Title: UPDATE: LIVESTOCK REGULATIONS AND NUISANCE SUITS IOWA PORK PRODUCERS ASSOC. August 22, 24, 25, 2005
1UPDATE LIVESTOCK REGULATIONS AND NUISANCE SUITS
IOWA PORK PRODUCERS ASSOC.August 22, 24, 25,
2005Eldon McAfee
2ANIMAL CAPACITY Animal weight capacity and
animal unit capacity
- Constructed before 2002 legislation animal
weight capacity (AWC) - maximum number of animals
confined at any time in a confinement operation
multiplied by the average weight during a
production cycle - Constructed or expanded after 2002 legislation
animal unit capacity (AUC) - maximum number of
animals confined at any one time in a confinement
operation multiplied by the animal unit factor -
swine animal unit factors - .4 - more than 55 pounds, .1 15 to 55
3CONFINEMENT OPERATIONSOne or two?
- To determine if a permit or manure management
plan is required, and if concrete standards
apply - Two CFOs are considered to be one operation
when - There is common ownership or management, and
- They are adjacent or
- Utilize a common area or system for manure
application - Adjacent CFOs within
- 1,250 feet if the combined AUC is lt1,000
- 2,500 feet if the combined AUC is gt1,000
4CONFINEMENT OPERATIONSOne or two?
- To determine required separation distances
- Two CFOs are considered to be one operation
when - There is common ownership or management, and
- They are adjacent
- Adjacent CFOs within
- 1,250 feet if the combined AUC is lt3,000 for
finishing or nursery (lt1,250 AUC for farrow-gest.
or lt2,700 AUC for farrow to fin.) - 1,500 ft. if the combined AUC is gt3,000 but
lt5,000 for finishing or nursery (gt1,250 but
lt2,000 AUC for farrow-gest. or gt2,700 but lt5,400
AUC for farrow to fin.) - 2,500 feet if the combined AUC is gt5,000 for
finishing or nursery (gt2,000 AUC for farrow-gest.
or gt5,400 AUC for farrow to fin.)
5Adjacency
1,200 head finisher 480 a.u.s
1,300 feet between not adjacent because more
than 1,250 feet and less than 1,000 total animal
units
1,200 head finisher 480 a.u.s
6Adjacency
1,200 head finisher 480 a.u.s
1,300 feet between adjacent because more than
1,000 total animal units and distance is less
than 2,500 feet
2,400 head finisher 960 a.u.s
7Adjacency contract feeding for same owner of
pigs
Producer A 2,400 head finisher 960 a.u.s
2,000 feet
Producer B 1,200 head finisher 480 a.u.s
8CONFINEMENT OPERATIONSOne or two?
- Common management
- Iowa law (DNR rule)
- Significant control of day-to-day operations
- DNR interpretation
- Common management if two producers contract feed
hogs for the same owner if the owner has the
right to control marketing, feed rations, or vet
services
9CONSTRUCTION-FORMED STOR.500 animal units or
less (small AFO)
- Separation distances from water bodies (500 ft.
from creek, etc.) wells - No construction in 100 yr. floodplain of
navigable river, etc. - Tile around footings for below ground storage (or
certification that groundwater table is below the
structure) - Stormwater discharge permit if area disturbed
during construction is more than 1 acre
10CONSTRUCTION-FORMED STOR.500 1,000 animal units
- MMP construction design statement to DNR
county 30 days before construction - Note All information on the MMP CDS be
completed correctly DNR has taken the position
that the 30 day period does not start if certain
info is not correct or is missing - Meet construction design stds. (including tile
around footings or cert. regarding groundwater
level) - Meet required separation distances
- No construction in 100 yr. floodplain of navig.
river, etc. - Stormwater discharge permit if area disturbed
during construction is more than 1 acre - See www.iowadnr.com/afo/forms.html for forms
11CONSTRUCTION-FORMED STOR.1,000 animal units or
more
- Construction permit app. to DNR county (DNR has
60 days to act but can extend for add. 30 days) - Engineer required if 3,000 or more AUC for
finishers or nursery (gt1,250 AUC farrow gest or
gt2,750 AUC farrow to finish) - Const. design statement if no engineer reqd
- Meet construction design stds. (including tile
around footings or eng. cert. regarding
groundwater level) - Meet required separation distances
- No construction in 100 yr. floodplain of navig.
