UPDATE: LIVESTOCK REGULATIONS AND NUISANCE SUITS IOWA PORK PRODUCERS ASSOC. August 22, 24, 25, 2005 - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

UPDATE: LIVESTOCK REGULATIONS AND NUISANCE SUITS IOWA PORK PRODUCERS ASSOC. August 22, 24, 25, 2005

Description:

... such as fans, slats, gates, roofs or covers ... Also contact local police or county sheriff. Must report within 6 hours of onset or discovery of release ... – PowerPoint PPT presentation

Number of Views:68
Avg rating:3.0/5.0
Slides: 49
Provided by: iowa3
Category:

less

Transcript and Presenter's Notes

Title: UPDATE: LIVESTOCK REGULATIONS AND NUISANCE SUITS IOWA PORK PRODUCERS ASSOC. August 22, 24, 25, 2005


1
UPDATE LIVESTOCK REGULATIONS AND NUISANCE SUITS
IOWA PORK PRODUCERS ASSOC.August 22, 24, 25,
2005Eldon McAfee
2
ANIMAL CAPACITY Animal weight capacity and
animal unit capacity
  • Constructed before 2002 legislation animal
    weight capacity (AWC) - maximum number of animals
    confined at any time in a confinement operation
    multiplied by the average weight during a
    production cycle
  • Constructed or expanded after 2002 legislation
    animal unit capacity (AUC) - maximum number of
    animals confined at any one time in a confinement
    operation multiplied by the animal unit factor -
    swine animal unit factors
  • .4 - more than 55 pounds, .1 15 to 55

3
CONFINEMENT OPERATIONSOne or two?
  • To determine if a permit or manure management
    plan is required, and if concrete standards
    apply
  • Two CFOs are considered to be one operation
    when
  • There is common ownership or management, and
  • They are adjacent or
  • Utilize a common area or system for manure
    application
  • Adjacent CFOs within
  • 1,250 feet if the combined AUC is lt1,000
  • 2,500 feet if the combined AUC is gt1,000

4
CONFINEMENT OPERATIONSOne or two?
  • To determine required separation distances
  • Two CFOs are considered to be one operation
    when
  • There is common ownership or management, and
  • They are adjacent
  • Adjacent CFOs within
  • 1,250 feet if the combined AUC is lt3,000 for
    finishing or nursery (lt1,250 AUC for farrow-gest.
    or lt2,700 AUC for farrow to fin.)
  • 1,500 ft. if the combined AUC is gt3,000 but
    lt5,000 for finishing or nursery (gt1,250 but
    lt2,000 AUC for farrow-gest. or gt2,700 but lt5,400
    AUC for farrow to fin.)
  • 2,500 feet if the combined AUC is gt5,000 for
    finishing or nursery (gt2,000 AUC for farrow-gest.
    or gt5,400 AUC for farrow to fin.)

5
Adjacency
1,200 head finisher 480 a.u.s
1,300 feet between not adjacent because more
than 1,250 feet and less than 1,000 total animal
units
1,200 head finisher 480 a.u.s
6
Adjacency
1,200 head finisher 480 a.u.s
1,300 feet between adjacent because more than
1,000 total animal units and distance is less
than 2,500 feet
2,400 head finisher 960 a.u.s
7
Adjacency contract feeding for same owner of
pigs
Producer A 2,400 head finisher 960 a.u.s
2,000 feet
Producer B 1,200 head finisher 480 a.u.s
8
CONFINEMENT OPERATIONSOne or two?
  • Common management
  • Iowa law (DNR rule)
  • Significant control of day-to-day operations
  • DNR interpretation
  • Common management if two producers contract feed
    hogs for the same owner if the owner has the
    right to control marketing, feed rations, or vet
    services

9
CONSTRUCTION-FORMED STOR.500 animal units or
less (small AFO)
  • Separation distances from water bodies (500 ft.
    from creek, etc.) wells
  • No construction in 100 yr. floodplain of
    navigable river, etc.
  • Tile around footings for below ground storage (or
    certification that groundwater table is below the
    structure)
  • Stormwater discharge permit if area disturbed
    during construction is more than 1 acre

