Title: The SEEREN Initiative Extending the Network into SouthEast Europe WP3 Procurement and Network Design
1The SEEREN InitiativeExtending the Network into
South-East EuropeWP3 Procurement and Network
Design
- David West
- DANTE
- David.West_at_dante.net, http//www.dante.net
- Athens, November 4, 2003
- 1st Technical Verification Meeting
2WP3 Objectives
- Agree procurement process
- Prepare and issue procurement notice
- Prepare and issue Invitation to Tender.
- Hold Information Event for Suppliers
- Confirm if equipment tender required
- Clarify tender responses to ensure compliance and
completeness. Identify areas for further
information to be determined before or during
interview stage - Hold meetings with compliant suppliers to further
clarify and negotiate technical solution and
commercial offers, possible short listing during
this stage - Evaluate best offers and produce recommendations
for SEEREN Steering Committee - Produce tender evaluation report for EC
- Negotiate connectivity contracts between GRNET
and recommended suppliers - Develop final network topology for approval by
SEEREN Steering Committee
3WP3 GANTT
4WP3 PERT
5WP3 Resources
- Evaluation Team
- David West, Tryfon Chiotis, Octavian Rusu, Tamas
Maray, Jorge-A. Sanchez-P - Budget for connectivity and equipment around 1M
Euro
6SEEREN Procurement Scope
- Connectivity for the SEEREN beneficiary NRENs
(AL, BA, BG, MK, YU) in the range of 2-34 Mbps
via existing GÉANT PoPs in the area to GÉANT. - Completed, as detailed in following slides
- SEEREN Network equipment
- Preparatory stages completed, solution found
through equipment donations - (see WP5)
GEANT PoP
Beneficiary SEEREN NREN
Targeted GEANT hosting NREN receiving node
GEANT hosting NREN and SEEREN contractor
Targeted beneficiary SEEREN NREN access node
GEANT hosting NREN and non-SEEREN contractor
7 Procurement Activities
Work Package 2 Market Analysis of Beneficiary
Needs and Market Conditions
Work Package 3 Connectivity Procurement
Activities
Contract Notice 7 February 16
March Invitation to Tender 17 March 11
April Information Day 26 March Evaluation
and Negotiations 12 April early
July Recommendations and Contracting early July
8 August
Work Package 4 Network Implementation and
Operation
8Expressed InterestTenders Received
- PanTel Rt.
- In.life d.d.
- Telekom Srbija a.d.
- OTEGlobe
- T-Systems International GmbH
- TELEKOM AUSTRIA AG
- GTS
- Intelco Group
- Worldcom
- BH Telecom
- VIVENDI Telecom Hungary rt.
- Telekom CG
- ASTRIUM
- Romania Data Systems
- Elektro-Slovenija, d.o.o.
- ( BTC)
9Connectivity Tender Process Review
- Competing offers received for all countries,
despite reliance on national operators - Evaluation conducted to ensure like for like
comparisons and consistent treatment of tenderers - Securing affordable prices through commercial
negotiations and political lobbying was a key
issue - huge price variations
- 2 Mbps 93 760k
- 34 Mbps 340 1800k
- 155Mbps 250 2700k
- best total prices for required capacities
- March 2m Euro
- May 1.2m Euro
- July 1.0M Euro
10SEEREN Contracted Solution
- Contracted with OTE (with 5 sub-contractors)
- Uses MPLS technology
- Cost 1.0M
- Availability within 3 months max of order
- Advantages
- Capacities preferred by AL, BA, MK and YU, and
acceptable to BG - Provides intra-SEEREN connectivity
- Terrestrial connectivity for all SEEREN partners
- Provides back up if Athens PoP fails
- Network proactively managed
- Consistent SLA
- Simplified commercial interface for the
coordinator - Can be funded within SEEREN project budget
- Disadvantages
- Relatively new technology (though commercially
proven) - Reliance on single prime contractor
11Best alternative available
- Contracted with 3 service providers (with 3
sub-contractors) - Uses leased circuit SDH technology for 3
locations and satellite for 2 locations - Cost 1.06M
- Availability within 1 - 3 months from order
- Advantages
- Proven Layer 2 technology for 3 locations
- Provides the preferred international capacities
- Disadvantages
- No intra-SEEREN connectivity
- No Back up capabilities
- Satellite connectivity for AL and MK
- Limited management capability
- Considerable contractual overhead for the
coordinator - Still slightly above SEEREN project budget
- Variable SLA terms
12SEEREN Network Design (physical)
13SEEREN Network Design (logical)
14SEEREN Network Design (logical)
15(No Transcript)