Title: HomeSafenet Implementation Status Update


1
HomeSafenet Implementation Status Update
  • Presentation to
  • Senate Health and Human Services Appropriations
    Committee
  • October 20, 2005

2
HomeSafenet Status Update
  • System Integrator Procurement
  • Status of Invitation to Negotiate (ITN)
  • Schedule for completion
  • Maintenance and Operation of Current System
  • Stability of Current System
  • Deployment of system fixes

3
Reasons for System Integrator Procurement
  • Current HomeSafenet system cannot be fixed to
    meet federal SACWIS requirements.
  • Necessary to procure systems integrator with
    expertise in SACWIS.
  • Procurement will properly align resources and
    reduce risks.
  • Invitation to Negotiate (ITN) method selected to
    competitively select the best vendor solution.

4
HSn System Integrator Procurement Objective
  • Deliver a federally certifiable SACWIS including
  • Integrated case management and performance
    management system.
  • Complete functionality to ensure child and adult
    safety, well-being and permanency
  • Case management
  • Resource and provider management
  • Financial management
  • Interfaces to other Florida systems
  • Single electronic record.

5
Procurement Milestones
  • February 28, 2005 Invitation to Negotiate
    submitted for ACF approval
  • July 6, 2005 Full federal approval received
  • July 14, 2005 ITN Posted
  • September 2005 Proposals Received
  • September October Technical Evaluation
  • October 12, 2005 Cost Reply Opening
  • October 24, 2005 Posting of Rankings
  • November December Negotiation Period
  • January 3, 2006 Posting of Intended Contract
    Award

6
Stabilizing Current System
  • Capacity upgrade in July 2005 to avoid service
    interruptions.
  • Improved software stability.
  • Changes restricted to critical fixes such as
    search functionality, federal reporting
    requirements, and federal or state statutory
    requirements such as psychotropic medication
    screens.

7
Utilization as Percentage of Capacity
Chart shows change in percentage of capacity used
after upgrade to new machine in June 2005.
8
HomeSafenet Users
  • Currently have 9,997 active user IDs (individual
    users may have several user IDs) Up from 7,000
    last year.
  • Average concurrent users up to almost 1,400 (from
    slightly over 1,000)
  • More than 1,700 peak concurrent users including
    DCF staff, Sheriffs offices, CBCs, Courts

9
Utilization in Prime Time
10
Project Status vs. Maintenance and Operation
  • Project status
  • Applies to new SACWIS system development.
  • Federal funding is provided for 50 percent of
    full costs.
  • Maintenance and Operations Status
  • Ongoing work to maintain and operate system.
  • Federal funding is at the administrative rate of
    50 percent of the portion of the cost attributed
    to the title IV-E eligible caseload.

11
Conclusion
  • Actions taken on the current system are focused
    on maintaining stability and fixing known
    defects, where cost beneficial.
  • Primary focus for FY 2005-06 year will be
    completing system integrator procurement and
    initiating retool of HomeSafenet.