The SEEREN Initiative Extending the Network into SouthEast Europe WP3 Procurement and Network Design - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

The SEEREN Initiative Extending the Network into SouthEast Europe WP3 Procurement and Network Design

Description:

Negotiate connectivity contracts between GRNET and recommended suppliers ... Connectivity for the SEEREN beneficiary NRENs (AL, BA, BG, MK, YU) in the range ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 16
Provided by: see9
Category:

less

Transcript and Presenter's Notes

Title: The SEEREN Initiative Extending the Network into SouthEast Europe WP3 Procurement and Network Design


1
The SEEREN InitiativeExtending the Network into
South-East EuropeWP3 Procurement and Network
Design
  • David West
  • DANTE
  • David.West_at_dante.net, http//www.dante.net
  • Athens, November 4, 2003
  • 1st Technical Verification Meeting

2
WP3 Objectives
  • Agree procurement process
  • Prepare and issue procurement notice
  • Prepare and issue Invitation to Tender.
  • Hold Information Event for Suppliers
  • Confirm if equipment tender required
  • Clarify tender responses to ensure compliance and
    completeness. Identify areas for further
    information to be determined before or during
    interview stage
  • Hold meetings with compliant suppliers to further
    clarify and negotiate technical solution and
    commercial offers, possible short listing during
    this stage
  • Evaluate best offers and produce recommendations
    for SEEREN Steering Committee
  • Produce tender evaluation report for EC
  • Negotiate connectivity contracts between GRNET
    and recommended suppliers
  • Develop final network topology for approval by
    SEEREN Steering Committee

3
WP3 GANTT
  • contract

4
WP3 PERT
  • obsolete
  • obsolete

5
WP3 Resources
  • Evaluation Team
  • David West, Tryfon Chiotis, Octavian Rusu, Tamas
    Maray, Jorge-A. Sanchez-P
  • Budget for connectivity and equipment around 1M
    Euro

6
SEEREN Procurement Scope
  • Connectivity for the SEEREN beneficiary NRENs
    (AL, BA, BG, MK, YU) in the range of 2-34 Mbps
    via existing GÉANT PoPs in the area to GÉANT.
  • Completed, as detailed in following slides
  • SEEREN Network equipment
  • Preparatory stages completed, solution found
    through equipment donations
  • (see WP5)

GEANT PoP
Beneficiary SEEREN NREN
Targeted GEANT hosting NREN receiving node
GEANT hosting NREN and SEEREN contractor
Targeted beneficiary SEEREN NREN access node
GEANT hosting NREN and non-SEEREN contractor
7
Procurement Activities
Work Package 2 Market Analysis of Beneficiary
Needs and Market Conditions
Work Package 3 Connectivity Procurement
Activities
Contract Notice 7 February 16
March Invitation to Tender 17 March 11
April Information Day 26 March Evaluation
and Negotiations 12 April early
July Recommendations and Contracting early July
8 August
Work Package 4 Network Implementation and
Operation
8
Expressed InterestTenders Received
  • PanTel Rt.
  • In.life d.d.
  • Telekom Srbija a.d.
  • OTEGlobe
  • T-Systems International GmbH
  • TELEKOM AUSTRIA AG
  • GTS
  • Intelco Group
  • Worldcom
  • BH Telecom
  • VIVENDI Telecom Hungary rt.
  • Telekom CG
  • ASTRIUM
  • Romania Data Systems
  • Elektro-Slovenija, d.o.o.
  • ( BTC)

9
Connectivity Tender Process Review
  • Competing offers received for all countries,
    despite reliance on national operators
  • Evaluation conducted to ensure like for like
    comparisons and consistent treatment of tenderers
  • Securing affordable prices through commercial
    negotiations and political lobbying was a key
    issue
  • huge price variations
  • 2 Mbps 93 760k
  • 34 Mbps 340 1800k
  • 155Mbps 250 2700k
  • best total prices for required capacities
  • March 2m Euro
  • May 1.2m Euro
  • July 1.0M Euro

10
SEEREN Contracted Solution
  • Contracted with OTE (with 5 sub-contractors)
  • Uses MPLS technology
  • Cost 1.0M
  • Availability within 3 months max of order
  • Advantages
  • Capacities preferred by AL, BA, MK and YU, and
    acceptable to BG
  • Provides intra-SEEREN connectivity
  • Terrestrial connectivity for all SEEREN partners
  • Provides back up if Athens PoP fails
  • Network proactively managed
  • Consistent SLA
  • Simplified commercial interface for the
    coordinator
  • Can be funded within SEEREN project budget
  • Disadvantages
  • Relatively new technology (though commercially
    proven)
  • Reliance on single prime contractor

11
Best alternative available
  • Contracted with 3 service providers (with 3
    sub-contractors)
  • Uses leased circuit SDH technology for 3
    locations and satellite for 2 locations
  • Cost 1.06M
  • Availability within 1 - 3 months from order
  • Advantages
  • Proven Layer 2 technology for 3 locations
  • Provides the preferred international capacities
  • Disadvantages
  • No intra-SEEREN connectivity
  • No Back up capabilities
  • Satellite connectivity for AL and MK
  • Limited management capability
  • Considerable contractual overhead for the
    coordinator
  • Still slightly above SEEREN project budget
  • Variable SLA terms

12
SEEREN Network Design (physical)
13
SEEREN Network Design (logical)
14
SEEREN Network Design (logical)
15
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com