Chapter 16 Material Requirements Planning How much of an - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Chapter 16 Material Requirements Planning How much of an

Description:

Chapter 16 Material Requirements Planning How much of an item is needed? When is an item needed to complete a specified number of units... in a specified period of time? – PowerPoint PPT presentation

Number of Views:281
Avg rating:3.0/5.0
Slides: 33
Provided by: cobhomepa
Category:

less

Transcript and Presenter's Notes

Title: Chapter 16 Material Requirements Planning How much of an


1
Materials Requirements Planning
  • Chapter 16

2
Material Requirements Planning
  • How much of an item is needed?
  • When is an item needed to complete
  • a specified number of units...
  • in a specified period of time?
  • Dependent demand drives MRP

3
Dependent/Independent Demand
  • independent demand
  • customer demand for final product (could be
    customer at next work station)
  • dependent demand
  • demand for component used to build final
    product

4
Master Production Schedule (MPS)
  • Time-phased plan specifying how many and when the
    firm plans to build each end item

Master Production Schedule
5
Master Production Schedule Functions
  • Schedules production and purchases
  • Principal input to MRP schedule
  • Basis for determining resource requirements
  • Provides basis for making delivery promises to
    customers

6
Information Inputs to the MPS
  • demand data
  • Marketing forecasts
  • Sales orders
  • inventory status
  • on hand inventory
  • safety stock levels
  • production data
  • processing times (lead times)

7
Terminology
  • Parent item An item manufactured from one or
    more components.
  • Component An item that goes into one or more
    parent items.
  • Bill of Materials (BOM) A diagram or record that
    shows all components going into an item and the
    usage quantities.

8
Bill of Materials (BOM) FileA Complete Product
Description
  • Materials
  • Parts
  • Components
  • Production sequence
  • Modular BOM
  • Subassemblies
  • Planning BOM
  • Fractional options

9
Bill-of-Material Product Structure Tree
Bicycle(1)
P/N 1000
Handle Bars (1)
Frame Assy (1)
P/N 1001
P/N 1002
Wheels (2)
Frame (1)
P/N 1003
P/N 1004
10
Terminology
  • Usage quantity Number of units of components
    needed to make one unit of parent.
  • Part commonality Degree to which a part has more
    than one parent.
  • End Item A parent, but not a component,typically
    a final product.

11
Bill-of-Material Product Structure Tree
Bicycle(1)
P/N 1000
Handle Bars (1)
Frame Assy (1)
P/N 1001
P/N 1002
Wheels (2)
Frame (1)
P/N 1003
P/N 1004
12
Terminology
  • Intermediate Item An item with at least one
    parent and at least one component.
  • Subassembly Special case of intermediate item
    it is assembled from more than one component.
  • Purchased Item An item with no components,
    coming from a supplier.

13
Time Fences
  • Frozen
  • No schedule changes allowed within this window
  • Moderately Firm
  • Specific changes allowed within product groups as
    long as parts are available
  • Flexible
  • Significant variation allowed as long as overall
    capacity requirements remain at the same levels

14
Time Fences
Moderately Firm
Frozen
Flexible
Capacity
Forecast and available capacity
Firm Customer Orders
26
8
15
Weeks
15
Material Requirements Planning
  • Manufacturing computer information system
  • Determines quantity timing of dependent demand
    items

16
MRP Requirements
  • Computer system
  • Mainly discrete products
  • Accurate bill-of-material
  • Accurate inventory status
  • 99 inventory accuracy
  • Stable lead times


17
MRP Benefits
  • Increased customer satisfaction due to meeting
    delivery schedules
  • Faster response to market changes
  • Improved labor equipment utilization
  • Better inventory planning scheduling
  • Reduced inventory levels without reduced customer
    service

