Project Risk Management A Preparation Guide for the PMI-RMP Exam - PowerPoint PPT Presentation

1 / 50
About This Presentation
Title:

Project Risk Management A Preparation Guide for the PMI-RMP Exam

Description:

A Preparation Guide for the PMI-RMP Exam Scott Reynolds MBA, PMP, PMI-RMP Plan Risk Response Outputs of Risk Response Planning Updates to Risk Register Risk Triggers ... – PowerPoint PPT presentation

Number of Views:416
Avg rating:3.0/5.0
Slides: 51
Provided by: apiNingC9
Category:

less

Transcript and Presenter's Notes

Title: Project Risk Management A Preparation Guide for the PMI-RMP Exam


1
Project Risk ManagementA Preparation Guide for
the PMI-RMP Exam
  • Scott Reynolds MBA, PMP, PMI-RMP

2
What is Project Risk Management?
  • Project risk management is actively managing the
    risks on your project
  • The goal of risk management is to be more
    proactive and less reactive

3
What is a Risk?
  • A risk is an uncertain event that could have a
    positive or negative effect on your project
  • This means there is a probability between 1-99
    that the event could occur
  • If there is a 0 chance of an event occurring,
    there is no risk
  • (example there is a 0 chance your project will
    be adequately funded, this is not a risk, it is a
    reality)
  • If there is a 100 chance of an event occurring,
    this would be an issue, not a risk
  • Risks with negative consequences are called
    threats
  • Risks with positive consequences are called
    opportunities (Yes, risk can be good! Stop
    thinking of risk as bad, and start thinking of it
    in terms of probabilities!)

4
Types of Risk
  • Risks can be broken out into two primary types
  • Pure Risk (hazard) risk with potential loss only
  • ex. Fire, theft, personal injury
  • Business Risk (speculative risk) risk with
    potential loss or gain
  • ex. A highly skilled employee becomes available
    to work on your project, reducing your schedule
    time, the tax rate changes, a new server costs
    less (or more) than you budgeted for

5
Risk Management Processes
  • There are six project risk management processes
  • Go ahead and learn them now (in order), this is
    the only knowledge area in the Project Management
    Body of Knowledge (PKBOK) that must be completed
    in successive order
  • Plan Risk Management
  • Identify Risks
  • Perform Qualitative Analysis
  • Perform Quantitative Analysis
  • Plan Risk Response
  • Monitor Control Risks

6
Risk Management Processes
  • Risk Planning this is how you plan on
    conducting risk management. You wouldnt start
    managing your project without a plan, so why
    would you approach risk management that way?
  • Remember Plan the work, and work the plan?
    Applies to risk management as well.
  • Identify Risks this is the phase where you
    attempt to identify most of your risks
  • Qualitative analysis this is a subjective
    analysis of your risks that produces a risk
    ranking, usually in the order of high, medium,
    low, or on an ordinal scale. Rankings are by
    agreement of your project team, sponsors and key
    stakeholders.

7
Risk Management Processes
  • Quantitative Analysis a numerical analysis of
    the probability and impact of the risk on your
    project
  • Plan Risk Response a course of action you will
    take to deal with your risks should they go from
    risk to issue
  • Monitor Control Risks monitoring your lists
    (there are two lists which I will discuss later)
    of risks to enact a risk response plan, to move a
    risk from one list to the other, or to remove a
    risk because it is no longer a risk

8
Risk Management Planning
  • Before you start dealing with risks, you should
    first plan on how you will handle risk on your
    project
  • Things to consider when creating your Risk
    Management plan
  • The risk tolerance of your project sponsors and
    stakeholders In order to gain buy-in, you need
    to create a plan your sponsors can support. It is
    not likely they will support a plan that is in
    opposition to their agenda or is out of their
    comfort zone
  • The size and value of your project there is a
    cost to risk management, you shouldnt spend more
    on preventing the risk than the cost of the risk
    occurring
  • The methodology you will use the methodology
    you use is not as important as gaining agreement
    and buy-in on the methodology chosen
  • Sources of risk risk categories think of all
    possible areas or events that could introduce
    risk to your project