10
CONSTRUCTION-FORMED STOR.500 1,000 animal units
  • MMP construction design statement to DNR
    county 30 days before construction
  • Note All information on the MMP CDS be
    completed correctly DNR has taken the position
    that the 30 day period does not start if certain
    info is not correct or is missing
  • Meet construction design stds. (including tile
    around footings or cert. regarding groundwater
    level)
  • Meet required separation distances
  • No construction in 100 yr. floodplain of navig.
    river, etc.
  • Stormwater discharge permit if area disturbed
    during construction is more than 1 acre
  • See www.iowadnr.com/afo/forms.html for forms

11
CONSTRUCTION-FORMED STOR.1,000 animal units or
more
  • Construction permit app. to DNR county (DNR has
    60 days to act but can extend for add. 30 days)
  • Engineer required if 3,000 or more AUC for
    finishers or nursery (gt1,250 AUC farrow gest or
    gt2,750 AUC farrow to finish)
  • Const. design statement if no engineer reqd
  • Meet construction design stds. (including tile
    around footings or eng. cert. regarding
    groundwater level)
  • Meet required separation distances
  • No construction in 100 yr. floodplain of navig.
    river
  • Manure management plan
  • Stormwater discharge permit if area disturbed
    during construction is more than 1 acre
  • See www.iowadnr.com/afo/forms.html for forms

12
CONSTRUCTION-FORMED STOR.1,000 animal units or
more
  • Master matrix
  • Not required if expansion up to 1666 a.u.s if
    site existed on 4/1/02 or if county has not
    adopted matrix
  • Producer selects criteria county scores DNR
    independently scores if county rejects
  • Legally enforceable - part of permit
  • Supporting documentation, including design,
    operation, and maintenance plans.
  • Note If the necessary supporting documention is
    not included, DNR takes the position that it may
    reject the permit application (even if a county
    passes the matrix) because the matrix is a part
    of the permit
  • Also triggers countys 14 day right to appeal
    issuance of permit (county can waive right to
    appeal)

13
CONSTRUCTION-FORMED STOR.1,000 animal units or
more
  • Construction permit required if any construction
    of a manure storage structure occurs on site
  • Permit required even if no physical construction
    or alteration if there is an increase in manure
    volume or a modification in the manner manure is
    stored. Unless increases or modifications are
  • Within the limits of a previously issued
    construction permit
  • Determined insignificant by DNR (e.g., double
    stocking weaned pigs in a wean-to-finish barn)
  • No permit required for repairs or additions to a
    building such as fans, slats, gates, roofs or
    covers
  • Plans for repair or modification to a manure
    structure must be submitted to DNR to determine
    if a permit is required

14
CONSTRUCTION Stormwater discharge permit
  • Required if the total area disturbed is more than
    one acre - activities that further cropping are
    exempt
  • To obtain a stormwater discharge permit for
    construction activities
  • Publish a form notice in 2 newspapers with the
    largest circulation in the area
  • Prepare a pollution prevention plan that includes
    measures to be implemented to control erosion
    during construction and until a permanent ground
    cover is established. This plan must be in place
    at the time the notice of intent is submitted to
    DNR and must be kept on site
  • Submit a notice of intent to be covered by the
    state general stormwater discharge permit to DNR
    at least 24 hours before construction begins.
    Attach proof of publication of public notice to
    the notice of intent and filing fee.
  • See www.iowadnr.com/afo/forms.html for forms

15
SEPARATION DISTANCESResidences, businesses, road
rights of way, etc.
  • CFOs with formed manure storage and more than
    500 AUC are subject to separation distances
    regardless of whether a DNR permit is required
  • Residences, businesses, churches, schools, public
    use areas, and road rights-of-way
  • Public use areas include parks and cemeteries
  • For a worksheet and separation distance tables
    see www.iowadnr.com/afo/files/distreq.pdf