river - Manure management plan
- Stormwater discharge permit if area disturbed
during construction is more than 1 acre - See www.iowadnr.com/afo/forms.html for forms
12CONSTRUCTION-FORMED STOR.1,000 animal units or
more
- Master matrix
- Not required if expansion up to 1666 a.u.s if
site existed on 4/1/02 or if county has not
adopted matrix - Producer selects criteria county scores DNR
independently scores if county rejects - Legally enforceable - part of permit
- Supporting documentation, including design,
operation, and maintenance plans. - Note If the necessary supporting documention is
not included, DNR takes the position that it may
reject the permit application (even if a county
passes the matrix) because the matrix is a part
of the permit - Also triggers countys 14 day right to appeal
issuance of permit (county can waive right to
appeal)
13CONSTRUCTION-FORMED STOR.1,000 animal units or
more
- Construction permit required if any construction
of a manure storage structure occurs on site - Permit required even if no physical construction
or alteration if there is an increase in manure
volume or a modification in the manner manure is
stored. Unless increases or modifications are - Within the limits of a previously issued
construction permit - Determined insignificant by DNR (e.g., double
stocking weaned pigs in a wean-to-finish barn) - No permit required for repairs or additions to a
building such as fans, slats, gates, roofs or
covers - Plans for repair or modification to a manure
structure must be submitted to DNR to determine
if a permit is required
14CONSTRUCTION Stormwater discharge permit
- Required if the total area disturbed is more than
one acre - activities that further cropping are
exempt - To obtain a stormwater discharge permit for
construction activities - Publish a form notice in 2 newspapers with the
largest circulation in the area - Prepare a pollution prevention plan that includes
measures to be implemented to control erosion
during construction and until a permanent ground
cover is established. This plan must be in place
at the time the notice of intent is submitted to
DNR and must be kept on site - Submit a notice of intent to be covered by the
state general stormwater discharge permit to DNR
at least 24 hours before construction begins.
Attach proof of publication of public notice to
the notice of intent and filing fee. - See www.iowadnr.com/afo/forms.html for forms
15SEPARATION DISTANCESResidences, businesses, road
rights of way, etc.
- CFOs with formed manure storage and more than
500 AUC are subject to separation distances
regardless of whether a DNR permit is required - Residences, businesses, churches, schools, public
use areas, and road rights-of-way - Public use areas include parks and cemeteries
- For a worksheet and separation distance tables
see www.iowadnr.com/afo/files/distreq.pdf
16SEPARATION DISTANCESResidences, businesses, road
rights of way etc.
- Exemptions
- Written waiver from owner of residence, etc.
- Expansion of CFO -- use distances in effect at
time CFO constructed (if CFO constructed before
any distances required, distances adopted in 1995
apply) - lt2x cap.,lt1,000 AUC, and new structure built
further from residence, etc. - Residence, etc. built after CFO began operation
- For distance from road rights-of-way
- Can be waived by county or state
17SEPARATION DISTANCESWater bodies rivers,
creeks, wells, etc.
- Ag drainage wells surface inlets, sinkholes,
navigable waters (rivers, etc. from list in DNR
rules), all other waters (creeks,etc.), and
designated wetlands (protected by U.S. Dept. of
Interior or DNR and owned and managed by the
U.S. government or DNR - Distances do not apply to
- Farm ponds or private lakes
- CFO structures using secondary containment
- Wells
- Can request variance from DNR
18MANURE MANAGEMENT PLANSOriginal (new) filed with
DNR county
- Formed storage
- More than 500 animal units capacity (1,250 head
of swine weighing more than 55 pounds or 5,000
head weighing 15 to 55 pounds) - Constructed or expanded after 5/31/85
- Earthen storage- DNR construction permit
- DNR interpretation Upon transfer of operation
- New MMP
- MMP fees and indemnity fund fees
- Transfers may include family transfers forming
a corporation - Transferee loses grandfather status for phase-in
of P Index
19MANURE MANAGEMENT PLANS
- Annual updates
- To DNR and county
- Short form detailing changes in MMP or statement
that there are no changes - May use table values in updates submitted to DNR
each year then apply manure based actual sample
values if amend plan before manure applied (do
not have to submit amended plan to DNR) - Compliance fee - .15/a.u. if contract feeding,
livestock owner required to pay fee
20MANURE MANAGEMENT PLANSRecordkeeping
- Records - must be kept on site or at a residence
or office of the owner or operator within 30
miles of the site - DNR recordkeeping form not mandatory, producer
can use own form - Current MMP
- Rate, methods and date(s) of app.
