Industrial Design Application for Power Distribution over Extra-Long Distances - PowerPoint PPT Presentation

1 / 38
About This Presentation
Title:

Industrial Design Application for Power Distribution over Extra-Long Distances

Description:

... loads over large distance cause unique problems Introduction Goals Downtime eliminated Protection system isolates faults ... transformer (load point) Protect ... – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 39
Provided by: thewaycor
Category:

less

Transcript and Presenter's Notes

Title: Industrial Design Application for Power Distribution over Extra-Long Distances


1
Industrial Design Application for Power
Distribution over Extra-Long Distances
  • Or
  • Lots of Wire Little Vd

Robert A Durham, PE New Dominion, LLC Tulsa, OK
Marcus O Durham, PhD, PE THEWAY Corp Tulsa, OK
2
Introduction
  • Typical petrochemical installations
  • Geographically confined
  • Large loads
  • Utility installations
  • Geographically dispersed
  • Distributed loads
  • Large loads over large distance
  • cause unique problems

3
IntroductionGoals
  • Downtime eliminated
  • Protection system isolates faults
  • Total system voltage gt 95
  • Contingency is bi-directional feed
  • Adequate Ampacity to prevent sags

4
Loads
  • Primary loads
  • 150 400 Hp, 2400 VAC
  • 2 pole, low inertia
  • Steep speed-torque curve
  • Centrifugal pumps
  • Eff ? 80, pf ? 78

5
Loads
  • Secondary Loads
  • 1000 Hp, 2400VAC
  • 4 pole, induction machines
  • Reciprocating compressors

6
LoadsStarting
  • Primary Loads (150 400 Hp)
  • Generally started across the line
  • Some use VFD
  • Inherent robustness of system adequate

7
LoadsStarting
  • Secondary Loads (1000 hp)
  • Vd caused by starting trips primary load
  • Need soft start 60 FLA

8
Geography
  • System spread over 900 square miles
  • Main trunk line 25 miles in length
  • Radial lines 1 12 miles long
  • Each radial 1 5 MW

9
Design Philosophy
  • Difference between utility industrial
  • - purely a matter of economics
  • Utility Downtime loss of electric sales
  • Industrial Downtime loss of production sales
  • Damage to production may be unrecoverable
  • Industrial has much larger risk

10
Construction Management
  • Emphasis on elimination of maintenance
  • Contractors used on day work basis

11
Environmental Controls
  • ROW clearing
  • 60 - 100 wide
  • leave root balls for erosion control
  • treat with herbicide
  • 95 of recovered product is waste
  • Extensive load shedding and motor control
  • used to ensure responsible disposal

12
Meteorological Considerations
  • Temperature range 23C to 47C
  • Thunderstorms 55 isoceraunic days
  • Ice Heavy ice
    loading area
  • Wind Basic winds 80
    MPH
  • Severe Heart of Tornado
    Alley
  • Seismic Occasional
    earthquake
  • No applicable industry standards
  • Build above utility standards

13
Table 1 Line Construction Practices
Conductor Industrial Utility
Size (ACSR) Span Span
477 kcmil 64 m (210 ft) 76 m (250 ft)
4/0 69 m (225 ft) 76 m (250
ft)
1/0 69 m (225 ft) 90 m (295
ft)
2 76 m (250 ft) 90 m (295
ft)
Add 4 poles / mile (1.63 km)
14
Results of Philosophy
  • Recent winter storm
  • Severe icing in region
  • Some areas w/o utility for 30 days
  • The system discussed here
  • single incidence of blown fuses
  • no line on ground

15
Supply
  • Most loads this size served from transmission
  • Limited number of 69 /138 kV lines in area
  • Supply taken at distribution levels

16
Supply
  • Supply taken at distribution levels
  • Many areas served from REC lines
  • Some dedicated 138/25kV subs
  • At dedicated subs, voltage as high as 120
    assists with voltage conditions

17
Electrical Constraints
  • Wire size based on ampacity- Sag
  • Here, voltage drop is main concern
  • Low power factor contributes
  • Main trunk line 477 ACSR
  • Main branch feeders 4/0 ACSR
  • Individual load service 2 ACSR