16
SEPARATION DISTANCESResidences, businesses, road
rights of way etc.
  • Exemptions
  • Written waiver from owner of residence, etc.
  • Expansion of CFO -- use distances in effect at
    time CFO constructed (if CFO constructed before
    any distances required, distances adopted in 1995
    apply)
  • lt2x cap.,lt1,000 AUC, and new structure built
    further from residence, etc.
  • Residence, etc. built after CFO began operation
  • For distance from road rights-of-way
  • Can be waived by county or state

17
SEPARATION DISTANCESWater bodies rivers,
creeks, wells, etc.
  • Ag drainage wells surface inlets, sinkholes,
    navigable waters (rivers, etc. from list in DNR
    rules), all other waters (creeks,etc.), and
    designated wetlands (protected by U.S. Dept. of
    Interior or DNR and owned and managed by the
    U.S. government or DNR
  • Distances do not apply to
  • Farm ponds or private lakes
  • CFO structures using secondary containment
  • Wells
  • Can request variance from DNR

18
MANURE MANAGEMENT PLANSOriginal (new) filed with
DNR county
  • Formed storage
  • More than 500 animal units capacity (1,250 head
    of swine weighing more than 55 pounds or 5,000
    head weighing 15 to 55 pounds)
  • Constructed or expanded after 5/31/85
  • Earthen storage- DNR construction permit
  • DNR interpretation Upon transfer of operation
  • New MMP
  • MMP fees and indemnity fund fees
  • Transfers may include family transfers forming
    a corporation
  • Transferee loses grandfather status for phase-in
    of P Index

19
MANURE MANAGEMENT PLANS
  • Annual updates
  • To DNR and county
  • Short form detailing changes in MMP or statement
    that there are no changes
  • May use table values in updates submitted to DNR
    each year then apply manure based actual sample
    values if amend plan before manure applied (do
    not have to submit amended plan to DNR)
  • Compliance fee - .15/a.u. if contract feeding,
    livestock owner required to pay fee

20
MANURE MANAGEMENT PLANSRecordkeeping
  • Records - must be kept on site or at a residence
    or office of the owner or operator within 30
    miles of the site
  • DNR recordkeeping form not mandatory, producer
    can use own form
  • Current MMP
  • Rate, methods and date(s) of app.
  • Field location and number of acres

21
MANURE MANAGEMENT PLANSRecordkeeping
commercial N P
  • For manure applications after 8/25/05, MMP
    records must include dates and application rates
    of commercial N P on fields receiving manure
    including land farmed by someone else where
    manure is applied under an application agreement.
  • DNR cannot bring an enforcement action for over
    application of N or P on land farmed by someone
    else unless the producer knew or should have
    known that commercial N or P would result in N
    or P exceeding legal limits.

22
MANURE MANAGEMENT PLANSRecordkeeping
commercial N P
  • Producer must obtain statement from farmer who
    owns, rents, or leases each field receiving
    manure specifying the planned commercial N and P
    fertilizer rates to be applied to each field
  • DNR does not currently have a form, but suggests
    the following pounds N (and
  • pounds P) are planned to be applied to
    this field, which is pounds of type of
    fertilizer product, such as anhydrous ammonia or
    liquid N

23
MANURE MANAGEMENT PLANSDNR policy
  • Crop available N during first crop year after
    manure application
  • Previously DNR allowed less than 100
  • Beginning 8/25/04 new MMPs - use 100 based on
    ISU Pub. Pm-1811
  • Can use less than 100 if provide DNR with
    supporting credible information
  • Existing operations may continue to use less than
    100 without supporting info until the first P
    Index based MMP is due