9
Plan Risk Management
  • Inputs to Risk Management Planning
  • Enterprise environmental factors company
    culture or existing systems the project will have
    to deal with or can make use of
  • Organizational process assets processes,
    procedures, and historical information
  • Project scope statement statement of what the
    project shall deliver and what it should not
    deliver (if you dont know what the scope of your
    project is, can you really identify all areas of
    risk?)
  • Project management plan the guide on how you
    will manage your project

10
Plan Risk Management
  • Inputs to Risk Management Planning
  • Cost Management Plan The guide on how you and
    your team will control costs on the project to
    try to stay within budget
  • Schedule Management Plan The guide on how you
    and your team will manage the schedule of the
    project
  • Communications Management Plan -The guide on who
    you need to communicate to, what information, how
    it needs to be communicated and how often

11
Plan Risk Management
  • Outputs of Risk Management Planning
  • Risk Management Plan
  • - Methodology
  • - Roles Responsibilities
  • - Budgeting
  • - Timing
  • - Risk Categories
  • - Definitions of risk impact
  • - Stakeholder tolerances
  • - Reporting formats
  • - Tracking

12
Identify Risks
  • This is the phase where you work with your team
    to identify as many risks as possible
  • Things to remember
  • Identify Risks cant be completed without the
    project scope statement and Work Breakdown
    Structure (WBS)
  • Identify Risks happens at the onset of the
    project and throughout the project
  • Risks can be identified at any time and during
    any phase of the project
  • Risk management is an iterative process, you
    should work to identify risk during any changes
    to the project, working with resources, and when
    dealing with issues

13
Identify Risks
  • Techniques to identify risk
  • Brainstorming - the free-flow of ideas on risk,
    done with the project team, stakeholders, subject
    matter experts, and experienced resources
  • Delphi technique an anonymous surveying of
    experts in which information is sent to a group
    of experts on the risk. The experts each provide
    input, the responses are compiled and then sent
    back to all of the experts for further review
    the process is repeated until consensus is
    reached.
  • Interviewing interviews of experts, project
    stakeholders, or associates who have worked on
    similar projects in order to discover risks

14
Identify Risks
  • Techniques to identify risk
  • Root Cause Analysis Determining the cause of
    the risk you might be able to identify more
    risks this way or you might be able to eliminate
    the risk by eliminating the cause
  • SWOT Analysis An analysis of the strengths,
    weaknesses, opportunities and threats on your
    project
  • Checklist Analysis after you have identified
    your categories of potential risks on your
    project, you create a checklist of these
    categories to make sure youre not neglecting any
    area where risk can hide

15
Identify Risks
  • Assumptions Analysis what assumptions have you
    made or been given about your project? Are they
    valid? If not, you could have risk
  • Diagramming Techniques diagramming techniques
    can show cause and effect. The effect would be
    your risk, would it be helpful to know what could
    cause that risk?
  • - Cause--Effect diagram
  • - System process flowcharts
  • - Influence diagrams
  • Whenever possible, deal with the cause, not
    the effect

16
Risk Factors
  • When analyzing your risk, you should be aware of
    the following risk factors
  • The probability the risk will occur
  • The range of possible outcomes
  • When in the project lifecycle the risk is likely
    to occur (the timing)
  • once the expected timeframe of the risk has
    passed and it is no longer a risk, it can be
    removed from the risk list
  • How often the risk is expected to occur on the
    project (frequency)

17
Identify Risks
  • Outputs of Identify Risks
  • Risk Register
  • - List of risks
  • - List of potential responses
  • - Root causes of risks
  • - Updated risk categories

18
Perform Qualitative Risk Analysis
  • This is the phase where you rank the risks youve
    identified from Identify Risks to come up with a
    list of risks you will create plans for dealing
    with
  • Things to remember
  • Perform Qualitative Risk Analysis is subjective
  • What is the probability of the risk occurring?
    High, medium, low? 1-10?
  • What is the impact if the risk does occur? High,
    medium, low? 1-10? What is the financial impact,
    are the consequences positive or negative?
  • the earlier you know about risk, the better
    prepared you will
  • be