- Field location and number of acres
21MANURE MANAGEMENT PLANSRecordkeeping
commercial N P
- For manure applications after 8/25/05, MMP
records must include dates and application rates
of commercial N P on fields receiving manure
including land farmed by someone else where
manure is applied under an application agreement.
- DNR cannot bring an enforcement action for over
application of N or P on land farmed by someone
else unless the producer knew or should have
known that commercial N or P would result in N
or P exceeding legal limits.
22MANURE MANAGEMENT PLANSRecordkeeping
commercial N P
- Producer must obtain statement from farmer who
owns, rents, or leases each field receiving
manure specifying the planned commercial N and P
fertilizer rates to be applied to each field - DNR does not currently have a form, but suggests
the following pounds N (and - pounds P) are planned to be applied to
this field, which is pounds of type of
fertilizer product, such as anhydrous ammonia or
liquid N
23MANURE MANAGEMENT PLANSDNR policy
- Crop available N during first crop year after
manure application - Previously DNR allowed less than 100
- Beginning 8/25/04 new MMPs - use 100 based on
ISU Pub. Pm-1811 - Can use less than 100 if provide DNR with
supporting credible information - Existing operations may continue to use less than
100 without supporting info until the first P
Index based MMP is due
24MANURE MANAGEMENT PLANS
- Account for all sources of nitrogen (and
phosphorus if phosphorus based application rates
are required) - Manure, fertilizer, and legume credit
- Establishes limit on amount of nitrogen (and
phosphorus) from all sources - Nitrogen in addition to amounts allowed in MMP
may be applied up to amounts recommended by soil
or crop nitrogen test for optimum crop yield - Phosphorus in addition to amounts allowed under P
based MMP rates may be applied if recommended by
soil tests and ISU PM-1688
25MANURE MANAGEMENT PLANSPhosphorus index
- In addition to N requirements
- Phased in based on date of original MMP
- Before 4/1/02 P Index required with first
annual update MMP on or after 8/25/08 - On or after 4/1/02 before 10/25/04 P Index
required with first annual update MMP on or after
8/25/06 - On or after 10/25/04 must comply with P Index
- Note DNR has determined that an MMP submitted
for an expansion of an existing operation is an
original MMP an MMP for a modification without
expansion of animal numbers is not an original
MMP
26COMPOSTING Mortalities DNR rules
- Mortalities must be incorporated into compost
material within 24 hours of death - Compost site must be on compacted soil, compacted
granular aggregates, asphalt, concrete or similar
relatively impermeable material. - The site must be accessible during periods of
inclement weather and prevent contamination of
surface and groundwater. - The site cannot be located on a wetland, and must
be at least 100 feet from private wells, 200 feet
from public wells, 50 feet from property lines,
500 feet from inhabited residences (excluding the
operators) and 100 feet from flowing or
intermittent streams, lakes or ponds. Composting
in a 100 yr floodplain must meet DNR floodplain
requirements.
27COMPOSTING Mortalities DNR rules
- No runoff any water or liquid ponding must be
corrected within 48 hours - Odors, dust, noise, litter and vectors which may
create nuisance conditions must be minimized - Mortalities cannot be removed until soft tissue
is fully decomposed - Finished compost cannot be stored for more than
18 months - DNR recommends that finished compost be land
applied at N or P crop use rates, whichever is
more limiting - Mortalities must be composted on the site where
they were produced unless a composting permit or
variance is obtained from DNR
28MANURE APPLICATIONAll livestock operations no
pollution
- No manure app. within 200 feet of designated area
(800 feet if high quality water resource, see DNR
website for list) unless manure injected or
incorporated on same date or perm. vegetation 50
ft. around water source no manure on 50 ft.
