Title: Industrial Design Application for Power Distribution over Extra-Long Distances
1Industrial Design Application for Power
Distribution over Extra-Long Distances
- Or
- Lots of Wire Little Vd
Robert A Durham, PE New Dominion, LLC Tulsa, OK
Marcus O Durham, PhD, PE THEWAY Corp Tulsa, OK
2Introduction
- Typical petrochemical installations
- Geographically confined
- Large loads
- Utility installations
- Geographically dispersed
- Distributed loads
- Large loads over large distance
- cause unique problems
3IntroductionGoals
- Downtime eliminated
- Protection system isolates faults
- Total system voltage gt 95
- Contingency is bi-directional feed
- Adequate Ampacity to prevent sags
4Loads
- Primary loads
- 150 400 Hp, 2400 VAC
- 2 pole, low inertia
- Steep speed-torque curve
- Centrifugal pumps
- Eff ? 80, pf ? 78
5Loads
- Secondary Loads
- 1000 Hp, 2400VAC
- 4 pole, induction machines
- Reciprocating compressors
6LoadsStarting
- Primary Loads (150 400 Hp)
- Generally started across the line
- Some use VFD
- Inherent robustness of system adequate
7LoadsStarting
- Secondary Loads (1000 hp)
- Vd caused by starting trips primary load
- Need soft start 60 FLA
8Geography
- System spread over 900 square miles
- Main trunk line 25 miles in length
- Radial lines 1 12 miles long
- Each radial 1 5 MW
9Design Philosophy
- Difference between utility industrial
- - purely a matter of economics
- Utility Downtime loss of electric sales
- Industrial Downtime loss of production sales
- Damage to production may be unrecoverable
- Industrial has much larger risk
10Construction Management
- Emphasis on elimination of maintenance
- Contractors used on day work basis
11Environmental Controls
- ROW clearing
- 60 - 100 wide
- leave root balls for erosion control
- treat with herbicide
- 95 of recovered product is waste
- Extensive load shedding and motor control
- used to ensure responsible disposal
12Meteorological Considerations
- Temperature range 23C to 47C
- Thunderstorms 55 isoceraunic days
- Ice Heavy ice
loading area - Wind Basic winds 80
MPH - Severe Heart of Tornado
Alley - Seismic Occasional
earthquake - No applicable industry standards
- Build above utility standards
13Table 1 Line Construction Practices
Conductor Industrial Utility
Size (ACSR) Span Span
477 kcmil 64 m (210 ft) 76 m (250 ft)
4/0 69 m (225 ft) 76 m (250
ft)
1/0 69 m (225 ft) 90 m (295
ft)
2 76 m (250 ft) 90 m (295
ft)
Add 4 poles / mile (1.63 km)
14Results of Philosophy
- Recent winter storm
- Severe icing in region
- Some areas w/o utility for 30 days
- The system discussed here
- single incidence of blown fuses
- no line on ground
15Supply
- Most loads this size served from transmission
- Limited number of 69 /138 kV lines in area
- Supply taken at distribution levels
16Supply
- Supply taken at distribution levels
- Many areas served from REC lines
- Some dedicated 138/25kV subs
- At dedicated subs, voltage as high as 120
assists with voltage conditions
17Electrical Constraints
- Wire size based on ampacity- Sag
- Here, voltage drop is main concern
- Low power factor contributes
- Main trunk line 477 ACSR
- Main branch feeders 4/0 ACSR
- Individual load service 2 ACSR
18Capacitors
- With no correction system at 80 pf
- Standard place caps on lines
19Capacitors
- Extensive load shedding system
- can trip large quantities of load
- Resulting excessively leading pf
- can damage equipment, cause trips
- Must switch caps with load shed
- Place oil reclosers or sectionalizers
- at each 25kV cap bank
20Capacitors - Options
- Place medium
- voltage caps
- at motors
- Automatically
- switch w/ load
- Nearest to load
- Can downsize
- transformers
- and fuses
- Cost less than
- oil switches
21Overcurrent Protection
- Two unique systems
- Protect motor transformer (load point)
- Protect system from cascading faults
22Overcurrent Protection
- Load points protected with fused cutouts
- Fuse links sized tightly to avoid extra trips
- Use high speed (X speed) fuse links
23Overcurrent ProtectionMain Line Cutouts
- High risk of single phasing motors
- High rating of fuses makes coordination with
utility difficult - Electric storms cause unacceptable of
outages due to arrestor operation - Outages require electrician to restore power
- excessive downtime
24Overcurrent ProtectionMain Line Reclosers
- Oil reclosers placed at utility supply point
- and each main branch feeder
- (2MW or greater load)
- Oil reclosers placed along trunk every 10 MW
25Overcurrent ProtectionMain Line Reclosers
- Main line reclosers use ?processor relays
- Branch reclosers can use
- plug-setting type relays
- ?processor when available
26Lightning
- Lightning is a major concern in this area
- 55 isoceraunic days per year
- odds of induced or direct strike high
- Lightning arrestors
- placed every 1500 1700 feet
- Excellent ground system is imperative
27Effective Grounding
- Multi-point ground required
- Personnel safety
- Equipment protection
- Length of system 1 factor
- L of ground wire ? length
- Long distance high Z
- Single point ground
- Does Not Exist
28Computer Modeling Selection
- Cost - 10,000
- Cost - Approximately two weeks
- engineering time
- Numerous products on the market
- Two are usable for this type design
- One was selected based on
- overhead line modeling capabilities
29Computer ModelingProcedures
- Build single motor model for each service point
- Create motor subsystem consisting of
- motor, transformer, switches, etc
- Combine several subsystems
- on a sub-trunk feeder
30Computer ModelingProcedures
- Tie sub-trunk feeders to main trunk line
- Add detail for protection devices, fuses,
switches, capacitor, microprocessor relays, motor
protection devices
31MOTOR1
184 HP
CONT5
FUSE101
FUSE12
CAP27
120 kvar
T6
225 kVA
SCHEMATICMOTOR MODEL
FUSE13
32Computer ModelingUses
- Original model created as
- design tool before any construction
- Allowed alternatives for
- conductor size, lengths, protection
- Used model during construction for communication
with crews
33Computer ModelingUses
- Refined model for operations
- voltage drop, current, power factor
- Updated model for system upgrades
- Recent upgrade netted 8 reduction
- in electric bill 6 month payout
34Review Goals
- Downtime eliminated
- Protection system isolates faults
- Total system voltage gt 95
- Contingency is bi-directional feed
- Adequate Ampacity to prevent sags
35Computer modelingSystem Results
- Under normal conditions voltage drop is 8
- Supply voltages at 115 allow for continuous
operation under contingency - Advanced coordination of protection allowed
advanced devices with little on-site prep - Properly coordinated protection shields
equipment w/o unnecessary downtime
36Conclusions
- Uncommon spread out industrial system
- Semi-utility design uniquely industrial ops
- Enhanced specs, gt cost, more reliable
- w/o computer, complex system impossible
- Design, construction, operations, mgt.
- One engineer
37Conclusion
- Conclusively With the aid of modern tools, a
system can be designed that - can meet industrial needs
- in a utility environment
- with environmental astuteness
- by a single engineer
38QUESTIONS?