18
Structure of the MRP System
Master Production Schedule
BOM
(Bill-of-Material)
MRP by period report
Lead Times
MRP by date report
(Item Master File)
MRP Programs
Planned orders report
Inventory Data
Purchase requirements
Purchasing data
Exception reports
19
Material Requirements Planning
  • Based on a master production schedule, a MRP
    system
  • Creates schedules identifying the specific parts
    and materials required to produce end items
  • Determines exact numbers needed
  • Determines the dates when orders for those
    materials should be released, based on lead times

20
Example - Dependent Demand
Product Structure Tree for Assembly A Bill of
Material (BOM)
A
B(4)
C(2)
E(1)
D(2)
F(2)
D(3)
Create a schedule to satisfy demand.
21
LT 1 day
22
LT 2
Spares
A
B(4)
C(2)
E(1)
D(2)
F(2)
D(3)
23
Part D Day 6
A
40 15 spares
B(4)
C(2)
E(1)
D(2)
F(2)
D(3)
24
Inventory Records File
  • Each inventory item carried as a separate file
  • See, for example, Exhibit 16.15
  • Status according to time buckets
  • Pegging
  • Identify each parent item that created demand

25
Primary MRP Reports
  • Planned orders
  • to be released at a future time
  • Order release notices
  • to execute the planned orders
  • Changes in due dates of open orders due to
    rescheduling

26
Primary MRP Reports
  • Cancellations or suspensions of open orders
  • due to cancellation or suspension of orders on
    the master production schedule.
  • Inventory status data

27
Net Change System
  • Generation of intermediate schedules
  • Activity driven
  • Net change schedules
  • Potential for system nervousness

28
Another MRP Example
X
A(2)
B(1)
D(5)
C(2)
C(3)
Requirements include 95 units (80 firm orders
and 15 forecast) of X in week 10.
29
Adding some more terminology
  • Gross Requirements
  • On-hand
  • Net requirements
  • Planned order receipt
  • Planned order release

30
Requirements 95 units of X in Week 10
45
15
20
35
80
31
Released Planned Order Release
45
45
32
Lead Time
Item
On Hand
Required
2
X
50
45
15
3
A
75
1
B
25
20
2
C
10
35/40
80
2
D
20
33
45
45
15
15
20
20
40
35
35
40
80
80
34
Closed Loop MRP
Production Planning Master Production
Scheduling Material Requirements
Planning Capacity Requirements Planning
Feedback
Realistic?
No
Feedback
Yes
Execute Capacity Plans Material Plans
35
Manufacturing Resource Planning (MRP II)
  • Goal Plan and monitor all resources of a
    manufacturing firm (closed loop)
  • manufacturing
  • marketing
  • finance
  • engineering
  • purchasing
  • Simulate the manufacturing system

36
Enterprise Resource Planning
  • SAP - Systems, Applications, and
    Products in Data
    Processing
  • incorporates accounts payable, project planning,
    work force planning, etc. into MRP
  • Oracle

37
Enterprise Resource Planning (ERP) Systems Defined
  • Enterprise Resource Planning Systems is a
    computer system that integrates application
    programs in accounting, sales, manufacturing, and
    other functions in the firm.
  • This integration is accomplished through a
    database shared by all the application programs.

38
Financial Accounting
  • Financials
  • Controlling
  • Asset management

39
Human Resources
  • Payroll
  • Benefits administration
  • Applicant data administration
  • Personnel development planning
  • Workforce planning
  • Schedule shift planning
  • Time management
  • Travel expense accounting

40
Manufacturing Logistics
  • Materials management
  • Plant maintenance
  • Quality management
  • Production planning control
  • Project management system

41
Sales and Distribution
  • Prospect customer management
  • Sales order management
  • Configuration management
  • Distribution
  • Export controls
  • Shipping and transportation management
  • Billing, invoicing, and rebate processing

42
Reasons for Implementing SAP R/3
  • Desire to standardize and improve processes
  • To improve the level of systems integration
  • To improve information quality
Write a Comment
User Comments (0)
About PowerShow.com