Citizen Bond Oversight Committee Update Administration Building Board Room June 8, 2006 6:00 PM Comm - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Citizen Bond Oversight Committee Update Administration Building Board Room June 8, 2006 6:00 PM Comm

Description:

La Porte ISD 2005 Bond Program. LPISD Program Management. Parsons -3D/I ... As each construction project is designed and contractor proposals are received, ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 19
Provided by: yashpa
Category:

less

Transcript and Presenter's Notes

Title: Citizen Bond Oversight Committee Update Administration Building Board Room June 8, 2006 6:00 PM Comm


1
Citizen Bond Oversight Committee
UpdateAdministration Building Board Room June
8, 2006 _at_ 600 PM Committee Rob Roy Co
Chair Ed Matuszak Co Chair Richard Ayres Joe
Gomer John Elfstrom Spiro Pomonis Richard
Passmore Lois Rogerson John Hagan Deanne
Thompson Gary Barton Christie Claypool Debbie
Wade
2
La Porte ISD Bond Public Website
IMPACTprogram IMPACTteam
3
(No Transcript)
4
LPISD Website http//sc.lpisd.org/education/distr
ict/district.php?sectionid1 Active Summary
Website http//www.3di.com/impact/LaPorte_ISD/bon
dproject.asp
5
Master Program Budget
6
Master Program Budget Methodology
  • The Master Budget is a living document that will
    be updated throughout the 2005 Bond Program.
  • As each construction project is designed and
    contractor proposals are received, actual results
    will be accounted for and reported.
  • Long Range Master Plan Compass
  • Master Program Schedule provided constraints
    for inflation allocation

7
(No Transcript)
8
La Porte ISD Project Updates
9
Administration Building Roof Schedule Update
  • Global Roof Consultants Awarded Contract April
    25, 2006
  • Board Approved Delivery Methods
  • for Roof interior work May 23, 2006
  • Pre-Proposal Conference May 30, 2006
  • 8 Firms in attendance
  • Proposal Opening June 08, 2006
  • Received 3 proposals
  • Proposal Review June 08 June 20,
    2006
  • Award contract June 26, 2006

10
Elementary No. 7 Schedule Update
  • Gamma Construction Awarded Contract May 23, 2006
  • Pre-Construction Conference June 06, 2006
  • Mobilized on site June 07, 2006

11
Elementary No. 7 City of Deer Park Permit
Progress
Current Layout
12
(No Transcript)
13
Baseball Field Renovation Schedule Update
  • DD Presentation to LPISD May 23, 2006
  • 50 CD Review June 07, 2006
  • Contractor Recommendation July 25, 2006
  • Ready for Use January 2007

14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
In the next 60 days -
  • La Porte High School Renovations
  • Request Board Approval of Architect

Baker 6th Grade Maintenance Issue Request For
Qualifications (RFQ) for Engineering Services
Roofing Package Issue Request For Qualifications
(RFQ) for Roofing Consultant
18
Questions?