area (does not apply to ag drainage wells) - Designated areas are
- Creeks, rivers, lakes, designated wetlands
- Known sinkhole
- Cistern, drinking water or abandoned well
- Ag drainage well or surface inlet
- Lake or farm pond
29MANURE APPLICATIONConfinement operations
liquid manure
- Must be injected or incorporated in 24 hrs. if
applied within 750 ft. of residence, bus.,
church, school or public use area (250 ft. if use
low pressure spray irrigation - lt25 psi, center
pivot lt 9 ft. high) - Does not apply if waiver from owner of residence,
etc. or operation has less than 500 animal units
capacity - Note DNR may consider incidental spillage (on
endrows, etc.) while incorporating as surface
application
30STOCKPILING MANURE Open feedlots
- New DNR rules apply to all swine, cattle (beef
and dairy), horse or sheep open lots with less
than 1,000 animal units of capacity and those
designated by DNR as a CAFO - Must land apply as soon as possible but no later
than 6 months - Cannot stockpile
- Within 200 ft. (800 ft. from a high quality water
resource) of a designated area unless a 50 ft.
permanent grass buffer is established - In a grass waterway
- Within 200 ft. of downgrade tile intakes
31DNR ENFORCEMENT Inspections
- Iowa Code DNR may enter private property
- With notification of and consent from owner or
occupant - Search warrant
- DNR policy enter without permission or a search
warrant if no one is present to refuse permission - County representative may accompany DNR
- DNR ( county rep) must follow standard
biosecurity requirements customarily required by
the producer to control spread of disease - If inspection is of a proposed construction site,
DNR must give at least 24 hours notice
32DNR ENFORCEMENT Environmental self audits
- Initiated by business owner to determine
environmental compliance - Benefits
- Immunity from penalties if a violation discovered
during audit and promptly reported to DNR, before
DNR investigates - Includes failure to file an MMP
- Confidentiality of audit report
- No immunity from penalties if
- DNR not properly notified
- Violations are intentional or result in injury to
persons, property or environment - Substantial economic benefit giving violator a
clear economic advantage over competitors
33DNR ENFORCEMENT Reporting manure releases
- Notify DNR state office by calling 515-281-8694.
Also contact local police or county sheriff - Must report within 6 hours of onset or discovery
of release - Release is an actual, imminent, or probable
discharge of manure to surface water,
groundwater, tile line or intake or designated
area - Verbal report at time of notification and written
report within 30 days
34CAFO RULES Discharge permit (NPDES)
- Federal court ruled no discharge permit required
if the operation does not discharge - Otherwise, operations with 1,000 animal units or
more required to have permit by Feb. 2006 but
EPA revising rules following courts ruling - Nutrient management plan part of NPDES permit
requirements in addition to MMP - DNR has withdrawn its proposed rules awaiting
guidance from federal EPA as a result of the
federal court decision - EPA and DNR considering whether there is
authority under the Clean Water Act to require a
discharge permit for a confinement operation
which has had an accidental manure spill
35AIR QUALITY STANDARDS2002 Iowa Legislation
- Hydrogen sulfide, ammonia and odor
- Field study must be conducted
- Levels commonly known to cause a material and
verifiable adverse health effect - All enforcement at a separated location
- Separated location is a location or object from
which a separation distance is required by law
(excluding a road) - DNR H2S standard 30 ppb, daily max. 1 hr.
