The PiE Process Debby Valin, P2 Coordinator August 25, 2005 - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

The PiE Process Debby Valin, P2 Coordinator August 25, 2005

Description:

PiEs Unknown. P2 Assessment & Plan. PiE an Option. SF/LF CO. SF/LF CO. Final Report ... Ready to Make Some PiEs? What kind of PiE was shown in the Intro? ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 23
Provided by: val9
Category:

less

Transcript and Presenter's Notes

Title: The PiE Process Debby Valin, P2 Coordinator August 25, 2005


1
The PiE ProcessDebby Valin, P2
CoordinatorAugust 25, 2005
P2
Projects in Enforcement
2
Basis for PiEsFlorida Statutes CH. 403
  • Florida P2 Definition Act 403.031(8),
    403.072-074
  • Defines P2 as non-mandatory efforts to reduce or
    eliminate contamination or pollution before
    discharge
  • Goal of state agenciesto develop and implement
    P2 strategies
  • State policy that P2 is necessary for materials
    and waste management activities

3
Basis for PiEsDEP Directive 923
  • Settlement Guidelines P2 Credits - 9
  • Encourages enforcement staff to affirmatively
    consider/offer P2 option for penalty offset
  • Involves P2 projects negotiated in consent/final
    orders
  • Model SF / LF consent order documents and
    attachments are current
  • P2 projects represent process improvements
  • Up to 100 of the civil penalties may be offset
  • Applicable expenses are allowed a 11 offset
  • Cannot involve actions or costs required to
    comply


4
P2 Hierarchy
  • Reduction
  • Recycling
  • Treatment
  • Disposal

5
Acceptable P2 Project Categories
  • Source Reduction
  • Material use reduction
  • Process modification or elimination
  • Waste Minimization
  • Material substitution
  • Operation and maintenance changes
  • Training
  • Equipment upgrades
  • Recycling On-Site
  • Re-use materials and chemicals
  • Uses in other operations or processes
  • Extend the life of by- products
  • Water/energy conservation

6
Unacceptable P2 Categories
  • Treatment
  • Re-use or recycling off site
  • Pre-treating contaminants or removing water from
    wastes
  • Emission control devices
  • Disposal
  • Wastewater treatment
  • Land-filling
  • Incineration

7
P2 Opportunities
  • Raw material reduction/re-use
  • Process chemical reduction/substitution
  • Water conservation/re-use/recycling
  • Energy conservation or alternate forms
  • Solid waste
  • Air emissions
  • Industrial waste
  • Hazardous waste

8
P2 Benefits
  • Employee Health Safety
  • Protection of Public Health Environment
  • Reduced Risk of Liability
  • Reduced Regulatory Burden
  • Improved Image
  • Increased Efficiency
  • Cost Savings

9
PiE Considerations
  • Permanently improves a facilitys
    environmental performance and impact
  • Provides opportunities for media other than
    that targeted in enforcement
  • Involves pre-approved projects or research to
    determine potential projects
  • Responsible party volunteers or agrees
  • Not applicable where a history shows lack of
    integrity, competence or performance

10
PiE Requirements
  • Needs to result in a net decrease in the
    amount of toxicity of pollution released
  • Not a transfer among environmental
    media
  • Cannot include required corrective actions
  • Only specific costs and expenses can be
    claimed
  • DEP oversees project selection /
    implementation
  • Assessment
  • Planning
  • Reporting
  • DEP has legal recourse if project is rejected
    or PiE not properly implemented

11
PiE Process
  • Discuss a PiE with the responsible party
  • Offer free help from P2 Program staff
  • Facility assesses opportunities and identifies
    options with consultation
  • Facility implements / documents expenses
  • Report due upon completion
  • DEP P2/Case staff review and approve each step