24
MANURE MANAGEMENT PLANS
  • Account for all sources of nitrogen (and
    phosphorus if phosphorus based application rates
    are required)
  • Manure, fertilizer, and legume credit
  • Establishes limit on amount of nitrogen (and
    phosphorus) from all sources
  • Nitrogen in addition to amounts allowed in MMP
    may be applied up to amounts recommended by soil
    or crop nitrogen test for optimum crop yield
  • Phosphorus in addition to amounts allowed under P
    based MMP rates may be applied if recommended by
    soil tests and ISU PM-1688

25
MANURE MANAGEMENT PLANSPhosphorus index
  • In addition to N requirements
  • Phased in based on date of original MMP
  • Before 4/1/02 P Index required with first
    annual update MMP on or after 8/25/08
  • On or after 4/1/02 before 10/25/04 P Index
    required with first annual update MMP on or after
    8/25/06
  • On or after 10/25/04 must comply with P Index
  • Note DNR has determined that an MMP submitted
    for an expansion of an existing operation is an
    original MMP an MMP for a modification without
    expansion of animal numbers is not an original
    MMP

26
COMPOSTING Mortalities DNR rules
  • Mortalities must be incorporated into compost
    material within 24 hours of death
  • Compost site must be on compacted soil, compacted
    granular aggregates, asphalt, concrete or similar
    relatively impermeable material.
  • The site must be accessible during periods of
    inclement weather and prevent contamination of
    surface and groundwater.
  • The site cannot be located on a wetland, and must
    be at least 100 feet from private wells, 200 feet
    from public wells, 50 feet from property lines,
    500 feet from inhabited residences (excluding the
    operators) and 100 feet from flowing or
    intermittent streams, lakes or ponds. Composting
    in a 100 yr floodplain must meet DNR floodplain
    requirements.

27
COMPOSTING Mortalities DNR rules
  • No runoff any water or liquid ponding must be
    corrected within 48 hours
  • Odors, dust, noise, litter and vectors which may
    create nuisance conditions must be minimized
  • Mortalities cannot be removed until soft tissue
    is fully decomposed
  • Finished compost cannot be stored for more than
    18 months
  • DNR recommends that finished compost be land
    applied at N or P crop use rates, whichever is
    more limiting
  • Mortalities must be composted on the site where
    they were produced unless a composting permit or
    variance is obtained from DNR

28
MANURE APPLICATIONAll livestock operations no
pollution
  • No manure app. within 200 feet of designated area
    (800 feet if high quality water resource, see DNR
    website for list) unless manure injected or
    incorporated on same date or perm. vegetation 50
    ft. around water source no manure on 50 ft.
    area (does not apply to ag drainage wells)
  • Designated areas are
  • Creeks, rivers, lakes, designated wetlands
  • Known sinkhole
  • Cistern, drinking water or abandoned well
  • Ag drainage well or surface inlet
  • Lake or farm pond

29
MANURE APPLICATIONConfinement operations
liquid manure
  • Must be injected or incorporated in 24 hrs. if
    applied within 750 ft. of residence, bus.,
    church, school or public use area (250 ft. if use
    low pressure spray irrigation - lt25 psi, center
    pivot lt 9 ft. high)
  • Does not apply if waiver from owner of residence,
    etc. or operation has less than 500 animal units
    capacity
  • Note DNR may consider incidental spillage (on
    endrows, etc.) while incorporating as surface
    application

30
STOCKPILING MANURE Open feedlots
  • New DNR rules apply to all swine, cattle (beef
    and dairy), horse or sheep open lots with less
    than 1,000 animal units of capacity and those
    designated by DNR as a CAFO
  • Must land apply as soon as possible but no later
    than 6 months
  • Cannot stockpile
  • Within 200 ft. (800 ft. from a high quality water
    resource) of a designated area unless a 50 ft.
    permanent grass buffer is established
  • In a grass waterway
  • Within 200 ft. of downgrade tile intakes