19
Perform Qualitative Risk Analysis
  • Tools and Techniques of Qualitative Analysis
  • Probability Impact Matrix a matrix that
    creates a consistent evaluation of high, medium,
    or low for your projects. This helps to make the
    risk rating process more repeatable between
    projects.
  • Risk Data Quality Assessment What is the
    quality of the data used to determine or assess
    the risk? Think about the following
  • Extent of the understanding of the risk
  • Data available about the risk
  • Quality of the data
  • Reliability Integrity of the data

20
Perform Qualitative Risk Analysis
  • Tools and Techniques of Qualitative Analysis
  • Risk Categorization Which of your categories
    has more risk than others? Which of your work
    packages could be most affected by risk?
  • Risk Urgency Assessment Which of your risks
    could occur soon, or require a longer planning
    time? Risk urgency assessment helps move these
    risks more quickly through the rest of the
    project management process
  • Perform Qualitative Risk Analysis is
    subjective

21
Perform Qualitative Risk Analysis
  • Outputs of Perform Qualitative Risk Analysis
  • Risk Register Updates
  • Risk ranking for the project compared to other
    projects
  • List of prioritized risks and their probability
    and impact ratings
  • Risks grouped by categories
  • List of risks requiring additional analysis in
    the near term
  • List of risks for additional analysis and
    response
  • Watchlist (non-critical risks)
  • Trends

22
Perform Qualitative Risk Analysis
  • Perform Qualitative Risk Analysis can help you
    determine the following
  • Which risks need to move on to Perform
    Quantitative Risk Analysis?
  • Which of your projects should be selected when
    compared with other projects?
  • You have two projects available and you can
    only complete one of them, both projects are
    projected to have the same benefit, but the
    qualitative risk score for one of the projects is
    higher than the other, would you want to know
    this before you decided which project you would
    work on?

23
Perform Quantitative Risk Analysis
  • This is the phase of risk management where you
    conduct a numerical analysis of the probability
    and impact of the risks with the highest risk
    rating score determined from qualitative analysis
  • Things to remember
  • Quantitative analysis is used to.
  • Determine which of your risks should have a
    response plan
  • Determine overall project risk
  • Determine the probability of delivering your
    project objectives

24
Perform Quantitative Risk Analysis
  • Things to remember
  • Determine cost and schedule reserves
  • Identify risks that will require more planning
  • Create more realistic and achievable cost,
    schedule, or scope goals

25
Perform Quantitative Risk Analysis
  • Tools and Techniques of Quantitative Analysis
  • Sensitivity Analysis Which risks will have the
    most impact on the project?
  • Monte Carlo Analysis A technique that uses
    simulation to show the probability of completing
    your project on time and within budget.
  • Determines the overall risk of the project, not
    the task
  • Determines the probability of completing the
    project on a specific day and for a specific cost
  • Takes into account path convergence (places in
    the network diagram where many paths converge
    into one activity)
  • Used to evaluate the impact to your schedule and
    budget
  • Due to the complicated mathematical computations
    used, Monte Carlo analysis is usually done with a
    computer program
  • Creates a probability distribution triangular,
    normal, beta, uniform or lognormal (learn these)
  • Perform Quantitative Risk Analysis is a
    numerical analysis

26
Perform Quantitative Risk Analysis
Tools and Techniques of Quantitative
Analysis EMV Expected Monetary Value What is
the probability of the risk occurring multiplied
by the impact if the risk does occur? If the risk
occurs, what could the financial or time loss be
to your project? In the example below, this
project has an EMV of (58,250), this means that
you need to put aside 58,250 in your risk
reserve account for potential risks
27
Perform Quantitative Risk Analysis
  • Tools and Techniques of Quantitative Analysis
  • Decision Tree used for planning on individual
    risks instead of planning for the whole project
  • Takes into account future events to make a
    decision today
  • Can calculate the EMV in more complex situations
  • Involves mutual exclusivity

