably to reflect the
higher risk carried by the project company. - Recommendation
Target Availability should be 75 for recovery of
fixed charges including ROE _at_ 16
3318. Incentive (Linked to availability or PLF? )
- Views
- PLF depends on despatch of the plant, which is
dictated by customer beneficiaries and not the
developer - Maintaining high availability is important for
grid stability and should be rewarded - Further, linking of incentives to PLF has a
number of other shortcomings. - Non-merit operation of grid
- Recommendation
Incentive should be linked to Availability
3419. Development Surcharge
- Views
- Development Surcharge was allowed in tariff to
central sector utilities as a means of gathering
surplus funds for future capacity additions. - In a competitive market place, there is no reason
why Govt. owned utilities should derive an
advantage of securing cashflows for future
investments by way of statutory levies/surcharge. - If the Govt. so desires, the funds required for
setting up new capacity should be given by way of
planned budgetary allocations rather than collect
the same by way of a surcharge. - The surplus funds for future capacity addition
can be generated through a higher rate of
depreciation etc. which would then be uniformly
available to all utilities and not to central
sector utilities only. - Recommendation
Development Surcharge should not be specific to
fund investment program of Central Generating
Stations
35Transition Period Support Need for
Cess/Surcharge
- Distribution Sector Transition Phase Need for
Support - Low retail tariff elasticity
- Need to keep retail tariffs affordable for all
consumer categories - This may be ensured by
- Reducing losses
- Tariff rationalization
- Operational/organizational efficiency improvement
- However, these measures would take time
- During this period sustainability of the utility
to be ensured - Therefore support required to bridge the gap
Actual tariff minus regulated tariff - Most State Govts do not have resources to bridge
this gap major constraint to distribution
privatization reforms - CERC requested to recommend to Central Govt. to
levy a cess on all power sold in the country to
meet transitional period support - Surcharge Collection to be administered by the
Excise Machinery.
36Transition Phase Need for Support (contd.)
Revenue Gap Govt. Support
?
Without reforms perpetual drain on Govt.
resources
With reforms
Transition Period
Reforms to release Govt. funds for priority
sectors
3720. Tariff Norms Review Period
- Views
- Tariff policy framework should be stable enough
for a reasonable period of time - keeping in view the development period of
projects - However, periodic review is necessary
- Changes in cost levels in economy, technology,
equipment prices - Revised norms to be applicable for new projects
only - For fully developed/set-up projects, tariff
principles once set, should continue for the
entire life of the plant. - The investment decision and financing is based on
prevalent norms - The apprehension of customers that escalation
component (viz. OM cost) may become very high
compared to actuals can be taken care of better
by suitably determining the escalation factor
with weights linked to various indices of costs
in the economy. - Recommendation
Tariff norms may be reviewed once in 5 years, to
be applicable for new projects only. No change
for fully developed/operating projects
3821. Regional Tariff (i.e. Pooled Tariff for CPSU)
- Views
- The need for pooled generation tariffs is not
clear. - Generation tariffs should be on station-wise
basis and not pooled basis. - Pooled tariff concept is generally applicable for
distribution utilities when they procure bulk
power and not for generation companies. - The pooled tariff concept for generating
companies can work specifically in a
short-term/spot sales scenario. - In case of long-term contracts, it would become
very difficult to implement a provision whereby
tariff gets upwardly revised every time a new
incremental capacity is set up. - Recommendation
Tariffs should be stationwise
3922. Peak/Off Peak Tariff in Bulk Generation
- Views (whether should be introduced?)
- The concept is in the right direction.
- Compels distribution companies to manage load
curves in a more efficient manner - Ensures higher availability of generating
capacity during peak hours - reduce congestion on transmission lines to some
extent - However for it to be really effective,
differential tariffs based on time of day etc.
should also be implemented at the downstream
level i.e., transmission distribution business.
- If this is not the case, the distribution
licensee/supplier would end up getting squeezed
by the higher peak bulk tariff rates which he
would not be able to pass to the retail
consumers. - There should be a clear road-map for appropriate
TOD metering/retail tariff fixing, etc. - Recommendation
Differential Tariffs should be introduced
4023. Declared Capacity Auxiliary Consumption
- Views/Basis for Recommendation
- Existing definitions are well accepted and
understood in the Sector - Recommendation
No need to change the definitions
41Goals for Tariff Setting Other Issues
42Need for Intra State ABT
- Currently applicable only to Central sector
generators and beneficiaries who are directly
connected to and are a player on the regional
grids (Inter State only). - The advantages not being completely utilized by
the entire power sector - On the intra-state level, a significant surplus
capacity exists with various generating companies
CPPs which at present is not being optimally
utilized. - Moreover, a number of state generating stations
still have single part tariff, which is not in
line with merit order regime. Such generating
stations would be asked to back down even though
on a variable-cost based merit order system they
would have been fully dispatched. - It is also necessary that the distribution
utilities become more accountable in their load
management processes by assessing consumer demand
more accurately and planning their load shedding
schedules judiciously.
43Need for Intra State ABT
- Unbundling of SEBs would increase no. of players
managing the load in the system. - Unless a mechanism is put into place at the
intra-state level to cover these distribution
companies also under ABT, the loop would not be
closed and the actual implementation of ABT would
not be complete. - Thus, implementation of ABT at the intra-state
level would free up idle generating capacity
leading to meeting of more consumer demand,
ensure better load management by the distribution
companies, boost bilateral trading, etc. - ABT with a self contained discipline mechanism
would enable better and reliable grid operations
44Advantages of Intra State ABT
- The experience of implementing ABT in the country
till date has shows following major advantages - The UI charge in ABT results in better grid
discipline and grid security by limiting grid
frequency excursions within a manageable range. - Improvement in grid voltage levels leading to
reduction in transmission losses and enhancement
of transmission capacity. - Maximization of generation during peak-hours and
backing down of generation during off-peak hours
as per merit order. ABT facilitates Merit Order
Dispatch as the fixed cost payable based on
capacity allocated becomes a sunk cost and
dispatch of plants is based on variable costs. - The two-part tariff concept of ABT presents an
inherent platform for bilateral trading. - Improvement in performance of power plants by
reducing trippings and long term damage. - Improvement in commercial dealings with reduction
in year-end adhoc adjustments and consequent
disputes.
45Summary
46Summary Tariff Setting Goals
- Tariff setting to take into account changing
structure of power sector - It should lead to faster approval process
- Normative cost etc. approach
- It should promote efficiencies
47Thank you