Title: Development of a GIS Network for Pavement Management Systems
1Development of a GIS Network for Pavement
Management Systems
United Arab Emirates University Faculty of
Engineering Graduation Project II
2Project Objectives
- The Main objectives are
- Developing a scientifically sound cost effective
PMS. - Using this system to evaluate pavement condition
, maintenance cost and ranking the pavement
section. - Supporting this system with a GIS database.
3Introduction
- Project classification.
- Design analyses (ABET criterion).
- Distress is any irregularity in the pavement
that may effect the ride quality. - PMS is a set of tools that help the decision
makers to select the best way of M R for a
particular Pavement. - PMS is used to optimize resources.
4Introduction
- Present condition index PCI is used as an
indicator of the pavement condition. - GIS is defined as a combination of layers of
information that is related to a specific place. - These layers give the decision makers better
understanding of the place.
5Distresses Classified as
Functional Improper drainage. Drying and wetting
Structural High load repetitions. High tire
pressure.
6Samples of Pavement Distresses
7Samples of Pavement Distresses
8Approaches to Select M R Alternatives
- Ad Hoc
- Depends on past experience.
- Few M R alternatives.
- Best alternative may not be selected.
- Present Condition
- Depends on the exist condition.
- The selected M R will improve the pavement
condition, but it may not be the most cost
effective solution. -
-
- Life Cycle
- Depends on the exist and future condition.
- The selected M R is the most suitable and cost
effective solution.
9Summary of Project Tasks
- Literature review
- Library and internet search for information
about - Pavement distresses.
- PMS.
- GIS.
- Data collection (For three sections in Al Ain)
- Distress types.
- Severity.
- Intensity.
- Base map development (Stage 1).
10Summary of Project Tasks
- Base map development (Stage 2).
- MS EXCEL sheet
- PCI.
- Cost.
- Spatial Data Analyses
11Section Definition
- The selected network was divided into smaller
parts called sections for managerial purpose. - The entire section should have the same
- Pavement Structure.
- Traffic.
- Construction History.
- Pavement Rank.
- Drainage.
- Condition.
- The section dimensions are
- Length 1500 m
- Width 7.5 m
12Divide section into S U
Pavement Condition Survey Rating Procedure
Determine number of S U to be surveyed
Calculate the PCI
Perform condition survey
13Dividing the Section into Sample Units
- The selected section was divided into sample
units for the purpose of inspection. - Each sample unit should have an area of
- 160 to 320 m2.
- The selected dimensions of each sample unit
(figure). - The total number of sample units N 50 S U.
14Determining the Number of units to be Surveyed
- In Project level inspection the following
procedure is followed
Step 1
Determine the minimum number of Sample units (n).
15Step 2
Determine the interval. Interval N/n 50/13
3.8 Interval 3
Step 3
Select the first S U Randomly, then use the
interval to select next S Us.
16Field Inspection
- Inspection sheet was used to record distress
- Type.
- Severity.
- Quantity.
17Inspection Sheet
18Distresses
19PCI Calculation Procedure
- Step1 Determine deduct values.
- Calculate the density percentage.
- Density (Quantity /S U Area) 100
- Determine the deduct value form the Deduct value
curves.
20PCI Calculation Procedure
- Step 2 Determine the maximum allowable number of
deducts (m). - Determine the maximum allowable number of
deducts. m 1 (9/98)(100- HDV). - Reduce the number of deduct values to m. if the
deduct values are fewer than m, then all of the
deduct values should be taken. - List the deduct values in a descending order.
21(No Transcript)
22PCI Calculation Procedure
- Step 3 Determine the maximum number of corrected
deduct value (CDV). - Determine the number of deducts gt2, q.
- Determine the total deduct values by adding all
individual deduct values.
23PCI Calculation Procedure
- Determine the CDV form q and total deduct value
for the first iteration by looking for the
appropriate correction curve.
24PCI Calculation Procedure
- Set the minimum deduct value gt2 to 2 in the next
iteration and repeat the steps. - Select the maximum CDV form the calculated CDVs
as the largest value. - Step 4 Calculate PCI by subtracting the maximum
CDV form 100.
25(No Transcript)
26Excel Sheet Preparation
- a program was made to calculate the PCI and
maintenance cost. - PCI calculation procedure was used in Excel.
- The benefit of this program is to save time and
effort that may spent in manual calculation.
27Procedure
- The deduct value curves for each severity level
were best fitted using MS Excel .
28Procedure
- Points were taken on the curves of alligator
cracking and the x and y values for each point
were recorded.
29Procedure
- The relation between the density and deduct value
of the curve were drawn and the equation of each
severity level curve was determined.
30Procedure
- Two or more equations were determined for each
curve to get accurate results. - The same steps were done to get CDV equations.
Excel Sheet
31Critical PCI Value
- Critical PCI is the PCI value at which the rate
of PCI loss increases with time. - Usually this value ranges form 70 to 55 .
32Methods of M R
1- Stop Gap It is defined as the M R
needed to keep the pavement operational
in a safe condition.
2- Preventive It is defined as the M R
activities applied to the pavement to slow the
rate of deterioration.
3- Major It is defined as the M R
activities applied to the entire section to
improve or correct the pavement condition.
331- Stop Gap
- Called safety stop gap.
- Applied for localized segments of pavement
section. - Applied with PCI lt Critical PCI.
342- Preventive
- Divided into two types, localized and global.
- Localized applied on specific parts of the
section. -
- Global applied on the entire section.
- Applied on sections with PCI gt Critical PCI.
353-Major
- Applied on the entire section to repair the
severe distresses. - Applied on sections with PCI lt Critical PCI.
- Consists of Two types, full reconstruction and
thick overlay. - The section PCI will resume to 100.
36(No Transcript)
37GIS Map Development
- Three maps were drawn using Auto CAD.
- The maps were imported to MapInfo.
38GIS Map Development
- Each sample unit were represented on the map.
39GIS Map Development
- Tables were created to store sample units data.
40Conclusion
- Tasks for this semester were completed.
- The data for the three selected sections were
collected. - Base map were prepared to enter distress data for
each sample unit. -
41Thank You.