31
DNR ENFORCEMENT Inspections
  • Iowa Code DNR may enter private property
  • With notification of and consent from owner or
    occupant
  • Search warrant
  • DNR policy enter without permission or a search
    warrant if no one is present to refuse permission
  • County representative may accompany DNR
  • DNR ( county rep) must follow standard
    biosecurity requirements customarily required by
    the producer to control spread of disease
  • If inspection is of a proposed construction site,
    DNR must give at least 24 hours notice

32
DNR ENFORCEMENT Environmental self audits
  • Initiated by business owner to determine
    environmental compliance
  • Benefits
  • Immunity from penalties if a violation discovered
    during audit and promptly reported to DNR, before
    DNR investigates
  • Includes failure to file an MMP
  • Confidentiality of audit report
  • No immunity from penalties if
  • DNR not properly notified
  • Violations are intentional or result in injury to
    persons, property or environment
  • Substantial economic benefit giving violator a
    clear economic advantage over competitors

33
DNR ENFORCEMENT Reporting manure releases
  • Notify DNR state office by calling 515-281-8694.
    Also contact local police or county sheriff
  • Must report within 6 hours of onset or discovery
    of release
  • Release is an actual, imminent, or probable
    discharge of manure to surface water,
    groundwater, tile line or intake or designated
    area
  • Verbal report at time of notification and written
    report within 30 days

34
CAFO RULES Discharge permit (NPDES)
  • Federal court ruled no discharge permit required
    if the operation does not discharge
  • Otherwise, operations with 1,000 animal units or
    more required to have permit by Feb. 2006 but
    EPA revising rules following courts ruling
  • Nutrient management plan part of NPDES permit
    requirements in addition to MMP
  • DNR has withdrawn its proposed rules awaiting
    guidance from federal EPA as a result of the
    federal court decision
  • EPA and DNR considering whether there is
    authority under the Clean Water Act to require a
    discharge permit for a confinement operation
    which has had an accidental manure spill

35
AIR QUALITY STANDARDS2002 Iowa Legislation
  • Hydrogen sulfide, ammonia and odor
  • Field study must be conducted
  • Levels commonly known to cause a material and
    verifiable adverse health effect
  • All enforcement at a separated location
  • Separated location is a location or object from
    which a separation distance is required by law
    (excluding a road)
  • DNR H2S standard 30 ppb, daily max. 1 hr.
    average, 7 exceedances per year

36
AIR QUALITY Dust DNR rule
  • Must take reasonable precautions to prevent
    particulate matter from becoming airborne in
    quantities sufficient to create a nuisance
  • Exemptions
  • Farming operations
  • Dust from ordinary travel on unpaved roads
  • DNR interpretation Dust from construction
    activities on farm operations not eligible for
    the farming operation exemption

37
AIR QUALITY Federal air emissions laws
  • Sign up period for Air Emissions Consent
    Agreement closed 8/12/05
  • For farms that commence operation or expand after
    the signup deadline, producer may consider taking
    steps to comply with federal air emissions laws
    at the outset
  • If an operation will emit more than 100 of
    ammonia or hydrogen sulfide in a 24 hour period,
    an operator must file CERCLA and EPCRA reports
    after the operation begins
  • For more information see www.epa.gov/superfund/pro
    grams/er/triggers/haztrigs/crelproc.htm

38
NUISANCE Recent and pending cases
  • 13 cases filed in 2003, 2 in 04 2 in 05 6
    currently set for trial, 1 grain drying and
    storage case on appeal
  • Tasler v. Wilkerson Prestage Stoecker- Dallas
    County - Aug. 2004
  • 4,400 head finisher
  • 5 plaintiffs (3 residences) all over 1 mile away
  • Producer and other neighbors lived closer
  • Jury found nuisance - 4,700 total damages - No
    future damages or decrease in property value
  • Following jury verdict, judge granted new trial
    based on inconsistent jury verdicts
  • After the judges ruling, the parties settled the
    case