average, 7 exceedances per year
36AIR QUALITY Dust DNR rule
- Must take reasonable precautions to prevent
particulate matter from becoming airborne in
quantities sufficient to create a nuisance - Exemptions
- Farming operations
- Dust from ordinary travel on unpaved roads
- DNR interpretation Dust from construction
activities on farm operations not eligible for
the farming operation exemption
37AIR QUALITY Federal air emissions laws
- Sign up period for Air Emissions Consent
Agreement closed 8/12/05 - For farms that commence operation or expand after
the signup deadline, producer may consider taking
steps to comply with federal air emissions laws
at the outset - If an operation will emit more than 100 of
ammonia or hydrogen sulfide in a 24 hour period,
an operator must file CERCLA and EPCRA reports
after the operation begins - For more information see www.epa.gov/superfund/pro
grams/er/triggers/haztrigs/crelproc.htm
38NUISANCE Recent and pending cases
- 13 cases filed in 2003, 2 in 04 2 in 05 6
currently set for trial, 1 grain drying and
storage case on appeal - Tasler v. Wilkerson Prestage Stoecker- Dallas
County - Aug. 2004 - 4,400 head finisher
- 5 plaintiffs (3 residences) all over 1 mile away
- Producer and other neighbors lived closer
- Jury found nuisance - 4,700 total damages - No
future damages or decrease in property value - Following jury verdict, judge granted new trial
based on inconsistent jury verdicts - After the judges ruling, the parties settled the
case
39NUISANCE Anticipated nuisance
- Nuisance suit filed before or during construction
alleging that a nuisance will necessarily
result and that an injunction should be granted
prohibiting construction and/or operation - Courts usually deny in livestock cases where it
is not certain a nuisance will occur - In Simpson v. Kollasch, Kossuth Co. district
court judge denied request for injunction on
anticipated nuisance because there was no
evidence that a nuisance would clearly and
necessarily result from the operation as
proposed - Time period for appeal to Iowa Supreme Court is
still open
40NUISANCE Statute of limitations
- No Iowa Supreme Court decisions on statute of
limitations for odor nuisance - For permanent nuisances, once time period
elapses, lawsuit cannot be filed - Iowa law 5 years for property damage, 2 years
for personal injury - District court rulings have varied. A Polk
county judge ruled the statute of limitations for
all nuisance claims was 5 years while a Franklin
county judge ruled the statute of limitations for
claims for loss of property value was 5 years and
claims for personal inconvenience, annoyance and
discomfort, physical and emotional pain and
suffering, mental distress and fear of illness
had a 2 year statute of limitations
41NUISANCE Contract feeding
- General rule in Iowa for independent contractors
Owners of livestock should not be liable for
nuisance unless owner knows or has reason to
know nuisance is likely - Tasler v. Wilkerson Prestage Stoecker 2004
Dallas County - Prestage-Stoecker found to be jointly liable for
nuisance because it substantially participated
in the nuisance via contract feeding relationship
42NUISANCE Manure application - landowner liability
- Tetzlaff v. Camp Pangborn- Madison County
- 300 head finisher built in 1970s, Camps bought
in 1992, Tetzlaffs built new home across road in
1999 - Court ruled landlord (Pangborns) not liable if
there is a nuisance from manure application
because the LL did not have substantial control
or participation in manure application - On appeal to the Iowa Supreme Court
43NUISANCE Protection for producer
- Insurance
- Standard farm liability policies normally dont
cover - Environmental policies available
- Coverage for claims and costs of defense
- Nuisance defense
- Ag Area Law - 1998 unconstitutional
- Animal Feeding Operation 2004
unconstitutional if plaintiff precedes livestock
operation - Tetzlaff v. Camp Court ruled nuisance defense
constitutional because manure application had
been occurring when Tetzlaffs moved in - Trial scheduled for April 2006
44NUISANCE Steps to help to avoid lawsuit
- Know the neighborhood
- Meet with neighbors
- Sincerely respond to concerns expressed by
neighbors - Meet or exceed all legal requirements
- Design construct operation to minimize impact
on neighbors - Stay current on and use new technology and
management practices to minimize odor
45NUISANCE Steps to help to avoid lawsuit
- Inject or incorporate manure
- Apply manure as far from concerned neighbors as
possible - Avoid manure on roads and mud, dust, etc. as much
as possible - Notify neighbors before manure application
- Watch wind, temp. other weather conditions when
applying manure
46NUISANCE Steps to help to avoid lawsuit
- Apply manure as few times as possible
- If need more land, consider offering manure to
neighbors - Consider ownership of neighboring residences or
purchasing re-selling with nuisance covenants - Keep good records
47NUISANCE Steps to help to avoid lawsuit
- Inform employees about good neighbor practices
make sure they follow them - Require all manure applicators, input suppliers,
livestock haulers, etc. to follow good neighbor
practices - Avoid the following
- Nothing will satisfy those people.
- If I make changes now, Ill be admitting there
is a problem
48NUISANCE
- All reasonable steps to minimize the impact of a
livestock operation on neighbors must be taken to
improve chances of avoiding a nuisance lawsuit or
help in legal defense if a nuisance suit is filed