28
Perform Quantitative Risk Analysis
29
Perform Quantitative Risk Analysis
Decision Tree
It is cheaper to make the units rather than
buying them
30
Perform Quantitative Risk Analysis
  • Outputs of Perform Quantitative Risk Analysis
  • Risk Register Updates
  • Prioritized list of quantified risks
  • Amount needed for contingency reserves for time
    and cost
  • Confidence levels of completing the project on a
    certain date for a certain amount of money
  • The probability of delivering the project
    objectives
  • Trends - risk management is an iterative
    process as you repeat the process you can track
    your overall project risk and determine the trend
    (if you are decreasing or increasing the level of
    risk on your project)

31
Plan Risk Response
  • This is the phase of risk management where you
    decide how you will respond to your most
    important risks
  • Risk Response Strategies
  • Threats
  • Avoid remove the cause of the risk so that it
    never materializes
  • Mitigate reduce the probability and or impact
    of the risk
  • Transfer transfer the risk to another party
    usually done with insurance, performance bonds,
    warranties, guarantees or outsourcing the work.
  • Opportunities
  • Exploit make sure the opportunity occurs, you
    can add work or make a change to the project
  • Enhance increase the probability and or
    positive impact of the risk
  • Share share the opportunity with a third party
    to be able to take advantage of the opportunity

32
Plan Risk Response
  • Risk Response Strategies
  • For both Threats Opportunities
  • Accept
  • Active acceptance preparing a contingency
    reserve of cost or time reserves in case the risk
    does happen
  • Passive acceptance preparing for the dealing
    with the effects of the risk after the risk has
    occurred

33
Plan Risk Response
  • Outputs of Risk Response Planning
  • Project Management Plan Updates Changes made
    due to risk management will be changes made to
    the project and should be updated in the project
    management plan
  • Updates to Risk Register
  • Residual Risks risks that are left over after
    Plan Risk Response
  • Contingency Plans plans of action in case the
    risk does occur
  • Risk Response Owners the person on the team
    responsible for monitoring the risk, risk
    triggers, developing a response strategy, and
    implementing the strategy should the risk occur
  • Secondary Risks new risks that result from the
    implementation of the contingency plans for the
    primary risks

34
Plan Risk Response
  • Outputs of Risk Response Planning
  • Updates to Risk Register
  • Risk Triggers early warning signs that there is
    a high probability the risk will occur
  • Fallback Plans a secondary contingency plan, in
    case the contingency plan does not work or is not
    effective
  • Reserves
  • Contingency reserves - covers the cost for
    known unknowns discovered during risk
    management covers the residual risks. The
    contingency reserve is calculated and made part
    of the baseline.
  • Management reserves these are estimated and
    made part of the project budget, not the
    baseline. Management approval is needed to use
    the management reserve.

35
Monitor and Control Risks
  • This is the phase of risk management where you
    monitor the risk list for risks that have a
    higher probability of affecting your project, and
    the risk watchlist for risks that could change
    and should either be added to the risk list or
    removed from the watchlist
  • Inputs to Monitor Control Risks
  • Risk Management Plan
  • Risk Register
  • Approved Change Requests
  • Work performance information
  • - Deliverable status
  • - Schedule progress
  • - Costs incurred
  • Performance reports

36
Monitor and Control Risks
  • Things to Know
  • Workaround a response to a risk that has
    occurred when no contingency plan exists
  • Risk audit a team of experienced project team
    members reviews the risk management process and
    response strategies to see if youve effectively
    identified the major risks on the project and
    developed effective strategies for dealing with
    them
  • Risk Reassessment Risk management is iterative,
    you should review the risks on your project
    throughout the project to update their
    qualitative and quantitative values
  • the earlier you know about risk, the better
    prepared you will
  • be

37
Monitor and Control Risks
  • Things to Know
  • Status meetings status meetings should be used
    to identify new risks or changes to existing
    risks. This is a great opportunity to discuss
    with your team and stakeholders existing risks
    and new risks
  • Reserve analysis has the reserve kept up with
    changes to the risk list? Does the reserve still
    cover the costs of these risks should they occur?
  • Closing of risks Risks are expected to happen
    during a particular phase of the project. When
    that phase has passed and the risk is no longer
    probable, the risk should be removed from the
    risk list and any reserve associated should be
    freed up