39
NUISANCE Anticipated nuisance
  • Nuisance suit filed before or during construction
    alleging that a nuisance will necessarily
    result and that an injunction should be granted
    prohibiting construction and/or operation
  • Courts usually deny in livestock cases where it
    is not certain a nuisance will occur
  • In Simpson v. Kollasch, Kossuth Co. district
    court judge denied request for injunction on
    anticipated nuisance because there was no
    evidence that a nuisance would clearly and
    necessarily result from the operation as
    proposed
  • Time period for appeal to Iowa Supreme Court is
    still open

40
NUISANCE Statute of limitations
  • No Iowa Supreme Court decisions on statute of
    limitations for odor nuisance
  • For permanent nuisances, once time period
    elapses, lawsuit cannot be filed
  • Iowa law 5 years for property damage, 2 years
    for personal injury
  • District court rulings have varied. A Polk
    county judge ruled the statute of limitations for
    all nuisance claims was 5 years while a Franklin
    county judge ruled the statute of limitations for
    claims for loss of property value was 5 years and
    claims for personal inconvenience, annoyance and
    discomfort, physical and emotional pain and
    suffering, mental distress and fear of illness
    had a 2 year statute of limitations

41
NUISANCE Contract feeding
  • General rule in Iowa for independent contractors
    Owners of livestock should not be liable for
    nuisance unless owner knows or has reason to
    know nuisance is likely
  • Tasler v. Wilkerson Prestage Stoecker 2004
    Dallas County
  • Prestage-Stoecker found to be jointly liable for
    nuisance because it substantially participated
    in the nuisance via contract feeding relationship

42
NUISANCE Manure application - landowner liability
  • Tetzlaff v. Camp Pangborn- Madison County
  • 300 head finisher built in 1970s, Camps bought
    in 1992, Tetzlaffs built new home across road in
    1999
  • Court ruled landlord (Pangborns) not liable if
    there is a nuisance from manure application
    because the LL did not have substantial control
    or participation in manure application
  • On appeal to the Iowa Supreme Court

43
NUISANCE Protection for producer
  • Insurance
  • Standard farm liability policies normally dont
    cover
  • Environmental policies available
  • Coverage for claims and costs of defense
  • Nuisance defense
  • Ag Area Law - 1998 unconstitutional
  • Animal Feeding Operation 2004
    unconstitutional if plaintiff precedes livestock
    operation
  • Tetzlaff v. Camp Court ruled nuisance defense
    constitutional because manure application had
    been occurring when Tetzlaffs moved in
  • Trial scheduled for April 2006

44
NUISANCE Steps to help to avoid lawsuit
  • Know the neighborhood
  • Meet with neighbors
  • Sincerely respond to concerns expressed by
    neighbors
  • Meet or exceed all legal requirements
  • Design construct operation to minimize impact
    on neighbors
  • Stay current on and use new technology and
    management practices to minimize odor

45
NUISANCE Steps to help to avoid lawsuit
  • Inject or incorporate manure
  • Apply manure as far from concerned neighbors as
    possible
  • Avoid manure on roads and mud, dust, etc. as much
    as possible
  • Notify neighbors before manure application
  • Watch wind, temp. other weather conditions when
    applying manure

46
NUISANCE Steps to help to avoid lawsuit
  • Apply manure as few times as possible
  • If need more land, consider offering manure to
    neighbors
  • Consider ownership of neighboring residences or
    purchasing re-selling with nuisance covenants
  • Keep good records

47
NUISANCE Steps to help to avoid lawsuit
  • Inform employees about good neighbor practices
    make sure they follow them
  • Require all manure applicators, input suppliers,
    livestock haulers, etc. to follow good neighbor
    practices
  • Avoid the following
  • Nothing will satisfy those people.
  • If I make changes now, Ill be admitting there
    is a problem

48
NUISANCE
  • All reasonable steps to minimize the impact of a
    livestock operation on neighbors must be taken to
    improve chances of avoiding a nuisance lawsuit or
    help in legal defense if a nuisance suit is filed
Write a Comment
User Comments (0)
About PowerShow.com