18
Capacitors
  • With no correction system at 80 pf
  • Standard place caps on lines

19
Capacitors
  • Extensive load shedding system
  • can trip large quantities of load
  • Resulting excessively leading pf
  • can damage equipment, cause trips
  • Must switch caps with load shed
  • Place oil reclosers or sectionalizers
  • at each 25kV cap bank

20
Capacitors - Options
  • Place medium
  • voltage caps
  • at motors
  • Automatically
  • switch w/ load
  • Nearest to load
  • Can downsize
  • transformers
  • and fuses
  • Cost less than
  • oil switches

21
Overcurrent Protection
  • Two unique systems
  • Protect motor transformer (load point)
  • Protect system from cascading faults

22
Overcurrent Protection
  • Load points protected with fused cutouts
  • Fuse links sized tightly to avoid extra trips
  • Use high speed (X speed) fuse links

23
Overcurrent ProtectionMain Line Cutouts
  • High risk of single phasing motors
  • High rating of fuses makes coordination with
    utility difficult
  • Electric storms cause unacceptable of
    outages due to arrestor operation
  • Outages require electrician to restore power
  • excessive downtime

24
Overcurrent ProtectionMain Line Reclosers
  • Oil reclosers placed at utility supply point
  • and each main branch feeder
  • (2MW or greater load)
  • Oil reclosers placed along trunk every 10 MW

25
Overcurrent ProtectionMain Line Reclosers
  • Main line reclosers use ?processor relays
  • Branch reclosers can use
  • plug-setting type relays
  • ?processor when available

26
Lightning
  • Lightning is a major concern in this area
  • 55 isoceraunic days per year
  • odds of induced or direct strike high
  • Lightning arrestors
  • placed every 1500 1700 feet
  • Excellent ground system is imperative

27
Effective Grounding
  • Multi-point ground required
  • Personnel safety
  • Equipment protection
  • Length of system 1 factor
  • L of ground wire ? length
  • Long distance high Z
  • Single point ground
  • Does Not Exist

28
Computer Modeling Selection
  • Cost - 10,000
  • Cost - Approximately two weeks
  • engineering time
  • Numerous products on the market
  • Two are usable for this type design
  • One was selected based on
  • overhead line modeling capabilities

29
Computer ModelingProcedures
  • Build single motor model for each service point
  • Create motor subsystem consisting of
  • motor, transformer, switches, etc
  • Combine several subsystems
  • on a sub-trunk feeder

30
Computer ModelingProcedures
  • Tie sub-trunk feeders to main trunk line
  • Add detail for protection devices, fuses,
    switches, capacitor, microprocessor relays, motor
    protection devices

31
MOTOR1
184 HP
CONT5
FUSE101
FUSE12
CAP27
120 kvar
T6
225 kVA
SCHEMATICMOTOR MODEL
FUSE13
32
Computer ModelingUses
  • Original model created as
  • design tool before any construction
  • Allowed alternatives for
  • conductor size, lengths, protection
  • Used model during construction for communication
    with crews

33
Computer ModelingUses
  • Refined model for operations
  • voltage drop, current, power factor
  • Updated model for system upgrades
  • Recent upgrade netted 8 reduction
  • in electric bill 6 month payout

34
Review Goals
  • Downtime eliminated
  • Protection system isolates faults
  • Total system voltage gt 95
  • Contingency is bi-directional feed
  • Adequate Ampacity to prevent sags

35
Computer modelingSystem Results
  • Under normal conditions voltage drop is 8
  • Supply voltages at 115 allow for continuous
    operation under contingency
  • Advanced coordination of protection allowed
    advanced devices with little on-site prep
  • Properly coordinated protection shields
    equipment w/o unnecessary downtime

36
Conclusions
  • Uncommon spread out industrial system
  • Semi-utility design uniquely industrial ops
  • Enhanced specs, gt cost, more reliable
  • w/o computer, complex system impossible
  • Design, construction, operations, mgt.
  • One engineer

37
Conclusion
  • Conclusively With the aid of modern tools, a
    system can be designed that
  • can meet industrial needs
  • in a utility environment
  • with environmental astuteness
  • by a single engineer

38
QUESTIONS?
Write a Comment
User Comments (0)
About PowerShow.com