Estimating Project Costs & Time - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Estimating Project Costs & Time

Description:

Estimating Project Costs & Time Project Management Unit, Lecture 5 Cost & Schedule Estimates As previously mentioned the principal measures of a project are cost ... – PowerPoint PPT presentation

Number of Views:701
Avg rating:3.0/5.0
Slides: 10
Provided by: laspaceLs
Category:

less

Transcript and Presenter's Notes

Title: Estimating Project Costs & Time


1
Estimating Project Costs Time
  • Project Management Unit, Lecture 5

2
Cost Schedule Estimates
  • As previously mentioned the principal measures of
    a project are cost, time (schedule) and
    performance
  • For a given project one or more of these measures
    may be constrained
  • For LA ACES your launch opportunity has a fixed
    date and you must have a payload ready by this
    date
  • Initial estimates on cost and schedule are
    essential to determine if your plan is realistic
  • May need to plan for (or implement) trade-offs
    according to established priorities
  • Cost and schedule needs to be monitored
    throughout the project life-cycle

3
Factors affecting the estimate
  • Task Definition The completeness of your project
    definition will determine if all tasks have been
    taken into account.
  • People Productivity People do not focus on a
    task with 100 efficiency. The difference between
    calendar time and effort must be considered.
  • Project Structure A dedicated project team will
    be able to focus its effort on completing the
    project effectively.
  • Padding People may increase estimates to take
    into account unknown risks and this may force an
    unnecessary trade-off.
  • Culture What is deemed acceptable behavior by
    the organization (e.g. padding vs. accuracy) will
    affect estimates.
  • Downtime Equipment repairs, holidays, vacations,
    exam schedules can all affect the time estimate.

4
Categories of estimates
  • The Macro or Top-Down approach can provide a
    quick but rough estimate
  • Done when the time and expense of a detailed
    estimate are an issue
  • Usually occurs during conception stage when a
    full design and WBS are not available
  • Requires experienced personnel to do the estimate
  • Can be highly inaccurate
  • A Micro or Bottom-Up approach can provide a
    fairly accurate estimate, but is time consuming
  • Takes into account the project design and a
    roll-up of WBS elements
  • May require multiple personnel and time to
    complete
  • If done properly, a bottom-up estimate can yield
    accurate cost and time estimates

5
Steps to developing the estimates
  • Start with a Macro estimate then refine with a
    Micro estimate
  • Develop the general project definition
  • Perform a macro cost and time estimate
  • Develop the detailed project definition and WBS
  • Roll-up the WBS elements as part of a micro
    estimate
  • Establish the project schedules
  • Reconcile differences between the macro and micro
    estimates

6
Macro Estimates
  • Scaling Given a cost for a previous project
    then an estimate for a new project can be scaled
    from the known cost. E.g NASA, at times, uses
    spacecraft weight to estimate total cost.
  • Apportion Given a similar previous project,
    costs for major subunits of the new project would
    be proportional to similar subunits in the
    previous project.
  • Weighted Variables Certain types of projects can
    be characterized by specific parameters (e.g.
    number of inputs, number of detector channels).
    Historical costs times for single units of
    these parameters are weighted by the numbers
    required for the new project.
  • Learning Curve If the same task is repeated a
    number of times there will be a cost / time
    savings relative to the first time the task is
    done.

7
Micro Estimates
  • Template Uses historical data to establish
    detailed costs and schedules for project
    subunits. A new project composed of some
    combination of these subunits can then be quickly
    estimated.
  • Ratio Similar to the Macro ratio method but
    applied to specific tasks associated with project
    subunits. For example, if it takes 1 day to
    build test a particular sensor unit, then an
    instrument with 10 sensors would take 2
    technicians, 5 days to complete.
  • WBS Roll-up Times and costs associated with the
    lowest level WBS work packages are estimated and
    then these are added or rolled-up to yield the
    costs for higher level units. This method
    provides the most accurate estimates at the
    expense of time devoted to developing the
    estimate.

8
Phased Approach
  • On a phased project, details over the entire
    life-cycle may not be immediately available.
  • During the each phase details for the remaining
    phases are refined, modified or changed.
  • In this case an alternate approach may be
    appropriate.
  • Develop the general project definition
  • Perform a macro cost and time estimate for all
    phases
  • Develop a detailed definition and WBS for the
    immediate phase
  • Roll-up the WBS elements as a micro estimate for
    the immediate phase
  • Establish a detailed schedule for the immediate
    phase
  • Reconcile differences between previous macro
    current micro estimates
  • Refine the macro cost and time estimate for the
    remaining phases
  • Refine the schedule for the remaining phases
  • Repeat items 3-8 just prior to next phases for
    the entire life-cycle

9
Guidelines for Estimates
  • Estimates should be done by the person most
    familiar with the task
  • If possible obtain estimates from several people
    and use the variance for risk assessment (lecture
    7)
  • Multiple estimates should be done independently
    to avoid GroupThink (lecture 1)
  • Base the estimates upon normal conditions.
  • Use consistent units when estimating task time.
  • Work package estimates should not include
    contingencies
  • Use a separate risk assessment (lecture 7) for
    estimating the affect of abnormal conditions and
    contingencies.
Write a Comment
User Comments (0)
About PowerShow.com