12
PiE Flow Chart
PiEs Known
P2 Project Summary
SF/LF CO
PiE an Option
Final Report
PiEs Unknown
P2 Assessment Plan
SF/LF CO
13
Model PiE CO Docs Revised
  • Short-Form (SF) Consent Order
  • With P2 Language
  • Long-Form (LF) Consent Order P2 Paragraphs
  • P2 Project Attachments 3
  • 1 for SF LF COs when Projects are known
  • cost accounting IS needed
  • 1 for SF LF COs when Projects are known
  • cost accounting IS NOT needed
  • 1 for LFCO when Projects are UNKNOWN
  • Effective August 19, 2005 See OGC
    Enforcement Manual

14
Civil Penalty Offsets
  • Costs that can be considered
  • P2 Project Plan/Summary Preparation
  • P2 Project Design
  • P2 Project Installation
  • P2 Project Construction
  • P2 Project Testing
  • P2 Project Training
  • P2 Project Capital/Equipment

15
Civil Penalty Offsets
  • Costs that cannot be considered
  • P2 Opportunity Assessment/Reporting
  • Conceptual P2 Project Proposals
  • Maintenance Operation
  • Monitoring Reporting

16
PiE Short Form Consent Order Model
  • Specifies that ( 100) a certain dollar
    amount may be offset (less admin cost total)
  • States that P2 Project(s) is described in
    Exhibit___
  • (P2 Project Summary)
  • Reflects that P2 Project(s) must be
    implemented per Exhibit___
  • Requires P2 Project(s) must be started and
    completed in no later than ___ days
  • Re-iterates requirement for Final Report
  • Lack of timeliness will result in P2 Project
    forfeiture and payment of the civil penalty
    balance

17
PiE Long Form Consent Order Model
  • Specifies that ( 100) a certain dollar
    amount may be offset (less admin cost)
  • Requires notification within 15 days that the
    PiE option is chosen
  • States that P2 Project(s) must be used
    per paragraph___ if PiE option is chosen
  • P2 Projects Exhibit or P2 Project Summary are
    attached as Exhibit___
  • Asserts that requirements and time frames in
    Exhibit___ must be met

18
P2 Projects Exhibit
  • LF CO only
  • Describes what is P2 and the tri-archy of
    methods
  • Lays out a 5-step process
  • P2 Opportunity Assessment
  • P2 Project Plan
  • P2 Project Implementation
  • Progress Report
  • Final Report

19
P2 Project Summary ExhibitProject is Known
Cost is Certain
  • Project Description
  • Details
  • Completion date
  • Benefits
  • Savings at front-end
  • Savings at back-end
  • Quantitative figures
  • Project Cost
  • Projected cost for each component
  • Total should exceed the penalty offset amount
  • Final Report and Project Termination
  • Expense report
  • Receipts
  • Other documents itemizing costs expended

20
P2 Project Summary ExhibitProject is Known
Cost is Uncertain
  • Project Description
  • Details
  • Completion date
  • Benefits
  • Savings at front-end
  • Savings at back-end
  • Quantitative figures
  • Project Cost
  • Projected cost for each component
  • Should not include a lump sum
  • Progress and Final Reports
  • Expense report
  • Receipts
  • Other documents itemizing costs expended

21
P2 Project Summary Differences
  • Project is either known or unknown
  • Cost is known to meet or exceed offset amount
    or is uncertain
  • Final Report is due only or follows a Progress
    Report
  • Final Report is reviewed to determine whether
    Project was properly implemented only or which
    expenses apply toward P2 credits also

22
Ready to Make Some PiEs?
  • What kind of PiE was shown in the Intro?
  • What 2 Docs set the basis for P2/PiEs?
  • What is the P2 Hierarchy?
  • What are Acceptable P2 Categories?
  • What are Not Acceptable P2 Categories?
  • What are some sources of P2 Opportunities?
  • What are some P2 Benefits?
  • When would a PiE Not be allowed?
  • Does the PiE have to be tied to the violation
    source?
  • What is the penalty amount match ratio?
Write a Comment
User Comments (0)
About PowerShow.com