38
Monitor and Control Risks
  • Outputs of Monitor Control Risks
  • Updates to Risk Register
  • Outcomes of the risk reassessments and risk
    audits
  • Updates to previous parts of risk management
  • Closing of risks that are no longer applicable
  • Details of what happened when risks occurred
  • Lessons learned
  • Requested Changes
  • Recommended Corrective Preventive Actions
  • Updates to the Project Management Plan
  • Organizational Process Assets Updates

39
Project Risk Management Review
  • Plan Risk Management
  • Inputs
  • Project Scope Statement
  • Cost Management Plan
  • Schedule Management Plan
  • Communications Management Plan
  • Enterprise Environmental Factors
  • Organizational Process Assets
  • Tools Techniques
  • Planning Meetings and Analysis
  • Output
  • Risk Management Plan

40
Project Risk Management Review
  • Identify Risks
  • Inputs
  • Risk Management Plan
  • Activity Cost Estimates
  • Activity Duration Estimates
  • Scope Baseline
  • Stakeholder Register
  • Cost Management Plan
  • Schedule Management Plan
  • Quality Management Plan
  • Project Documents
  • Enterprise Environmental Factors
  • Organizational Process Assets

41
Project Risk Management Review
  • Identify Risks
  • Tools Techniques
  • Documentation Reviews
  • Information Gathering Techniques
  • Checklist Analysis
  • Assumptions Analysis
  • Diagramming Techniques
  • SWOT Analysis
  • Expert Judgment
  • Outputs
  • Risk Register

42
Project Risk Management Review
  • Perform Qualitative Risk Analysis
  • Inputs
  • Risk Register
  • Risk Management Plan
  • Project Scope Statement
  • Organizational Process Assets
  • Tools Techniques
  • Risk Probability and Impact Assessment
  • Probability and Impact Matrix
  • Risk Data Quality Assessment
  • Risk Categorization
  • Risk Urgency Assessment
  • Expert Judgment

43
Project Risk Management Review
  • Perform Qualitative Risk Analysis
  • Outputs
  • Risk Register Updates

44
Project Risk Management Review
  • Perform Quantitative Risk Analysis
  • Inputs
  • Risk Register
  • Risk Management Plan
  • Cost Management Plan
  • Schedule Management Plan
  • Organizational Process Assets
  • Tools Techniques
  • Data Gathering and Representation Techniques
  • Quantitative Risk Analysis and Modeling
    Techniques
  • Expert Judgment
  • Outputs
  • Risk Register Updates

45
Project Risk Management Review
  • Plan Risk Responses
  • Inputs
  • Risk Register
  • Risk Management Plan
  • Tools Techniques
  • Strategies for negative risks or threats
  • Strategies for positive risks or opportunities
  • Contingent Response Strategies
  • Expert Judgment

46
Project Risk Management Review
  • Plan Risk Responses
  • Outputs
  • Risk Register Updates
  • Risk-Related Contract Decisions
  • Project Management Plan Updates
  • Project Document Updates

47
Project Risk Management Review
  • Monitor Control Risks
  • Inputs
  • Risk Register
  • Project Management Plan
  • Work Performance Information
  • Performance Reports
  • Tools Techniques
  • Risk Reassessment
  • Risk Audits
  • Variance and Trend Analysis
  • Technical Performance Measurement
  • Reserve Analysis
  • Status Meetings

48
Project Risk Management Review
  • Monitor Control Risks
  • Outputs
  • Risk Register Updates
  • Organizational Process Assets Updates
  • Change Requests
  • Project Management Plan Updates
  • Project Document Updates

49
Project Risk Management
  • Other Sources of Information
  • A Guide to the Project Management Body of
    Knowledge (PMBOK Guide)
  • PMP Exam Prep Rita Mulcahy
  • Project Management A Systems Approach to
    Planning, Scheduling, and Controlling Harold
    Kerzner
  • Hot Topics Flashcards for Passing the PMP and
    CAPM Exams Rita Mulcahy

50
Contact
  • Scott Reynolds
  • scottdreynolds_at_hotmail.com
  • Please send me comments, questions, or anything
    else,
  • Thanks Everyone for your time!
Write a Comment
User Comments (0)
About PowerShow.com